Question:
Spencerville Products is expanding its operations west of the Mississippi. Its first step is to build a manufacturing facility in Denver to satisfy demand on the West Coast. Spencerville has an option to build either a large facility that has an annual output of 500,000 units per year or a smaller facility with an output of 250,000 units per year. It must build one of these two facilities - it does not have any other options.
The expected demand for the company's products is shown as either high or moderate in the table below:
Demand Level Annual Demand (units/year) Probability
High 450,000 0.4
Moderate 150,000 0.6
The small facility has a profit of $5.00 per unit. The large facility has a profit of $4.00/unit.
a) What size facility should Spencerville Products build based on expected values and using a decision tree approach? You must also provide the decision tree using the appropriate decision tree symbols.
b) Suppose that the company is not certain about the 450,000 projection for the High Demand scenario. It could be higher than this projection. How sensitive is the selection in a) to the High Demand projection. In other words, at what annual demand for the High Demand scenario would the company be indifferent between the two size facilities?
#queSix Operators are to be assigned to five jobs with the cost of assignment in Rs. given in the matrix below. Determine the optimal assignment. Which operator will have no assign
A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper i
Techniques of Observation Method Observation always involves some interaction between respondent and researcher in which researcher has an opportunity to watch respondent fu
SIMO Chart Flow Diagram The flow diagram is a drawing indicating the paths of men materials or components on a scale plan of the work area, department or factory.
the following table gives place under different states of nature Strategies States of nature s1 s2 s3 A 10000 3000 2000 B
Question 1 Discuss the types of measurement scales used in research Question 2 Identify the various ways of selecting a random sample Question 3 Discuss five advan
Making Decision Lastly a decision should be arrived as to whether the null hypothesis is to be accepted or rejected. In this regard the value of the test statistic
types of OR ,technique and mathematical system and linear programming system in operation research
A paper mill products two grade of paper viz., X & Y. Because of raw material restriction, it cannot produce more than 400 tons of grade X paper & 300 tons of grade Y paper in a we
Show simple vapour compression Refrigeration cycle with showing all the devices and also draw T-sand P-R diagram and illustrate it also. A Bell-Coleman cycle works between 1 bar
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd