Question:
Spencerville Products is expanding its operations west of the Mississippi. Its first step is to build a manufacturing facility in Denver to satisfy demand on the West Coast. Spencerville has an option to build either a large facility that has an annual output of 500,000 units per year or a smaller facility with an output of 250,000 units per year. It must build one of these two facilities - it does not have any other options.
The expected demand for the company's products is shown as either high or moderate in the table below:
Demand Level Annual Demand (units/year) Probability
High 450,000 0.4
Moderate 150,000 0.6
The small facility has a profit of $5.00 per unit. The large facility has a profit of $4.00/unit.
a) What size facility should Spencerville Products build based on expected values and using a decision tree approach? You must also provide the decision tree using the appropriate decision tree symbols.
b) Suppose that the company is not certain about the 450,000 projection for the High Demand scenario. It could be higher than this projection. How sensitive is the selection in a) to the High Demand projection. In other words, at what annual demand for the High Demand scenario would the company be indifferent between the two size facilities?
Determining Degrees of Freedom One of the prerequisites for using chi square test is that we should calculate the number of degrees of freedom for the contingency table. T
Question 1 A) Differentiate among descriptive and inferential analysis of data B) Describe with examples various measures of Central Tendency Question 2 The chi-square
Higher Order Table When three or more characteristics are represented in the same table such a table is called higher order table. The need for such a table arises
A paper mill produces two grades of paper viz X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper in
cumulative discount factor
#Principles of OR
what is pert and cpm?
Maximize Z= 3x1 + 2X2 Subject to the constraints: X1+ X2 = 4 X1 - X2 = 2 X 1, X2 = 0
describe the similarities and differences of transportation and linear programing methods
use of game theory by state bank of india
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd