Cost-volume relationship, Civil Engineering

Assignment Help:

Cost-volume relationship:

Cost-volume relationship is illustrated through a simple example dealing with the cost of operating an automobile. To perform the analysis following cost regarding owning and operating an automobile is supposed.

2307_Cost-volume relationship.png

388_Cost-volume relationship1.png

Figure: Cost Volume Relationship

The cost-volume-relationship may be expressed graphically. The relation among volume (miles per year) and different type of costs (that means. fixed, variable and semi variable) is illustrated in Figure

The estimated automobile cost per annum for any assumed mileage may be determined from the graph of total cost. For instance, to drive 10,000 km in a given year a total cost of Rs. 41800 or Rs. 4.18 per km is estimated. By combining all of the fixed and variable elements of the cost, the cost of owning an automobile can be estimated as Rs.11800 per year plus Rs. 3 per km driven during the year.

The effect of volume on unit (per km) costs may be calculated through the conversion of net costs into average costs as described below:

Cost per Mile of Owning and Using an Automobile

 

Miles driven                                    5,000          10,000         15,000            20,000

Costs:                                      

Completely variable (Rs. 2Per km)   10,000                   20,000        30,000           40,000

Semi variable:                                    

Variable part (Rs.1 per km)             5,000         10,000         15,000         20,000

Fixed part                                      10,000    10,000          10,000            10,000

Fixed Costs (1500 + 300)                1,800          1,800                1,800         1,800

Total Costs                                    25,800           41,800       56,800    71,800

Cost per km                                  5.16            4.18                3.78         3.59

From the aforementioned analysis it may be seen that the variable portion of the costs raise with the increase in volume but the rate of change in variable cost remains constant. On the other hand fixed costs remains constant with changes in distances traversed but reduce on a per km basis as number of kilometers increase.


Related Discussions:- Cost-volume relationship

Illustrate shaft grouting for friction barrettes, Q. Illustrate Shaft grout...

Q. Illustrate Shaft grouting for friction barrettes? For the construction of friction barrettes, some grout pipes are designed at periphery of the barrettes. Within a short dur

3-d stress, If the resultant forces are resolved in the three co-ordinate d...

If the resultant forces are resolved in the three co-ordinate directions and divided by the area of the face of the cube we have the general state of 3-dimensional stress as shown.

Embankment, Describe the various steps in embankment construction.

Describe the various steps in embankment construction.

Show the application of concrete crash barriers, Q. Show the application of...

Q. Show the application of Concrete crash barriers? Concrete crash barriers aren't considered as the best barrier design due to the following reasons when compared with flexibl

Scheming thermal reinforcement, Question What is importance of critical...

Question What is importance of critical steel ratio in scheming thermal reinforcement ? Answer Execution of critical steel ratio resources that in construction joints,

State the term- friction in tendon, State the term- friction in tendon ...

State the term- friction in tendon Considerable frictional loss takes place due to friction between the tendon and the material surrounding it, namely the concrete or the sheat

Premix carpet open graded, what is premix carpet open graded and where is i...

what is premix carpet open graded and where is it used and what are its limitations ?

R.c.c, solution of point of contraflexure

solution of point of contraflexure

Distomat., write a note on distomat

write a note on distomat

Define the shock transmission unit, Define the Shock Transmission Unit? ...

Define the Shock Transmission Unit? Ever since engineers have started designing multi span simply supported bridges, they have been dreaming of connecting all the spans togethe

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd