Cost variance and schedule variance, Cost Accounting

Assignment Help:

(i) In terms of cashflow, which month will be the most costly for your project?

(ii) If the 3rd and 4th months are more expensive by 25% each because the outsourced labour took longer than expected, what is the effect on the final predicted project cost? What action do you think you could take in these circumstances? 

3(c) Assume you have completed three months of the project. The Budget at Completion (BAC) was $250,000 for this six-month project. Also assume the following:

Planned Value (PV) = $150,000

Earned Value (EV) = $140,000

Actual Cost (AC) = $125,000  

2343_Cost variance and schedule variance.png

Use this information to answer the following questions.

(i) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

(ii) Use the CPI to calculate the estimate at completion (EAC) for this project. Use the SPI to estimate how long it will take to finish this project. Sketch an earned value chart using the above information, including the EAC point. Use the chart below (Figure 7-5, p.289 in Schwalbe 5ed) as an example of what your Earned Value Chart should look like. Comment on your chart.

(iii) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Should you alert POSS senior management and ask for assistance?


Related Discussions:- Cost variance and schedule variance

Compute the net cash used, Martinez Corporation engaged in the following ca...

Martinez Corporation engaged in the following cash transactions during 2012. Sale of land and building $186,710 Purchase of treasury stock 42,130 Purchase of land 39,130

Direct labour efficiency variances, Direct Labour Efficiency Variances ...

Direct Labour Efficiency Variances It is the difference between the standard hours allowed for the actual production achieved and the hours actually worked, all valued at THE

What amount of units, If fixed costs are $200,000 and the unit contribution...

If fixed costs are $200,000 and the unit contribution margin is $20, what amount of units must be sold in order to have a zero profit?

Allocate joint production costs to each product, Bubble Corporation manufac...

Bubble Corporation manufactures two products, I and II, from a joint process. A single production costs $4,000 and results in 100 units of I and 400 units of II. To be ready for sa

British Columbia Lumber has a Raw Lumber Division, British Columbia Lumber ...

British Columbia Lumber has a Raw Lumber Division and a Finished Lumber Division. The  variable costs are: 1.Raw Lumber Division: Rs. 100 per 100 board-feet of raw lumber 2.F

What profit is earned by each firm, Three oligopolists, A, B and C, produce...

Three oligopolists, A, B and C, produce an identical product, Q. Q is produced under conditions of constant costs, that is, AC = MC = $100. The market demand schedule for Q is:

Marginal costing and break evan point analysis, what is marginal costing an...

what is marginal costing and explain concept of marginal costing

Exploration costs, are exploration cost treated as an asset or expense or b...

are exploration cost treated as an asset or expense or both?

Determine a simplified single cost allocation rate, When implementing ABC, ...

When implementing ABC, once a company has identified business activities and their costs, the company will probably: A) determine a simplified single cost allocation rate B)

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd