data warehouse, Database Management System

Assignment Help:
#queDefine a job scheduling strategy that will meet business requirement of reporting availability by 6am CST for the following cubes? Show the job scheduling dependencies in a pictorial form so that it is easy to understand.
a. Finance cube (3 hours to build)
b. Warranty cube (4 hours to build)
c. Order cube (2 hours to build)
d. Customer master data (30 min run time)
e. Vendor master data (60 min run time)
f. Product master data (60 min run time)
g. Other Master data (2 hour run time)
Finance and Order cubes cannot run togetherstion..

Related Discussions:- data warehouse

Er diatgrams, Ask q“A database will be made to store information about pati...

Ask q“A database will be made to store information about patients in a hospital. On arrival, each patient’s personal details (name, address, and telephone number) are recorded wher

Relational schema, crete a data base relationship model Entity: ...

crete a data base relationship model Entity: Students; Professors; Dormitories buildings; Attributes of students: Name; Address; Dorm;

What is nested trigger, What is Nested Trigger? A trigger can also havi...

What is Nested Trigger? A trigger can also having INSERT, UPDATE and DELETE logic within itself, so when the trigger is fired because of data modification it can also cause ano

A database administrator'', A database administrator''s responsibilities an...

A database administrator''s responsibilities and data contents

Define a property that is not a property of transactions, Define a property...

Define a property that is not a property of transactions? Ans: Concurrency is not a property of transactions

Er schema can be represented by relation schemas , Q. Describe how an ER sc...

Q. Describe how an ER schema can be represented by relation schemas and constraints arising from ER design can be mapped to constraints on a relation schema.     The entity rela

Assign, #quesDefine a job scheduling strategy that will meet business requi...

#quesDefine a job scheduling strategy that will meet business requirement of reporting availability by 6am CST for the following cubes? Show the job scheduling dependencies in a pi

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd