Cost variance and schedule variance, Cost Accounting

Assignment Help:

(i) In terms of cashflow, which month will be the most costly for your project?

(ii) If the 3rd and 4th months are more expensive by 25% each because the outsourced labour took longer than expected, what is the effect on the final predicted project cost? What action do you think you could take in these circumstances? 

3(c) Assume you have completed three months of the project. The Budget at Completion (BAC) was $250,000 for this six-month project. Also assume the following:

Planned Value (PV) = $150,000

Earned Value (EV) = $140,000

Actual Cost (AC) = $125,000  

2343_Cost variance and schedule variance.png

Use this information to answer the following questions.

(i) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

(ii) Use the CPI to calculate the estimate at completion (EAC) for this project. Use the SPI to estimate how long it will take to finish this project. Sketch an earned value chart using the above information, including the EAC point. Use the chart below (Figure 7-5, p.289 in Schwalbe 5ed) as an example of what your Earned Value Chart should look like. Comment on your chart.

(iii) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Should you alert POSS senior management and ask for assistance?


Related Discussions:- Cost variance and schedule variance

Cvp analysis in situations subject to change, CVP Analysis in Situations Su...

CVP Analysis in Situations Subject To Change Revenue and Cost will change and also sales volume because of a number of factors involving: a) Increased competition may need

Bases of cost classification, Bases of Cost Classification These vario...

Bases of Cost Classification These various bases of cost classification are summarized in the diagram underneath as: Here, we will usually refer to either of these ter

Direct and indirect costs, Direct and Indirect costs Recall such direc...

Direct and Indirect costs Recall such direct costs are costs which can be traced particularly to the end product of the production procedure while indirect costs cannot be so

Overhead costs, Overhead Costs Introduction Overhead costs may be...

Overhead Costs Introduction Overhead costs may be defined like the net cost of indirect materials, indirect expenses and indirect labour. They may happen or be charged to

Calculate cost of direct manufacturing labour, Dixon Corporation was establ...

Dixon Corporation was established on January 1, Year 1.  The firm has 2 divisions, Division A and Division B.  Division A manufactures standard carpets, and Division B manufactures

Cost volume analysis, Production of a particular product costs $50 per mate...

Production of a particular product costs $50 per material, $80 per labour and variable overhead is 75% of labour cost. If the selling price per unit is $230 and fixed cost amounts

MATERIALCOSTING, what are the material management questions

what are the material management questions

Just in time, advantages and disadvantages of just in time

advantages and disadvantages of just in time

Variable overhead variance (vohv), Variable Overhead Variance (VOHV) VO...

Variable Overhead Variance (VOHV) VOHV is defined by ICMA, London, as 'the variation between the standard variable production overhead absorbed in the production achieved, whet

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd