Cost-reimbursable contracts , Project Management

Assignment Help:

Cost-reimbursable contracts 

In cost-reimbursable contracts you pay the contractor the costs necessarily incurred in the construction plus a fee. The latter portion viz. the fee can be fixed in a number of ways which we will discuss later in this section. The main reasons for adopting this mode of contracting are: 

  • At the time of contracting, the scope of the work is indeterminate or highly uncertain and the kind of labour, material and equipment needed are also uncertain. 
  • At the time of contracting, you are unable to finalise the plans and specifications for the project.  
  • At the time of contracting, you are not certain whether the construction project will be completed in full. 
  • Cost-reimbursable contracts offer an easy response to unexpected conditions arising during project implementation. 
  • Under this arrangement complete records of all time and materials spent by the contractor must be maintained. (These types of contracts are also called Time and Material contracts or Cost-plus contracts). Evidently the  risk of cost increase in the project depends entirely upon you. 

The most important question that should be resolved for finalising cost-reimbursable contracts is to identify the following costs: 

  • Reimbursable costs (costs that are reimbursable to contractor that is. costs that are necessarily incurred in the performance of the work). 
  • Non-reimbursable costs (costs that are not reimbursable to contractor). 
  • Costs that are included in the base figure which is agreed as the basis for determining the fee. 

Typically these costs comprise the following elements: 

  • Reimbursable costs (that is. costs that are necessarily incurred in the performance of the work), which includes: 

 

  1. Wages, payroll taxes and fringe benefits. 
  2. Cost of all materials, supplies and equipment including the costs of transportation, unloading thereof. 
  3. Payments to subcontractors. 
  4. Rental and maintenance charges for all equipment, trucks and hand tools. 
  5. Cost of salaries of all contractor?s staff stationed at the field office. 
  6. Cost of salaries of contractor?s staff utilised for expediting of supplies, supervising of transportation and so on calculated for time specifically spent on the project. 
  7. Cost of travel and travel incidentals of contractor?s staff directly incurred on the project. 
  8. Premiums of all bonds and insurances incurred by contractor for the work. 
  9. Permit fees. 
  10. Cost incurred for communication that is, telephone, electronic communication and so on and for stationery at site. 
  11. Cost of temporary site facilities like removal of debris. 
  12. Losses and expenses not compensated by insurance which result from causes other than the fault or negligence of the contractor. 

Non-reimbursable costs which includes:

  1. Salaries or other compensation for the contractor?s officers and employees while working at the contractor?s main office or branch offices. 
  2. Expenses of the contractor?s principal or branch offices other than the field office. 
  3. Any capital expenses including interest on the contractor?s capital and any additional capital required to perform the work. 
  4. All general overhead expenses.

Costs due to negligence of the contractor, subcontractors, or anyone directly employed by the contractor. While the above list is typical, there can be some variations to the list depending on the agreement between owner and contractor. But the contract should make these costs clear in order to avoid disputes.   


Related Discussions:- Cost-reimbursable contracts

Describe incremental approach to testing by unit test, Describe the increme...

Describe the incremental approach to testing represented by the orderly unit (module) test. Unit (module) test: Along with the incremental approach to testing, every unit

Phases of value engineering process, P hases of value engineering process ...

P hases of value engineering process I nvestigation phase: This phase investigates the background information, the technical input reports, the field data, the functiona

WBS and Network diagram, Network Diagram for my course project based upon t...

Network Diagram for my course project based upon the WBS. The Network Diagram should include the Earliest Start (ES), Earliest Finish (EF), Latest Start (LS), Latest Finish (LF), a

What are the major characteristics of a project, Question : (a) Organi...

Question : (a) Organizations and individuals have studied a number of projects that have both succeeded and failed and some common factors emerge. Can you give some reasons fo

Determine development lifecycles appropriate for project, You have been ask...

You have been asked to acquire charge of a system growth where the customer needs about fifty per cent of the functionality very immediately to meet a business opportunity but wher

Upward communication from subordinate to superior, How must be the upward c...

How must be the upward communication from subordinate to superior ? Upward Communication moves through subordinate to the superior within the form of feedback. This takes th

Sequence activities and milestones , This assignment is designed to demonst...

This assignment is designed to demonstrate your understanding of project scheduling, time and cost estimation. Assignment: Update your group's WBS created in Assignment 1

What are the risk management strategies, What are the risk management strat...

What are the risk management strategies? Risk management strategies: • Retain the risk (Absorption) as like when the risk is small and won’t influence the project a great de

Define project evaluation review technique, Question 1: As a Business d...

Question 1: As a Business development Officer, how you will bring business to a CRO? Responsibilities and roles of Business development Officer in a CRO Method and Tec

What is working of definition phase in project management, What is the work...

What is the working of definition phase in the project management? Definition phase: After the project plan that developed into the initiation phase, has been approved, a

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd