Cost variance and schedule variance, Cost Accounting

Assignment Help:

(i) In terms of cashflow, which month will be the most costly for your project?

(ii) If the 3rd and 4th months are more expensive by 25% each because the outsourced labour took longer than expected, what is the effect on the final predicted project cost? What action do you think you could take in these circumstances? 

3(c) Assume you have completed three months of the project. The Budget at Completion (BAC) was $250,000 for this six-month project. Also assume the following:

Planned Value (PV) = $150,000

Earned Value (EV) = $140,000

Actual Cost (AC) = $125,000  

2343_Cost variance and schedule variance.png

Use this information to answer the following questions.

(i) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

(ii) Use the CPI to calculate the estimate at completion (EAC) for this project. Use the SPI to estimate how long it will take to finish this project. Sketch an earned value chart using the above information, including the EAC point. Use the chart below (Figure 7-5, p.289 in Schwalbe 5ed) as an example of what your Earned Value Chart should look like. Comment on your chart.

(iii) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Should you alert POSS senior management and ask for assistance?


Related Discussions:- Cost variance and schedule variance

Important aspect regarding to service cost centres, Important Aspect Regard...

Important Aspect Regarding to Service Cost Centres The basis selected should be one that is judged to be the mainly equitable way of sharing the service costs of department

Current funding availability, 1. The Initial Borrowings required are determ...

1. The Initial Borrowings required are determined by the amount required to start  the project less the Cash Invested by the Corporation.  The loans will always be principle & inte

Marginal cost, contribution per unit 8 fixed cost=800.find B.E.P?

contribution per unit 8 fixed cost=800.find B.E.P?

Calculate the range of monthly financing rates, Calculate the range of mont...

Calculate the range of monthly financing rates for which the schedule of monthly cash flows is profitable: Month Cash Flow, $ -------------------- 0 -10,100 1 +23,000 2 -13,

Determine how much to stock, Determine how much to stock 1. Employ The...

Determine how much to stock 1. Employ The Economic Order Quantity Model This is an easiest model which helps the manager to find out the optimum quantity of stock to order

MANAGERIAL DECISION, DIFERENCE BETWEEN MARGINAL AND DIFFERENTIAL COSTING

DIFERENCE BETWEEN MARGINAL AND DIFFERENTIAL COSTING

Cost audit, what is cost audit? types of cost audit explain

what is cost audit? types of cost audit explain

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd