Cycle time,work assignment,deletion and assignment, Project Management

Assignment Help:

Cycle time and Assign work elements and Delete the assigned elements

A task having 12 work elements and their logical relationship and time ( in Seconds ) taken is given in the table below.

2339_Precedence Diagram and Identify the Element.png

Cycle Time: Select a feasible cycle time (CT). By a feasible time mean one for which TMax > CT > ∑Ti.
Work Assignment: Assign work elements to the station , such that the sum of elemental times at a station does not exceed the cycle time C T. This assignment proceeds from column I to II and so on braking intra column ties using the criterion of minimum number of predecessors.

Deletion: Delete the assigned elements from the total number of work element and repeat the above step until all the element are assigned.

Assignment to next station: If the station time exceeds the cycle time due to the inclusion of a certain work element this work element should be assigned to the next station.

Repeat all above steps except first until all elements are assigned to work stations.

2339_Cycle Time,Work Assignment,Deletion and Assignment.png

Figure: precedence diagram with colums


Related Discussions:- Cycle time,work assignment,deletion and assignment

Develop a integrated management project, You are not expected to submit a f...

You are not expected to submit a formal proposal. However, you will be able to access Subject Tutors via HenleyConnect and you may seek feedback from them as to the suitability and

Lack of specialized supervision, Lack of Specialized Supervision There...

Lack of Specialized Supervision There will be greater difficulty in securing specialized supervision. Because line layout consists of several machines requiring a wide range o

Unit rate contracts , Unit rate contracts  In a unit-rate contract, the...

Unit rate contracts  In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item. Engineered m

Advantages and disadvantages of a matrix project structure, C Consultancy C...

C Consultancy Company gives management consultancy to a range of organisations.  It employs staff who have dissimilar industry backgrounds and who also offer dissimilar specialisms

What is the estimated cost of the whole project, Question 1: (a) Using...

Question 1: (a) Using information from Table 1, build a network diagram for the project. (b) Perform a Forward Pass on the network diagram and deduce the duration of the p

Show idea screening in process of development, Q. Show Idea Screening in Pr...

Q. Show Idea Screening in Process of development? Idea screening involves the acceptance of formulation of the idea by doing cause and effect analysis. This stage usually ident

Case Study, Develop a work breakdown structure. 3. Make a list of the speci...

Develop a work breakdown structure. 3. Make a list of the specific activities that need to be done between now and the wedding day. 4. For each activity, identify the person (Tony,

Objectives of materials management, Objectives  of Materials Management: ...

Objectives  of Materials Management: 1. Low  prices: Obtaining  the least possible  price  for purchased materials is the  most  obvious  purchasing  objectives and certai

Matrix organisation structure, M a t r i x organisation A matrix o...

M a t r i x organisation A matrix organisation is a combination of functional and project organisation. A weak matrix organisation has most of the characteristics of a fun

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd