Cost variance and schedule variance, Cost Accounting

Assignment Help:

(i) In terms of cashflow, which month will be the most costly for your project?

(ii) If the 3rd and 4th months are more expensive by 25% each because the outsourced labour took longer than expected, what is the effect on the final predicted project cost? What action do you think you could take in these circumstances? 

3(c) Assume you have completed three months of the project. The Budget at Completion (BAC) was $250,000 for this six-month project. Also assume the following:

Planned Value (PV) = $150,000

Earned Value (EV) = $140,000

Actual Cost (AC) = $125,000  

2343_Cost variance and schedule variance.png

Use this information to answer the following questions.

(i) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

(ii) Use the CPI to calculate the estimate at completion (EAC) for this project. Use the SPI to estimate how long it will take to finish this project. Sketch an earned value chart using the above information, including the EAC point. Use the chart below (Figure 7-5, p.289 in Schwalbe 5ed) as an example of what your Earned Value Chart should look like. Comment on your chart.

(iii) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Should you alert POSS senior management and ask for assistance?


Related Discussions:- Cost variance and schedule variance

Specific order costing, Specific Order Costing This is a broad costing...

Specific Order Costing This is a broad costing system that is applicable where work jobs consist of separate jobs, batches or contracts.  Every job or contract or batch is a c

Advantages and disadvantages of group bonus plan, Advantages and Disadvanta...

Advantages and Disadvantages of Group Bonus Plan Benefits associated along with group bonus schemes involve i. It encourages teamwork and cooperation among workers ii.

Identify the relevant per-unit costs, Bakers Bagels LLC produces and sells ...

Bakers Bagels LLC produces and sells 20 types of bagels by the dozen. Bagels are priced at $6.00 per dozen (or $0.50 each) and cost $.020 per unit to produce. The company is consid

Determine the internal rate of return, AOL is considering two proposals to ...

AOL is considering two proposals to overhaul its network infrastructure. They have received two bids. The first bid, from Huawei, will require a $20 million upfront investment and

Which of the following are relevant in choosing, A company is considering t...

A company is considering the following alternatives: Alternative 1 Alternative 2 Revenues $240,000 240,000 Variable costs 120,000 140,000 Fixed costs 70,000 70,000 Which of the fol

Cost sheet, 10% of the finished castings were to be defective in manufactur...

10% of the finished castings were to be defective in manufacture and were rectified by expenditure of additional works overhead charges to the extent of 20% on the proportionate di

Timing of cashflows, The time of cashflows for the project are as follows; ...

The time of cashflows for the project are as follows; Operating Income (rent) is received annually, in advance. For NPV purposes they are assumed to have been received at th

Homework, i need help on my homework

i need help on my homework

Calculated the net working capital, Balance Sheet                      ...

Balance Sheet                                                                      2010                2011             Assets Cash

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd