Cycle time,work assignment,deletion and assignment, Project Management

Assignment Help:

Cycle time and Assign work elements and Delete the assigned elements

A task having 12 work elements and their logical relationship and time ( in Seconds ) taken is given in the table below.

2339_Precedence Diagram and Identify the Element.png

Cycle Time: Select a feasible cycle time (CT). By a feasible time mean one for which TMax > CT > ∑Ti.
Work Assignment: Assign work elements to the station , such that the sum of elemental times at a station does not exceed the cycle time C T. This assignment proceeds from column I to II and so on braking intra column ties using the criterion of minimum number of predecessors.

Deletion: Delete the assigned elements from the total number of work element and repeat the above step until all the element are assigned.

Assignment to next station: If the station time exceeds the cycle time due to the inclusion of a certain work element this work element should be assigned to the next station.

Repeat all above steps except first until all elements are assigned to work stations.

2339_Cycle Time,Work Assignment,Deletion and Assignment.png

Figure: precedence diagram with colums


Related Discussions:- Cycle time,work assignment,deletion and assignment

Concept of project risk audit , Define the Concept of Project Risk Audit  ...

Define the Concept of Project Risk Audit  Audit can be defined as an evaluation of a person, organisation, system, process, enterprise, project or product. Quality risk audit i

Project Planning Appraisal and Control, 2. Why Conflicts arise between two ...

2. Why Conflicts arise between two or more mutually exclusive projects? Analyse the situations where conflicts may arise and suggest how these conflicts can be resolved.

Responsibilities of an event manager, Question 1: a) Outline the key r...

Question 1: a) Outline the key responsibilities of an Event Manager b) Give THREE clear working examples of possible event objectives for either a country, a resort, an or

Why do projects always seem to cost more than expected, Q. Why do projects ...

Q. Why do projects always seem to cost more than expected? In general this seems to stem from three causes. The first may merely be an overly optimistic cost estimate. Sometime

Determine development lifecycles appropriate for project, You have been ask...

You have been asked to acquire charge of a system growth where the customer needs about fifty per cent of the functionality very immediately to meet a business opportunity but wher

What is the purpose of the post completion review, What is the purpose of t...

What is the purpose of the post completion review? The purpose of a PC (post completion) review: • Assist continuous improvement for example review procedures to design bett

Cost of quality, Cost of Quality In    spite    of   the    number    o...

Cost of Quality In    spite    of   the    number    of   definitions    available    for   quality    much misunderstanding exists about quality. Some of the misunderstandings

"simultaneous loose?tight" by Peters, Discuss the concept of "simultaneous ...

Discuss the concept of "simultaneous loose?tight" by Peters and Waterman

Numerical problems, Hi, I need help in learning and solving 20 questions n...

Hi, I need help in learning and solving 20 questions numerical which involves PM techniques from selection, planning, execution and controlling techniques. I want to know how can

Role and nature of estimation in project management, Question: (a) Th...

Question: (a) The Local Government Service Commission has advertised a post of "CLERK" on the L'Express newspaper on the April 1, 2004. The closing date for the submissio

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd