Cost-reimbursable contracts , Project Management

Assignment Help:

Cost-reimbursable contracts 

In cost-reimbursable contracts you pay the contractor the costs necessarily incurred in the construction plus a fee. The latter portion viz. the fee can be fixed in a number of ways which we will discuss later in this section. The main reasons for adopting this mode of contracting are: 

  • At the time of contracting, the scope of the work is indeterminate or highly uncertain and the kind of labour, material and equipment needed are also uncertain. 
  • At the time of contracting, you are unable to finalise the plans and specifications for the project.  
  • At the time of contracting, you are not certain whether the construction project will be completed in full. 
  • Cost-reimbursable contracts offer an easy response to unexpected conditions arising during project implementation. 
  • Under this arrangement complete records of all time and materials spent by the contractor must be maintained. (These types of contracts are also called Time and Material contracts or Cost-plus contracts). Evidently the  risk of cost increase in the project depends entirely upon you. 

The most important question that should be resolved for finalising cost-reimbursable contracts is to identify the following costs: 

  • Reimbursable costs (costs that are reimbursable to contractor that is. costs that are necessarily incurred in the performance of the work). 
  • Non-reimbursable costs (costs that are not reimbursable to contractor). 
  • Costs that are included in the base figure which is agreed as the basis for determining the fee. 

Typically these costs comprise the following elements: 

  • Reimbursable costs (that is. costs that are necessarily incurred in the performance of the work), which includes: 

 

  1. Wages, payroll taxes and fringe benefits. 
  2. Cost of all materials, supplies and equipment including the costs of transportation, unloading thereof. 
  3. Payments to subcontractors. 
  4. Rental and maintenance charges for all equipment, trucks and hand tools. 
  5. Cost of salaries of all contractor?s staff stationed at the field office. 
  6. Cost of salaries of contractor?s staff utilised for expediting of supplies, supervising of transportation and so on calculated for time specifically spent on the project. 
  7. Cost of travel and travel incidentals of contractor?s staff directly incurred on the project. 
  8. Premiums of all bonds and insurances incurred by contractor for the work. 
  9. Permit fees. 
  10. Cost incurred for communication that is, telephone, electronic communication and so on and for stationery at site. 
  11. Cost of temporary site facilities like removal of debris. 
  12. Losses and expenses not compensated by insurance which result from causes other than the fault or negligence of the contractor. 

Non-reimbursable costs which includes:

  1. Salaries or other compensation for the contractor?s officers and employees while working at the contractor?s main office or branch offices. 
  2. Expenses of the contractor?s principal or branch offices other than the field office. 
  3. Any capital expenses including interest on the contractor?s capital and any additional capital required to perform the work. 
  4. All general overhead expenses.

Costs due to negligence of the contractor, subcontractors, or anyone directly employed by the contractor. While the above list is typical, there can be some variations to the list depending on the agreement between owner and contractor. But the contract should make these costs clear in order to avoid disputes.   


Related Discussions:- Cost-reimbursable contracts

Small project, Q. If I only have a small project, do I really need to bothe...

Q. If I only have a small project, do I really need to bother with all of that? In any of project of any size all of these ten attributes requires some degree of attention. But

Risk management , Introduction to Risk Management Let us begin with def...

Introduction to Risk Management Let us begin with defining Risk. Risk, is an integral part of the business scenario, and can be termed as a potential event that can have opport

Why do projects always seem to take longer than expected, Q. Why do project...

Q. Why do projects always seem to take longer than expected? Usually this is because it is relatively easy to assign time allowances to all the activities that have been though

Assessing Infrastructure Project-Related Risks, The Three Gorges Dam is pot...

The Three Gorges Dam is potentially one of the largest, if not the largest infrastructure projects completed in the 21st century. Clearly, there were a number of key risks that the

The Walsham Hotel, Compare and Contrast the KN346 investment and the "plain...

Compare and Contrast the KN346 investment and the "plain vanilla" alternative.

Individual values and team behaviour, Teams  are made up of  individuals, v...

Teams  are made up of  individuals, values and beliefs drive team behavior. Individuals represent an important dynamic in the study and application of team behavior. Individuals pr

What must be the responsibility of the project manager, What must be the re...

What must be the responsibility of the project manager into relation to the business case? Idyllically, the project manager must be appointed early adequate to give to the deve

Client master plan, The Client Masterplan includes introduction, rationale,...

The Client Masterplan includes introduction, rationale, client objectives and stakeholder management. This should be a rationalisation of the requirements. Guidelines

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd