Cost-volume relationship, Civil Engineering

Assignment Help:

Cost-volume relationship:

Cost-volume relationship is illustrated through a simple example dealing with the cost of operating an automobile. To perform the analysis following cost regarding owning and operating an automobile is supposed.

2307_Cost-volume relationship.png

388_Cost-volume relationship1.png

Figure: Cost Volume Relationship

The cost-volume-relationship may be expressed graphically. The relation among volume (miles per year) and different type of costs (that means. fixed, variable and semi variable) is illustrated in Figure

The estimated automobile cost per annum for any assumed mileage may be determined from the graph of total cost. For instance, to drive 10,000 km in a given year a total cost of Rs. 41800 or Rs. 4.18 per km is estimated. By combining all of the fixed and variable elements of the cost, the cost of owning an automobile can be estimated as Rs.11800 per year plus Rs. 3 per km driven during the year.

The effect of volume on unit (per km) costs may be calculated through the conversion of net costs into average costs as described below:

Cost per Mile of Owning and Using an Automobile

 

Miles driven                                    5,000          10,000         15,000            20,000

Costs:                                      

Completely variable (Rs. 2Per km)   10,000                   20,000        30,000           40,000

Semi variable:                                    

Variable part (Rs.1 per km)             5,000         10,000         15,000         20,000

Fixed part                                      10,000    10,000          10,000            10,000

Fixed Costs (1500 + 300)                1,800          1,800                1,800         1,800

Total Costs                                    25,800           41,800       56,800    71,800

Cost per km                                  5.16            4.18                3.78         3.59

From the aforementioned analysis it may be seen that the variable portion of the costs raise with the increase in volume but the rate of change in variable cost remains constant. On the other hand fixed costs remains constant with changes in distances traversed but reduce on a per km basis as number of kilometers increase.


Related Discussions:- Cost-volume relationship

Which direction of reinforcement must be provided, Question In the desi...

Question In the designing of a simply supported skew bridge , which direction of reinforcement must be provided? Answer In conventional design of steel reinforcement f

Show the benefits of adopting marine fill, In reclamation involving large v...

In reclamation involving large volumes of fill and tight programme, shall engineers use marine fill or mud extracted from land borrow area as filling material?  There are two

Glazed tiles for construction material, Q. Glazed tiles for Construction Ma...

Q. Glazed tiles for Construction Material? Glazed tiles are only meant for dadoes of bath room, Toilet and kitchens etc as they have no strength . Normally 8'' x 4'' g

Brigdes, infomation about differnt brigdes

infomation about differnt brigdes

Define steel substructure - underwater inspection of bridge, Define Steel s...

Define Steel substructure - underwater inspection of bridge? Steel is used as a structural material and as external protective cladding on concrete foundation elements. Steel f

Forensic structural engineering, i need journals or articles of forensic st...

i need journals or articles of forensic structural engineering

Mixed ground with soils and boulders, Ground settlement occurs when pipe-ja...

Ground settlement occurs when pipe-jacking machine enters mixed ground with soils and boulders? The rate of cutting through soils is faster than cutting through boulders for pi

WBM Road, if the WBM Road is constructed with 80mm , 40mm metal what will b...

if the WBM Road is constructed with 80mm , 40mm metal what will be the depreciation factor per year, how much thickness of the layer will be reduced per year due to trafic and rai

Surveying, description of instruments used transfer upper floors *plumb-bob...

description of instruments used transfer upper floors *plumb-bob method *theodolite method *theodolite and target method *optical plumbing method

#frames, confusion on shear force diagram, bending moment diagram

confusion on shear force diagram, bending moment diagram

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd