Control of contracts, Other Management

Assignment Help:

Control of contracts

The contract control process commences right at the beginning stage of bid document preparation inviting contractors to bid, and proceeds through the contract negotiation, contractor selection, monitoring and controlling of the contractor?s work and terminating the contract..

For effective control of the contracts in a project, the following areas need attention:

  • Core competence of the project manager: The project manager must have experience in planning and management of similar projects. While he should be ready to refer to the individual specialists, he should be as knowledgeable as anyone about the economic and regulatory environment, engineering technology, project planning, scheduling and cost accounting, as well as construction.

His focus throughout the project implementation should be on the key criteria of scope, time, and cost and client satisfaction. He achieves this by interpreting the requirements to the specialists and directing their efforts to achieve the best combination of these four key criteria. His core competences will be to resolve conflicts which invariably arise between these four criteria. His objectives on the project are identical to that of the client; however, he should be able and willing to argue a point with the client when he feels it is necessary.

  • Requirements of the working system: For a competent project manager to be effective, the following components of the working system are necessary:
    • The project manager must have the necessary managerial authority to ensure response to his requirements from his team.
    • All major technical, cost, schedule, or performance decisions should be made only with the project manager's participation.
    • He must be identified as the authoritative and single formal contact in dealing with outside parties.
    • The project manager should have a say in the assembly of the project team, and personnel assigned to the project must be competent.
    • The project manager should have the authority to control the commitment of funds within the prescribed limits of the project, for which he liaises constantly with the owner?s representative.
    • Senior management must clearly demonstrate support for this concept.
  • Use of Work Breakdown Structure (WBS): A complex project is made manageable by breaking it down to smaller group to define task that can be achieved independently of other tasks. A formalised WBS is essential for effective control of contracts. A contract to be awarded on the project is identified after deciding the work package units. Consultants and contractors should confirm their agreement to the work package units for which they are responsible. Thumb rules for finalising and controlling work package units are:
  1. It should not  be necessary for the project management team to incorporate into the network schedule, information which is more detailed than the work package level. Progress should be monitored at this level and variances can be investigated through field reports.
  2. Work  packages  should  be  identified  2  to  6  months  prior  to performing the work, and can only be revised with the approval of the project manager and normally as a consequence of a change order.
  3. A project should not be broken down to such an extent, or contain work packages so small, that unnecessary administrative effort is incurred in maintaining the information flow. For example on projects up to, say, Rs.100 crores, a minimum work package value of, say,
  4. 0.1% is a good rule of thumb.
  5. For  schedule  control,  an  integrated network  should  be  drawn  to monitor and forecast progress. This schedule should not be changed unless:
  • A formal reprogramming of the entire project or major part takes place.
  • The target schedule and the current schedule become so far apart that recovery is impossible and target objectives become meaningless.
  • Such    changes    are     recognised     and    approved    by    top management.
  • Recognising the limitations with flexibility: While the D-B-B mode of contracting enables flexibility to make scope and design changes, it must be constantly ensured that the detailed designs with reference to a contract get substantially finalised prior to award of the contract.

Related Discussions:- Control of contracts

Factors driving contracting , Factors Driving Contracting  In this sect...

Factors Driving Contracting  In this section let us try to analyse the factors which drive contracting decisions. Here, the buy mode is referred as contracting, subcontracting

Introduction to internet, Internet - Definition   A great majority of p...

Internet - Definition   A great majority of people are now aware of the existence of Internet But, many of them have perhaps a some what misguided view of what the Internet rea

Stack -circulation area in library building, Stack -Circulation Area in lib...

Stack -Circulation Area in library building-library managenent Stacks are the storage spaces for the various types of documents kept in a library. The types of documents gener

Relationship between front desk and reservations department, Question 1: ...

Question 1: (i) Explain the relationship between the Front Desk and the Reservations Department. (ii) Enumerate the various steps in the reservations process and explai

Steps for direct contracting , Steps for direct contracting  Now that w...

Steps for direct contracting  Now that we are aware of the requirements for direct contracting, let us understand the steps involved in direct contracting:  1.  Invite short

Stacking systems - library management, STACKING SYSTEMS: The main cons...

STACKING SYSTEMS: The main consideration in stacking is to achieve economy of space while ensuring ease of accessibility for the readers to the contents of the shelves. Space

Roles of government in the economic development of a country, Question 1: ...

Question 1: (a) What are the main roles of Government in the economic development of a country? (b) What are some of the emerging issues affecting the role of Government?

Aids to searching in opac, Aids to Searching   Subject searching in OPA...

Aids to Searching   Subject searching in OPAC creates certain problems for the users. Several OPACs have been developed to ease vocabulary selection and aid in searching. When

Discuss the importance of having ilo standards on safety, QUESTION 1 De...

QUESTION 1 Describe the various methods that can be used at a place of work to ensure that the storage and handling of materials are carried out in an effective and efficient m

Explain the reinforcement theory of motivation, QUESTION (a) Define the...

QUESTION (a) Define the term 'Motivation' and explain its importance for organizational success (b) Reply ANY TWO of the following items- (i) Explain with the support of

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd