Data Warehousing Job Scheduling, Computer Engineering

Assignment Help:
1) Define a job scheduling strategy that will meet business requirement of reporting availability by 6am CST for the following cubes? Show the job scheduling dependencies in a pictorial form so that it is easy to understand.
a. Finance cube (3 hours to build)
b. Warranty cube (4 hours to build)
c. Order cube (2 hours to build)
d. Customer master data (30 min run time)
e. Vendor master data (60 min run time)
f. Product master data (60 min run time)
g. Other Master data (2 hour run time)
Finance and Order cubes cannot run together.

Related Discussions:- Data Warehousing Job Scheduling

Bubbling the pipeline - computer architecture, Bubbling the Pipeline: B...

Bubbling the Pipeline: Bubbling the pipeline (also known as a pipeline break or pipeline stall) is a technique for preventing, structural, data and branch hazards from taking p

Need of cisc cpu - computer architecture, Need of CISC CPU -  computer arc...

Need of CISC CPU -  computer architecture: Why is Intel spending money and time to manufacture the Pentium II and the Pentium III? The answer of this question is simple, ba

Explain the use of wire-center have any influence, Does the use of wire-cen...

Does the use of wire-center have any influence on the performance of a token ring? Explain. One problem along with a ring network is as if the cable breaks somewhere, the ring

Determine in brief about laptop computers, Laptop computers Laptop comp...

Laptop computers Laptop computers have the obvious advantage over desk-top computers (PCs) in that they are fully portable. This is of specific value if a user wishes to do wor

Define interrupts, Interrupts are signals which cause the CPU to suspend th...

Interrupts are signals which cause the CPU to suspend the currently executing program and transfer to a special program known as an interrupt handler. Interrupt handler determines

Convert hexadecimal bch to decimal number, Convert hexadecimal BCH to decim...

Convert hexadecimal BCH to decimal of form 0100 1000. Converting the hexadecimal BCH to decimal number firstly convert given number into two's compliment that is: 0100100

Define a formal system, Q. Define a Formal System? A Formal System is o...

Q. Define a Formal System? A Formal System is one which is planned in advance and is used according to schedule. In this system procedures and policies are documented well in a

What are latches and flipflops, What are latches and flipflops? There a...

What are latches and flipflops? There are two types of circuits as follows: a. Combinational b. Sequential Flipflops and latches both come into the category of "sequen

Explain wait for graph-resource request and allocation graph, Explain Wait ...

Explain Wait for graph (WFG) with Resource request and allocation graph (RRAG). WFG with RRAG: A graph G = (V,E) is termed as bipartite if V can be decomposed in two

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd