Cost variance and schedule variance, Cost Accounting

Assignment Help:

(i) In terms of cashflow, which month will be the most costly for your project?

(ii) If the 3rd and 4th months are more expensive by 25% each because the outsourced labour took longer than expected, what is the effect on the final predicted project cost? What action do you think you could take in these circumstances? 

3(c) Assume you have completed three months of the project. The Budget at Completion (BAC) was $250,000 for this six-month project. Also assume the following:

Planned Value (PV) = $150,000

Earned Value (EV) = $140,000

Actual Cost (AC) = $125,000  

2343_Cost variance and schedule variance.png

Use this information to answer the following questions.

(i) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

(ii) Use the CPI to calculate the estimate at completion (EAC) for this project. Use the SPI to estimate how long it will take to finish this project. Sketch an earned value chart using the above information, including the EAC point. Use the chart below (Figure 7-5, p.289 in Schwalbe 5ed) as an example of what your Earned Value Chart should look like. Comment on your chart.

(iii) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Should you alert POSS senior management and ask for assistance?


Related Discussions:- Cost variance and schedule variance

cost classification, Explain the value attached to this common exercise un...

Explain the value attached to this common exercise undertaken by Accountants.

What will be their allocated overhead?, Tyler's Consulting Company has purc...

Tyler's Consulting Company has purchased a new $15,000 copier. This overhead cost will be shared by the purchasing, accounting, and information technology departments since those a

Compute avoidable interest incurred during 2014, Early in 2014, Dobbs Corpo...

Early in 2014, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2014 and

Investment, under which type of asset the investment comes

under which type of asset the investment comes

Find out overhead application rate, Find Out Overhead Application Rate ...

Find Out Overhead Application Rate The given is the budget of Superb Engineering Works for the 2002 year Factory overheads Kshs 62,000

Budget Presentation for Management, 1) Please elaborate on the attached per...

1) Please elaborate on the attached performance report by preparing a presentation to "management" which incorporates the information presented in the performance report. Present t

Calculate direct materials used, Advertising expense $17,200 Wages expense-...

Advertising expense $17,200 Wages expense-assemblers 36,840 Depreciation expense-machines 21,480 Utilities expense-factory 21,120 Wages expense-lathe operators 23,480 Repair expens

Calculate the reduction in failure costs per unit, Each unit of a product r...

Each unit of a product requires four components. The average number of components is 4.25 due to component failure. Purchasing higher quality components can reduce the average numb

Explanation of total cost line, Total costs include both variable costs and...

Total costs include both variable costs and fixed costs. Variable costs are costs which can beeasily identified or related to a cost per unit or activity level of some kind for exa

Marginal costing, MARGINAL COSTING As per the Chartered Institute of Ma...

MARGINAL COSTING As per the Chartered Institute of Management Accountants, London, the phrase 'Marginal cost' means - 'the amount at every given volume of output through which

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd