Control of contracts, Other Management

Assignment Help:

Control of contracts

The contract control process commences right at the beginning stage of bid document preparation inviting contractors to bid, and proceeds through the contract negotiation, contractor selection, monitoring and controlling of the contractor?s work and terminating the contract..

For effective control of the contracts in a project, the following areas need attention:

  • Core competence of the project manager: The project manager must have experience in planning and management of similar projects. While he should be ready to refer to the individual specialists, he should be as knowledgeable as anyone about the economic and regulatory environment, engineering technology, project planning, scheduling and cost accounting, as well as construction.

His focus throughout the project implementation should be on the key criteria of scope, time, and cost and client satisfaction. He achieves this by interpreting the requirements to the specialists and directing their efforts to achieve the best combination of these four key criteria. His core competences will be to resolve conflicts which invariably arise between these four criteria. His objectives on the project are identical to that of the client; however, he should be able and willing to argue a point with the client when he feels it is necessary.

  • Requirements of the working system: For a competent project manager to be effective, the following components of the working system are necessary:
    • The project manager must have the necessary managerial authority to ensure response to his requirements from his team.
    • All major technical, cost, schedule, or performance decisions should be made only with the project manager's participation.
    • He must be identified as the authoritative and single formal contact in dealing with outside parties.
    • The project manager should have a say in the assembly of the project team, and personnel assigned to the project must be competent.
    • The project manager should have the authority to control the commitment of funds within the prescribed limits of the project, for which he liaises constantly with the owner?s representative.
    • Senior management must clearly demonstrate support for this concept.
  • Use of Work Breakdown Structure (WBS): A complex project is made manageable by breaking it down to smaller group to define task that can be achieved independently of other tasks. A formalised WBS is essential for effective control of contracts. A contract to be awarded on the project is identified after deciding the work package units. Consultants and contractors should confirm their agreement to the work package units for which they are responsible. Thumb rules for finalising and controlling work package units are:
  1. It should not  be necessary for the project management team to incorporate into the network schedule, information which is more detailed than the work package level. Progress should be monitored at this level and variances can be investigated through field reports.
  2. Work  packages  should  be  identified  2  to  6  months  prior  to performing the work, and can only be revised with the approval of the project manager and normally as a consequence of a change order.
  3. A project should not be broken down to such an extent, or contain work packages so small, that unnecessary administrative effort is incurred in maintaining the information flow. For example on projects up to, say, Rs.100 crores, a minimum work package value of, say,
  4. 0.1% is a good rule of thumb.
  5. For  schedule  control,  an  integrated network  should  be  drawn  to monitor and forecast progress. This schedule should not be changed unless:
  • A formal reprogramming of the entire project or major part takes place.
  • The target schedule and the current schedule become so far apart that recovery is impossible and target objectives become meaningless.
  • Such    changes    are     recognised     and    approved    by    top management.
  • Recognising the limitations with flexibility: While the D-B-B mode of contracting enables flexibility to make scope and design changes, it must be constantly ensured that the detailed designs with reference to a contract get substantially finalised prior to award of the contract.

Related Discussions:- Control of contracts

State five objectives that the ppa 2006 aims to achieve, QUESTION The P...

QUESTION The Public Procurement Act 2006 (PPA 2006) is a modern procurement legislation based on UNCITRAL Model Law. PPA 2006 was enacted in 2006 and came into force in 2008. A

Enumerate the principles of organization, Question 1 Enumerate the prin...

Question 1 Enumerate the principles of organization 2 What is decision making? Explain the steps involved in decision making 3 Explain briefly the classification of ward accomm

Periodicals department, PERIODICALS DEPARTMENT: Since periodical publi...

PERIODICALS DEPARTMENT: Since periodical publications are now a major information disseminating media, the work of the Periodical Publications Section assumes great magnitude

Describe the levels of consumer decision making while buying, Question 1 E...

Question 1 Explain the components of learning and also classical conditioning theory in brief Question 2 Briefly discuss the decision-making models(any three) Quest

Questions and answers while going for a negotiation, Let us review some que...

Let us review some questions that as a negotiator you can face while conducting a negotiation and the considerations to find answers to these questions:  Framing the opening

Output of quality assurance process, O u t put of quality assurance proc...

O u t put of quality assurance process The outputs of quality assurance process are: O rganisational process assets updates: elements of organisational process ass

Experimental research, EXPERIMENTAL RESEARCH: One of  the other method...

EXPERIMENTAL RESEARCH: One of  the other method used  in  research  is Experimental Research.  Meaning and Characteristics  Experimental research is concerned with  ca

Technical and operational performance of contracts, M onitoring  and  Co...

M onitoring  and  Controlling  Technical  and  Operational  Performance of Contracts (Contractors) Monitoring and controlling of a contract being executed by a contractor sho

Effective customer management systems, QUESTION 1 List 8 components tha...

QUESTION 1 List 8 components that need to be taken into consideration when assessing the total cost of ownership of a system QUESTION 2 With regards to supply chain man

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd