Cost-reimbursable contracts , Project Management

Assignment Help:

Cost-reimbursable contracts 

In cost-reimbursable contracts you pay the contractor the costs necessarily incurred in the construction plus a fee. The latter portion viz. the fee can be fixed in a number of ways which we will discuss later in this section. The main reasons for adopting this mode of contracting are: 

  • At the time of contracting, the scope of the work is indeterminate or highly uncertain and the kind of labour, material and equipment needed are also uncertain. 
  • At the time of contracting, you are unable to finalise the plans and specifications for the project.  
  • At the time of contracting, you are not certain whether the construction project will be completed in full. 
  • Cost-reimbursable contracts offer an easy response to unexpected conditions arising during project implementation. 
  • Under this arrangement complete records of all time and materials spent by the contractor must be maintained. (These types of contracts are also called Time and Material contracts or Cost-plus contracts). Evidently the  risk of cost increase in the project depends entirely upon you. 

The most important question that should be resolved for finalising cost-reimbursable contracts is to identify the following costs: 

  • Reimbursable costs (costs that are reimbursable to contractor that is. costs that are necessarily incurred in the performance of the work). 
  • Non-reimbursable costs (costs that are not reimbursable to contractor). 
  • Costs that are included in the base figure which is agreed as the basis for determining the fee. 

Typically these costs comprise the following elements: 

  • Reimbursable costs (that is. costs that are necessarily incurred in the performance of the work), which includes: 

 

  1. Wages, payroll taxes and fringe benefits. 
  2. Cost of all materials, supplies and equipment including the costs of transportation, unloading thereof. 
  3. Payments to subcontractors. 
  4. Rental and maintenance charges for all equipment, trucks and hand tools. 
  5. Cost of salaries of all contractor?s staff stationed at the field office. 
  6. Cost of salaries of contractor?s staff utilised for expediting of supplies, supervising of transportation and so on calculated for time specifically spent on the project. 
  7. Cost of travel and travel incidentals of contractor?s staff directly incurred on the project. 
  8. Premiums of all bonds and insurances incurred by contractor for the work. 
  9. Permit fees. 
  10. Cost incurred for communication that is, telephone, electronic communication and so on and for stationery at site. 
  11. Cost of temporary site facilities like removal of debris. 
  12. Losses and expenses not compensated by insurance which result from causes other than the fault or negligence of the contractor. 

Non-reimbursable costs which includes:

  1. Salaries or other compensation for the contractor?s officers and employees while working at the contractor?s main office or branch offices. 
  2. Expenses of the contractor?s principal or branch offices other than the field office. 
  3. Any capital expenses including interest on the contractor?s capital and any additional capital required to perform the work. 
  4. All general overhead expenses.

Costs due to negligence of the contractor, subcontractors, or anyone directly employed by the contractor. While the above list is typical, there can be some variations to the list depending on the agreement between owner and contractor. But the contract should make these costs clear in order to avoid disputes.   


Related Discussions:- Cost-reimbursable contracts

International/global competitive bidding (icb), Steps involved for Internat...

Steps involved for International/Global Competitive Bidding (ICB)      Now that we are aware of the requirements of ICB, let us understand the steps involved in ICB. There can b

Design and implement company network infrastructure, Network Infrastructure...

Network Infrastructure: This project will require replacement of major networking components throughout the office. Virtualization will result in increased speed and reliability f

Levels of strategy, Levels of strategy There are three levels of strate...

Levels of strategy There are three levels of strategy: Corporate strategy is the overall (grand) strategy for the organization as a whole. Business strategy refers to

Prepare a short notes on quality function deployment process, Question 1: ...

Question 1: Describe the concept of Cost of Quality briefly. What are the components of Cost of Quality? Concept of Cost of Quality Benefits Components of Cost

Leading lean project-Fifa Cup 2018, I want this assignment befor the due de...

I want this assignment befor the due deate of 7 sept..if some one over there than contact me.

PMP, A good leader is not necessarily a good manager.” Discuss this stateme...

A good leader is not necessarily a good manager.” Discuss this statement & compare leadership With management.

Research process, Research Process: Research process consists of a numbe...

Research Process: Research process consists of a number of closely related activates. But such activities overlap continuously and do not follow a strictly prescribed sequence.

What are the principal stages of a project life cycle, Question 1: (a) ...

Question 1: (a) What are the principal stages of a project life cycle? (b) Describe fully the steps involved in the project planning process. Question 2: "Effective

Evaluation of current organisational culture, It is gradually recognised th...

It is gradually recognised that culture, although difficult to measure precisely, it is a real and very powerful force in organisations. Organisational behaviour is related to cult

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd