Cost variance and schedule variance, Cost Accounting

Assignment Help:

(i) In terms of cashflow, which month will be the most costly for your project?

(ii) If the 3rd and 4th months are more expensive by 25% each because the outsourced labour took longer than expected, what is the effect on the final predicted project cost? What action do you think you could take in these circumstances? 

3(c) Assume you have completed three months of the project. The Budget at Completion (BAC) was $250,000 for this six-month project. Also assume the following:

Planned Value (PV) = $150,000

Earned Value (EV) = $140,000

Actual Cost (AC) = $125,000  

2343_Cost variance and schedule variance.png

Use this information to answer the following questions.

(i) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

(ii) Use the CPI to calculate the estimate at completion (EAC) for this project. Use the SPI to estimate how long it will take to finish this project. Sketch an earned value chart using the above information, including the EAC point. Use the chart below (Figure 7-5, p.289 in Schwalbe 5ed) as an example of what your Earned Value Chart should look like. Comment on your chart.

(iii) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Should you alert POSS senior management and ask for assistance?


Related Discussions:- Cost variance and schedule variance

Calculate the amount of interest capitalized for the year, A company constr...

A company constructs a building for its own use. Construction began on January 1 and ended on December 30. The expenditures for construction were as follows: January 1, $550,000; M

Prepare cost sheet, The Pacific Manufacturing Company operates a job-order ...

The Pacific Manufacturing Company operates a job-order costing system and applies overhead cost to jobs on the basis of direct labor cost. Its predetermined overhead rate was based

Trypanosoma, Place a prepared slide of Trypunosoma under tlic microscope an...

Place a prepared slide of Trypunosoma under tlic microscope and focus it under low power, You will observe large number of tiny spindle-shaped trypanosomes lying in the plasma alll

What is the predetermined overhead rate, Morrow Company applies overhead ba...

Morrow Company applies overhead based on direct labor hours. At the beginning of the year, Morrow estimates overhead to be $620,000, machine hours to be 180,000, and direct labor h

The weaknesses of an incremental budgeting system, Traditional budgeting  s...

Traditional budgeting  systems are  incremental  in nature and  tend  to  focus on  cost  centres.  Activity-based  budgeting  links  business  planning  to  the  budgeting  proces

prepare a simple balance sheet, Assume that Banc One receives a primary de...

Assume that Banc One receives a primary deposit of $1 million. The bank must keep reserves of 20 percent against its deposits. Prepare a simple balance sheet of assets and liabilit

EXPECTED CASH COLLECTIONS, WORKED EXAMPLES OF EXPECTED CASH COLLECTIONS PAT...

WORKED EXAMPLES OF EXPECTED CASH COLLECTIONS PATTERNS

introduction of internal rate of return , Introduction of Internal Rate of...

Introduction of Internal Rate of Return The traditional internal rate of return (IRR) method of project selection has been shown to be inferior to the NPV method due to vario

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd