Cost-reimbursable contracts , Project Management

Assignment Help:

Cost-reimbursable contracts 

In cost-reimbursable contracts you pay the contractor the costs necessarily incurred in the construction plus a fee. The latter portion viz. the fee can be fixed in a number of ways which we will discuss later in this section. The main reasons for adopting this mode of contracting are: 

  • At the time of contracting, the scope of the work is indeterminate or highly uncertain and the kind of labour, material and equipment needed are also uncertain. 
  • At the time of contracting, you are unable to finalise the plans and specifications for the project.  
  • At the time of contracting, you are not certain whether the construction project will be completed in full. 
  • Cost-reimbursable contracts offer an easy response to unexpected conditions arising during project implementation. 
  • Under this arrangement complete records of all time and materials spent by the contractor must be maintained. (These types of contracts are also called Time and Material contracts or Cost-plus contracts). Evidently the  risk of cost increase in the project depends entirely upon you. 

The most important question that should be resolved for finalising cost-reimbursable contracts is to identify the following costs: 

  • Reimbursable costs (costs that are reimbursable to contractor that is. costs that are necessarily incurred in the performance of the work). 
  • Non-reimbursable costs (costs that are not reimbursable to contractor). 
  • Costs that are included in the base figure which is agreed as the basis for determining the fee. 

Typically these costs comprise the following elements: 

  • Reimbursable costs (that is. costs that are necessarily incurred in the performance of the work), which includes: 

 

  1. Wages, payroll taxes and fringe benefits. 
  2. Cost of all materials, supplies and equipment including the costs of transportation, unloading thereof. 
  3. Payments to subcontractors. 
  4. Rental and maintenance charges for all equipment, trucks and hand tools. 
  5. Cost of salaries of all contractor?s staff stationed at the field office. 
  6. Cost of salaries of contractor?s staff utilised for expediting of supplies, supervising of transportation and so on calculated for time specifically spent on the project. 
  7. Cost of travel and travel incidentals of contractor?s staff directly incurred on the project. 
  8. Premiums of all bonds and insurances incurred by contractor for the work. 
  9. Permit fees. 
  10. Cost incurred for communication that is, telephone, electronic communication and so on and for stationery at site. 
  11. Cost of temporary site facilities like removal of debris. 
  12. Losses and expenses not compensated by insurance which result from causes other than the fault or negligence of the contractor. 

Non-reimbursable costs which includes:

  1. Salaries or other compensation for the contractor?s officers and employees while working at the contractor?s main office or branch offices. 
  2. Expenses of the contractor?s principal or branch offices other than the field office. 
  3. Any capital expenses including interest on the contractor?s capital and any additional capital required to perform the work. 
  4. All general overhead expenses.

Costs due to negligence of the contractor, subcontractors, or anyone directly employed by the contractor. While the above list is typical, there can be some variations to the list depending on the agreement between owner and contractor. But the contract should make these costs clear in order to avoid disputes.   


Related Discussions:- Cost-reimbursable contracts

Different steps in an environmental impact assessment, Question 1: (a) ...

Question 1: (a) Distinguish between Life Cycle Assessment (LCA) and Environmental Management System (EMS) and outline the benefits of implementing an Environmental Management

Risk type, Risk type  To identify specific problems in your project, yo...

Risk type  To identify specific problems in your project, you first need to categorise the risks.  The project constraints are  well-organised in the PERIL database, which are

Need for safety, Need for safety 1. Cost Saving: Two type  of costs ...

Need for safety 1. Cost Saving: Two type  of costs  are incurred by the management  when an accident  occurs. There are the  direct  costs in the  form  of compensation paya

Describe the factors that lead to the project failure, Question: a) Des...

Question: a) Describe lessons or best practices that could be learned from the above case study? b) Describe the factors that lead to the project failure? c) What is acc

Steps associated with the closure of a project, Question: There is a cy...

Question: There is a cycle associated with the life of a project. This runs from the commencement to the completion of the project with authority being required for both the co

Steps of heuristic method, Steps of Heuristic Method The heuristic ap...

Steps of Heuristic Method The heuristic approach involves following procedural steps: Identify the work ( job) Break down the work into elemental tasks or steps for

Quality tools in process improvement, Question : (a) Describe the impor...

Question : (a) Describe the importance of the following quality tools in process improvement: (i) Pareto diagrams (ii) cause-and-effect diagrams (b) The Managi

You are a Project manager at the Department of Public Works, Describe how y...

Describe how you, as a project manager in a Matrix Organisation, will set up your project r=team for the building of the community. Project team members names, and reason why they

Preliminary design, Having given the guidelines in the form of design s...

Having given the guidelines in the form of design specifications the designer should be given a free hand in developing the preliminary design of the product. However i

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd