Cost variance and schedule variance, Cost Accounting

Assignment Help:

(i) In terms of cashflow, which month will be the most costly for your project?

(ii) If the 3rd and 4th months are more expensive by 25% each because the outsourced labour took longer than expected, what is the effect on the final predicted project cost? What action do you think you could take in these circumstances? 

3(c) Assume you have completed three months of the project. The Budget at Completion (BAC) was $250,000 for this six-month project. Also assume the following:

Planned Value (PV) = $150,000

Earned Value (EV) = $140,000

Actual Cost (AC) = $125,000  

2343_Cost variance and schedule variance.png

Use this information to answer the following questions.

(i) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

(ii) Use the CPI to calculate the estimate at completion (EAC) for this project. Use the SPI to estimate how long it will take to finish this project. Sketch an earned value chart using the above information, including the EAC point. Use the chart below (Figure 7-5, p.289 in Schwalbe 5ed) as an example of what your Earned Value Chart should look like. Comment on your chart.

(iii) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Should you alert POSS senior management and ask for assistance?


Related Discussions:- Cost variance and schedule variance

Determine firms short run cost curve, Q. A firm uses capital and labor to p...

Q. A firm uses capital and labor to produce a single output good. The production function is given by F(K, L) = K 2 L where K is the amount of capital and L is the amount of labo

Prepare a complete cash flow statement of a company, Listed below are some ...

Listed below are some balances of XYZ, Inc as of and for the year ended December 31, 2012 and 2013 Year ending 12/31/13   Reven

Calculate average cost and marginal cost, Farmer Dorr figures that her fixe...

Farmer Dorr figures that her fixed costs are $2,000, and the relevant portion of her total cost curve is:                                           Thousands of

Difference, difference between diffrential cost and marginal cost

difference between diffrential cost and marginal cost

Direct material cost variances (dmcv), Direct Material Cost Variances (DMCV...

Direct Material Cost Variances (DMCV) This variance is a general difference in the standard direct material cost and the actual direct material cost. This variance may be prese

Explanation of sales revenue line, The sales revenue line demonstrates the ...

The sales revenue line demonstrates the amount of sales earned throughout the different level of activities. It can be observed that between zero and somewhere between activity B a

Cost estimation methods, using the high low method how do i calculate the c...

using the high low method how do i calculate the costs that are expected when the output expected is out of the range given for example cost prdctn volume 110000

Cost and budget, Frame-it Ltd is a manufacturer of metal picture frames. Th...

Frame-it Ltd is a manufacturer of metal picture frames. The firm's two product lines are designate S (small frames: 12 x18 cm) and L (large frames: 20 x 25 cm). The primary raw mat

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd