Cost variance and schedule variance, Cost Accounting

Assignment Help:

(i) In terms of cashflow, which month will be the most costly for your project?

(ii) If the 3rd and 4th months are more expensive by 25% each because the outsourced labour took longer than expected, what is the effect on the final predicted project cost? What action do you think you could take in these circumstances? 

3(c) Assume you have completed three months of the project. The Budget at Completion (BAC) was $250,000 for this six-month project. Also assume the following:

Planned Value (PV) = $150,000

Earned Value (EV) = $140,000

Actual Cost (AC) = $125,000  

2343_Cost variance and schedule variance.png

Use this information to answer the following questions.

(i) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

(ii) Use the CPI to calculate the estimate at completion (EAC) for this project. Use the SPI to estimate how long it will take to finish this project. Sketch an earned value chart using the above information, including the EAC point. Use the chart below (Figure 7-5, p.289 in Schwalbe 5ed) as an example of what your Earned Value Chart should look like. Comment on your chart.

(iii) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Should you alert POSS senior management and ask for assistance?


Related Discussions:- Cost variance and schedule variance

Cost audit, what is cost audit? types of cost audit explain

what is cost audit? types of cost audit explain

Determine the incremental cost, Determine the Incremental Cost A compa...

Determine the Incremental Cost A company currently makes a component that has the given unit cost structure Direct Material Shs. 100

Types of standard costs, Types of Standard Costs The standard cost set...

Types of Standard Costs The standard cost set could be ideal, basic, attainable or current. i. Basic Standards: These are long term standards that would keep unchanged ov

Define the marginal, Total profit means the total revenue excluding the tot...

Total profit means the total revenue excluding the total cost of the certain products. Average profit defines the profit which comes and achieved after selling each unit. Total

Stages of implementation of zero based budgeting, Stages of Implementation ...

Stages of Implementation of Zero Based Budgeting 1. Definition of decision package. It is the comprehensive description of the organizations activities or functions.

Materials mix variance, M aterials mix variance :  It can be described a...

M aterials mix variance :  It can be described as that portion of direct material usage variance which is the variation between the actual quantities of ingredients used in a mi

What will the bond sell, A 20-year bond pays a coupon of 8 percent per year...

A 20-year bond pays a coupon of 8 percent per year (coupon paid semi-annually). The bond has a par value of $1000. What will the bond sell for if the nominal YTM is: a) 10 per

Multiple product scenarios, Break-even analysis can be used to work out eit...

Break-even analysis can be used to work out either a break-even volume or revenue, as per given a multiple product scenario. This is achieved using 'average contribution per unit'

Ppe, is ppe taxable

is ppe taxable

Evaluate the cost structure, The project (using the tools and techniques gi...

The project (using the tools and techniques given in Chapters 3, 8, 10, 11, and 12 of the textbook) and its subsequent report are based on the complete economic analysis of a compa

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd