Data Warehousing Job Scheduling, Database Management System

Assignment Help:
1) Define a job scheduling strategy that will meet business requirement of reporting availability by 6am CST for the following cubes? Show the job scheduling dependencies in a pictorial form so that it is easy to understand.
a. Finance cube (3 hours to build)
b. Warranty cube (4 hours to build)
c. Order cube (2 hours to build)
d. Customer master data (30 min run time)
e. Vendor master data (60 min run time)
f. Product master data (60 min run time)
g. Other Master data (2 hour run time)
Finance and Order cubes cannot run together.

Related Discussions:- Data Warehousing Job Scheduling

Data storage and retrieval services, An Enterprising group of Entrepreneurs...

An Enterprising group of Entrepreneurs introduced a new business named StoreItRite which is based on data storage and retrieval services. It provides the services and the company c

Explain saving derived attributes to avoid re-computation, Saving Derived A...

Saving Derived Attributes to Avoid Re-computation   As discussed, "redundancy means duplication of exact data". But, if multiple copies of same data are present in the system,

Write a query to find name from the relational algebra, Consider the relati...

Consider the relations City (city_name, state) Hotel (name, address) City_hotel (hotel_name, city_name, owner) Answer the following queries in relational algebra (i) Find

Define the concept of generalization, Define the concept of generalization ...

Define the concept of generalization A generalization is relationship between specific kind of thing and general thing. It is also known as "is-a-kind-of" relationship. Inher

Cartisian product, Explain the cartesian product in Database Management Sys...

Explain the cartesian product in Database Management System

Modifyand removing a sequence-sequences, Modify a sequence: ALTER SEQU...

Modify a sequence: ALTER SEQUENCE SEQSS INCREMENT 2 MAXVALUE 3000;   Removing a sequence: DROP SEQUENCE SEQSS;

Describe the algorithm to draw the dependency graph, Describe the algorithm...

Describe the algorithm to draw the dependency graph?   Ans: Algorithm to draw Precedence Graph is like this: a.  For every transaction T i participating in schedule S, make

Datawarehouse, Explain four causes for failures in data warehouse projects

Explain four causes for failures in data warehouse projects

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd