Cost- sampling decisons

 

                      σ x¯ =S/√n

     

Where is the  standard  error of he mean is the standard devaluation of  the population and n is the sample size. Here  the standard  error  of the mean is expressed in terms  of money i, e. ± Rs. 10. If the  standard  deviation is 100  the factor  for 95 percent  confidence is 1.96 of standard deviation. Thus  the actual size  of the  sample  would be

                10/ 1.96 = 100/√n

                 √n = 196/10

                N = 384

The total  cost of  the budget  been reduced from  Rs.8000 to Rs. 7680= ( 384x 20)

Another  alternative may be to  increase  the allowable error  from a lower  level to  higher level  provided  it does  not affect  the attitude  of the  respondents. For  example  if the  error is increased to  15, the sample  size will be

         σ x¯ =s/√n

        1.5/1.96= 100√n

      √n= 196/ 15

     N= 169

Thus  the total  budget  will be reduced from  Rs. 8000 to Rs. 3380= ( 196x 20)

    

 


Related Discussions:- Cost- sampling decisons

Operations strategy in an organization, 1. Investigate: The Operations Str...

1. Investigate: The Operations Strategy of your organisation or one you are familiar with and answer the following points. Does your chosen organisation have an operations

Validity of the model - operation research model, Deriving the Solution fro...

Deriving the Solution from the Model: This phase is devoted to the computation of those value of decision variables that maximize or minimize the objective function. Such

Linear Programming Problem, A paper mill produces two grades of paper viz.,...

A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper i

A paper mill produces, . A paper mill produces two grades of paper viz., X ...

. A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper

Linear programming, solve the following linear programming problem using si...

solve the following linear programming problem using simplex method maximize z=3x1+2x2 subject to the constraints: x1+x2 x1+x2 x1,x2>=0

Help me please , This year Jan Rich, who is ranked number one in women''s s...

This year Jan Rich, who is ranked number one in women''s singles in tennis, and Marie Wacker, who is ranked number three, will play 4 times. If Marie can beat Jan 3 times, she will

B. A paper mill produces two grades of paper viz., b. A paper mill produces...

b. A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y pape

Organization of the study, In this project the main focus is conducted inte...

In this project the main focus is conducted interview to educational experts. This interview is base on Delphi technique. This technique is used to attain experts' consensus on ele

Linear programming, #questiona paper mill produce two grades of x&y.becouse...

#questiona paper mill produce two grades of x&y.becouse of raw material reswtriction

Probability and non probability sampling , Probability and Non  Probability...

Probability and Non  Probability Sampling The following s are some  of the  considerations for the  selection  of probability  an non  probability  sampling. 1.Sometimes p

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd