Control of contracts, Other Management

Assignment Help:

Control of contracts

The contract control process commences right at the beginning stage of bid document preparation inviting contractors to bid, and proceeds through the contract negotiation, contractor selection, monitoring and controlling of the contractor?s work and terminating the contract..

For effective control of the contracts in a project, the following areas need attention:

  • Core competence of the project manager: The project manager must have experience in planning and management of similar projects. While he should be ready to refer to the individual specialists, he should be as knowledgeable as anyone about the economic and regulatory environment, engineering technology, project planning, scheduling and cost accounting, as well as construction.

His focus throughout the project implementation should be on the key criteria of scope, time, and cost and client satisfaction. He achieves this by interpreting the requirements to the specialists and directing their efforts to achieve the best combination of these four key criteria. His core competences will be to resolve conflicts which invariably arise between these four criteria. His objectives on the project are identical to that of the client; however, he should be able and willing to argue a point with the client when he feels it is necessary.

  • Requirements of the working system: For a competent project manager to be effective, the following components of the working system are necessary:
    • The project manager must have the necessary managerial authority to ensure response to his requirements from his team.
    • All major technical, cost, schedule, or performance decisions should be made only with the project manager's participation.
    • He must be identified as the authoritative and single formal contact in dealing with outside parties.
    • The project manager should have a say in the assembly of the project team, and personnel assigned to the project must be competent.
    • The project manager should have the authority to control the commitment of funds within the prescribed limits of the project, for which he liaises constantly with the owner?s representative.
    • Senior management must clearly demonstrate support for this concept.
  • Use of Work Breakdown Structure (WBS): A complex project is made manageable by breaking it down to smaller group to define task that can be achieved independently of other tasks. A formalised WBS is essential for effective control of contracts. A contract to be awarded on the project is identified after deciding the work package units. Consultants and contractors should confirm their agreement to the work package units for which they are responsible. Thumb rules for finalising and controlling work package units are:
  1. It should not  be necessary for the project management team to incorporate into the network schedule, information which is more detailed than the work package level. Progress should be monitored at this level and variances can be investigated through field reports.
  2. Work  packages  should  be  identified  2  to  6  months  prior  to performing the work, and can only be revised with the approval of the project manager and normally as a consequence of a change order.
  3. A project should not be broken down to such an extent, or contain work packages so small, that unnecessary administrative effort is incurred in maintaining the information flow. For example on projects up to, say, Rs.100 crores, a minimum work package value of, say,
  4. 0.1% is a good rule of thumb.
  5. For  schedule  control,  an  integrated network  should  be  drawn  to monitor and forecast progress. This schedule should not be changed unless:
  • A formal reprogramming of the entire project or major part takes place.
  • The target schedule and the current schedule become so far apart that recovery is impossible and target objectives become meaningless.
  • Such    changes    are     recognised     and    approved    by    top management.
  • Recognising the limitations with flexibility: While the D-B-B mode of contracting enables flexibility to make scope and design changes, it must be constantly ensured that the detailed designs with reference to a contract get substantially finalised prior to award of the contract.

Related Discussions:- Control of contracts

Critically analyse the potential evils of bureaucratization, QUESTION 1 ...

QUESTION 1 Max Weber systematized the organization model of Bureaucracy (a) List and describe briefly the distinguishing features of bureaucracy (b) Critically analyse th

Define the service providers under foreign trade policy, Question A ) Disc...

Question A ) Discuss the changes in the composition of India's export and import since 1991. How has this affected Balance of payment situation of India? Question B ) Trading

Prospectus, This is a document which contains all relevant investor informa...

This is a document which contains all relevant investor information regarding the operations of an organization issuing privacies.

Halo effect, Halo Ef fect Halo effects refer to drawing a gener...

Halo Ef fect Halo effects refer to drawing a general impression of an individual based on a single characteristic. For example, if a person is well-dressed, you might s

How is the cost of fca best defensible to the public, Q. How is the cost of...

Q. How is the cost of FCA best defensible to the public? FCA is not a fixed product it is an approach, it is potential to tailor a cost-effective FCA system to meet the require

Importance of a price adjustment clause, QUESTION 1 (a) List five requi...

QUESTION 1 (a) List five required elements of a valid contract. (b) Give one circumstance when a contract can be modified. (c) Give one reason for which a public body may

Describe the various functions and duties, Question 1: With the help of...

Question 1: With the help of an organisation chart, explain the importance of: 1. The Front Office Department 2. The Reservation Office 3. The Housekeeping Department

Quality management, . During the analysis of a process that was evaluated, ...

. During the analysis of a process that was evaluated, a situation arose where it was seen that the variability of the data points collected was non-random on several occasions, i.

Government activities - information generation process, Government Activiti...

Government Activities  Information is also generated as a by-product from the activities undertaken by different governmental and non-governmental organisations. The most impo

Gilding and hollow backs - binding processes, Gilding:   Gilding or co...

Gilding:   Gilding or colouring edges may be done either at the time of trimming the edges or after cutting the boards. The purpose of gilding or colouring is primarily or prot

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd