#queDefine a job scheduling strategy that will meet business requirement of reporting availability by 6am CST for the following cubes? Show the job scheduling dependencies in a pictorial form so that it is easy to understand.
a. Finance cube (3 hours to build)
b. Warranty cube (4 hours to build)
c. Order cube (2 hours to build)
d. Customer master data (30 min run time)
e. Vendor master data (60 min run time)
f. Product master data (60 min run time)
g. Other Master data (2 hour run time)
Finance and Order cubes cannot run togetherstion..

Related Discussions:- data warehouse

Nested relational model, what is Nested relational model? Explain with exam...

what is Nested relational model? Explain with examples.

Create a classification model, Use again the GE Flight Quest Data and build...

Use again the GE Flight Quest Data and build on the work done for homework 1 and 2. The goal is to create a classification model which classifies flights into "on-time" (you can de

In case of entity integrity the primary key may be declared, In case of ent...

In case of entity integrity, the primary key may be declared? In a case of entity integrity primary key may be not Null.

Describe disk manager and their work, Describe disk manager and their work?...

Describe disk manager and their work? Disk Manager: Responsible for fetching data regulated through file Manager from disk storage within Main memory and deciding what data to

Discuss difference between drop table r and delete from r, Discuss The diff...

Discuss The difference between drop table R and delete from R.  DROP TABLE command deletes all the records with the table definition. This command will automatically committed

What is the use of integrity constraints, What is the use of integrity cons...

What is the use of integrity constraints? Integrity constraints make sure that changes made to the database by authorized users do not result in a loss of data consistency. The

DW, #ques Define a job scheduling strategy that will meet business requirem...

#ques Define a job scheduling strategy that will meet business requirement of reporting availability by 6am CST for the following cubes? Show the job scheduling dependencies in a p

Entity relationship, how to write tables and drow E-R diagrams for hosiptal...

how to write tables and drow E-R diagrams for hosiptal management system and how to normalize and cardinalities?

Describe the algorithm to draw the dependency graph, Describe the algorithm...

Describe the algorithm to draw the dependency graph?   Ans: Algorithm to draw Precedence Graph is like this: a.  For every transaction T i participating in schedule S, make

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd