Cost variance and schedule variance, Cost Accounting

Assignment Help:

(i) In terms of cashflow, which month will be the most costly for your project?

(ii) If the 3rd and 4th months are more expensive by 25% each because the outsourced labour took longer than expected, what is the effect on the final predicted project cost? What action do you think you could take in these circumstances? 

3(c) Assume you have completed three months of the project. The Budget at Completion (BAC) was $250,000 for this six-month project. Also assume the following:

Planned Value (PV) = $150,000

Earned Value (EV) = $140,000

Actual Cost (AC) = $125,000  

2343_Cost variance and schedule variance.png

Use this information to answer the following questions.

(i) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

(ii) Use the CPI to calculate the estimate at completion (EAC) for this project. Use the SPI to estimate how long it will take to finish this project. Sketch an earned value chart using the above information, including the EAC point. Use the chart below (Figure 7-5, p.289 in Schwalbe 5ed) as an example of what your Earned Value Chart should look like. Comment on your chart.

(iii) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Should you alert POSS senior management and ask for assistance?


Related Discussions:- Cost variance and schedule variance

Allocation of overhead costs, Allocation of Overhead Costs Allocation ...

Allocation of Overhead Costs Allocation of overheads is the term utilized where the overhead cost item can be charged to a exact cost center without the requirement for any es

Why are marginal costs increasing, 1. Why are marginal costs increasing? Wh...

1. Why are marginal costs increasing? Why are they not always constant? You may give examples in some industries or just state two reasons at least.

What is subphylum uniramia, Tlie subphylum is called Uniramia because of t...

Tlie subphylum is called Uniramia because of the presence of unbranched appendages. These animals have non-jointed mandibles, uubranched appendages without any palps. They have

What is emv and eol approach, Adele Weiss manages the campus flower shop. ...

Adele Weiss manages the campus flower shop. Flowers must be ordered three days in advance from her supplier in Mexico. Advance sales are so small that Weiss has no way to estimate

Example of economic order quantity, Example of Economic Order Quantity ...

Example of Economic Order Quantity The EOQ model supposes : - Annual demand is recognized - Hold costs are constant and recognized - Ordering costs are recognized a

Prepare an amortization table, On January 1, 2012 Morgan's Motors issued $5...

On January 1, 2012 Morgan's Motors issued $500,000 of 3-year, 8% bonds when the market yield was 6%. The bond agreement stated that compounding was semi-annual with payments due on

OBJECTIVES OF COST ACCOUNTING, OBJECTIVES OF COST ACCOUNTING : 1-DETERMININ...

OBJECTIVES OF COST ACCOUNTING : 1-DETERMINING SELLING PRICE 2-CONTROLING COST 3- PROVIDING INFORMATION FOR DESING MAKING 4-ASCERTAINING COSTING PROFIT 5-Facilitating preparation of

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd