Data Warehousing Job Scheduling, Computer Engineering

Assignment Help:
1) Define a job scheduling strategy that will meet business requirement of reporting availability by 6am CST for the following cubes? Show the job scheduling dependencies in a pictorial form so that it is easy to understand.
a. Finance cube (3 hours to build)
b. Warranty cube (4 hours to build)
c. Order cube (2 hours to build)
d. Customer master data (30 min run time)
e. Vendor master data (60 min run time)
f. Product master data (60 min run time)
g. Other Master data (2 hour run time)
Finance and Order cubes cannot run together.

Related Discussions:- Data Warehousing Job Scheduling

Script in multi user mode, What Component of LoadRunner would you use to pl...

What Component of LoadRunner would you use to play Back the script in multi user mode? Ans) The Controller component is used to playback the script in multi-user mode. This is c

Software project planning, Software Project Planning In the previous da...

Software Project Planning In the previous days of computing software costs comprised a small % of overall computer based system cost. In order of magnitude error software cost

Explain frequency division multiplexing, Explain FDM and show how CCITT sta...

Explain FDM and show how CCITT standards help in building the base band? Frequency Division Multiplexing: This is the process of combining some information channels through s

Sdr, advantages of sdr

advantages of sdr

What does not use by FTP, FTP does not use ? FTP doesn't use User Datag...

FTP does not use ? FTP doesn't use User Datagram Protocol.

Pipeline architecture, Explain detailed classification of pipelined process...

Explain detailed classification of pipelined processor.

Difference between perl and mod_perl, Perl is a language and MOD_PERL is a ...

Perl is a language and MOD_PERL is a module of Apache used to increase the performance of the application.

Colour management, There are three primary colours in pigments - Red, Yello...

There are three primary colours in pigments - Red, Yellow and Blue. There are two ways to produce more colours:   Physical Mixing: Physically mix colours to produce a new colour

What is delayed branching, What is delayed branching? A method called d...

What is delayed branching? A method called delayed branching can minimize the penalty incurred as a result of conditional branch instructions. The idea is easy. The instruction

How to reduce the maximum quantization error, In successive-approximation A...

In successive-approximation A/D converter, offset voltage equal to 1/2 LSB is added to the D/A converter's output. This is done to ? Ans. It is done to reduce the maximum quantiz

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd