Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
Cycle time and Assign work elements and Delete the assigned elements
A task having 12 work elements and their logical relationship and time ( in Seconds ) taken is given in the table below.
Cycle Time: Select a feasible cycle time (CT). By a feasible time mean one for which TMax > CT > ∑Ti.Work Assignment: Assign work elements to the station , such that the sum of elemental times at a station does not exceed the cycle time C T. This assignment proceeds from column I to II and so on braking intra column ties using the criterion of minimum number of predecessors.Deletion: Delete the assigned elements from the total number of work element and repeat the above step until all the element are assigned.Assignment to next station: If the station time exceeds the cycle time due to the inclusion of a certain work element this work element should be assigned to the next station.
Repeat all above steps except first until all elements are assigned to work stations.
Figure: precedence diagram with colums
Q. What level of project management do I need? A. This is a complicated question to answer for the reason that it very much depends on the size duration and technical complex
Question: There is a cycle associated with the life of a project. This runs from the commencement to the completion of the project with authority being required for both the co
Question 1: Describe the need for manpower planning Define Manpower planning. Need for manpower planning Question 2: Show the benefits of carrying out manpo
The Board of FF Supermarket is examining the company's current market position. As part of the review, the Board has asked for an analysis of industry competition to be undertaken
M a t r i x organisation A matrix organisation is a combination of functional and project organisation. A weak matrix organisation has most of the characteristics of a fun
1. Objective ( Theme ) : Continuous quality improvement at every level at every place and at every stage. 2. Approach :Management involvement and leadership, Empowering s
Q. How do I organize and apply resources? A. The first moreover most important step in the implementation phase is to re-visit the project plan (or the project brief) and to
Question 1: What do you mean by crash duration? Explain the Time-Cost Optimization algorithm crash duration/crash time - explanation including figures Steps of Time-C
Strategy is developed at different levels in large organisations. The process starts with the corporate strategy which is then translated into the strategy for the business divisio
what are the major problem in ground breaking project
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd