Cost-reimbursable contracts , Project Management

Assignment Help:

Cost-reimbursable contracts 

In cost-reimbursable contracts you pay the contractor the costs necessarily incurred in the construction plus a fee. The latter portion viz. the fee can be fixed in a number of ways which we will discuss later in this section. The main reasons for adopting this mode of contracting are: 

  • At the time of contracting, the scope of the work is indeterminate or highly uncertain and the kind of labour, material and equipment needed are also uncertain. 
  • At the time of contracting, you are unable to finalise the plans and specifications for the project.  
  • At the time of contracting, you are not certain whether the construction project will be completed in full. 
  • Cost-reimbursable contracts offer an easy response to unexpected conditions arising during project implementation. 
  • Under this arrangement complete records of all time and materials spent by the contractor must be maintained. (These types of contracts are also called Time and Material contracts or Cost-plus contracts). Evidently the  risk of cost increase in the project depends entirely upon you. 

The most important question that should be resolved for finalising cost-reimbursable contracts is to identify the following costs: 

  • Reimbursable costs (costs that are reimbursable to contractor that is. costs that are necessarily incurred in the performance of the work). 
  • Non-reimbursable costs (costs that are not reimbursable to contractor). 
  • Costs that are included in the base figure which is agreed as the basis for determining the fee. 

Typically these costs comprise the following elements: 

  • Reimbursable costs (that is. costs that are necessarily incurred in the performance of the work), which includes: 

 

  1. Wages, payroll taxes and fringe benefits. 
  2. Cost of all materials, supplies and equipment including the costs of transportation, unloading thereof. 
  3. Payments to subcontractors. 
  4. Rental and maintenance charges for all equipment, trucks and hand tools. 
  5. Cost of salaries of all contractor?s staff stationed at the field office. 
  6. Cost of salaries of contractor?s staff utilised for expediting of supplies, supervising of transportation and so on calculated for time specifically spent on the project. 
  7. Cost of travel and travel incidentals of contractor?s staff directly incurred on the project. 
  8. Premiums of all bonds and insurances incurred by contractor for the work. 
  9. Permit fees. 
  10. Cost incurred for communication that is, telephone, electronic communication and so on and for stationery at site. 
  11. Cost of temporary site facilities like removal of debris. 
  12. Losses and expenses not compensated by insurance which result from causes other than the fault or negligence of the contractor. 

Non-reimbursable costs which includes:

  1. Salaries or other compensation for the contractor?s officers and employees while working at the contractor?s main office or branch offices. 
  2. Expenses of the contractor?s principal or branch offices other than the field office. 
  3. Any capital expenses including interest on the contractor?s capital and any additional capital required to perform the work. 
  4. All general overhead expenses.

Costs due to negligence of the contractor, subcontractors, or anyone directly employed by the contractor. While the above list is typical, there can be some variations to the list depending on the agreement between owner and contractor. But the contract should make these costs clear in order to avoid disputes.   


Related Discussions:- Cost-reimbursable contracts

Principle of parity of authority and responsibility, What is the principle ...

What is the principle of parity of authority and responsibility? The principle of parity of authority and responsibility states which in delegating; managers should match the r

Explain what is public-private-partnership, Question : (a) Explain wha...

Question : (a) Explain what is public-private-partnership (PPP)? (b) What are the benefits of public-private-partnership? (c) Explain the different forms PPP arrangeme

What are the causes of poor industrial relations, What are the Causes of Po...

What are the Causes of Poor Industrial Relations? Purposes of Poor Industrial Relations situation for good IR are as follows: a. Inadequate fixation of wages and wage struct

Quantitative layout analysis - Trial and Error Method, Quantitative layout ...

Quantitative layout analysis - Trial and Error Method Here we use simple travel chart and graphical approach to reduce to minimize nonadjacent flows by centrally locating the

Evaluation of the prototype, At this stage of design the designer will...

At this stage of design the designer will invariably by under tremendous pressure to quickly finish the design and pass it on for production. This is so because even w

What is critical path in job operation of a project, What is critical path ...

What is critical path in job operation of a project? Critical Path: This is that sequence of activities that decide the total project duration. This Path is formed throu

Explain the terms - product and work package, Explain the terms "product" a...

Explain the terms "product" and "work package" and describe how these are related to each other. A product is a particular deliverable from a project and this may also make a wo

Outline at least three steps common to pert and cpm, QUESTION (a) Feasi...

QUESTION (a) Feasibility Study is a preliminary study undertaken before a real work of a project start what factors should the project manager take into consideration while con

What is brainstorming, Question 1: (a) Mr Dupuy, the Chaiperson of the ...

Question 1: (a) Mr Dupuy, the Chaiperson of the Rose Flower Senior Citizen Association having its seat at 30 Avenue Des Loisirs Pointes-aux-sables wishes to call a meeting of m

Cobit, compare cobit 4.1 with cobit 5

compare cobit 4.1 with cobit 5

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd