Control of contracts, Other Management

Assignment Help:

Control of contracts

The contract control process commences right at the beginning stage of bid document preparation inviting contractors to bid, and proceeds through the contract negotiation, contractor selection, monitoring and controlling of the contractor?s work and terminating the contract..

For effective control of the contracts in a project, the following areas need attention:

  • Core competence of the project manager: The project manager must have experience in planning and management of similar projects. While he should be ready to refer to the individual specialists, he should be as knowledgeable as anyone about the economic and regulatory environment, engineering technology, project planning, scheduling and cost accounting, as well as construction.

His focus throughout the project implementation should be on the key criteria of scope, time, and cost and client satisfaction. He achieves this by interpreting the requirements to the specialists and directing their efforts to achieve the best combination of these four key criteria. His core competences will be to resolve conflicts which invariably arise between these four criteria. His objectives on the project are identical to that of the client; however, he should be able and willing to argue a point with the client when he feels it is necessary.

  • Requirements of the working system: For a competent project manager to be effective, the following components of the working system are necessary:
    • The project manager must have the necessary managerial authority to ensure response to his requirements from his team.
    • All major technical, cost, schedule, or performance decisions should be made only with the project manager's participation.
    • He must be identified as the authoritative and single formal contact in dealing with outside parties.
    • The project manager should have a say in the assembly of the project team, and personnel assigned to the project must be competent.
    • The project manager should have the authority to control the commitment of funds within the prescribed limits of the project, for which he liaises constantly with the owner?s representative.
    • Senior management must clearly demonstrate support for this concept.
  • Use of Work Breakdown Structure (WBS): A complex project is made manageable by breaking it down to smaller group to define task that can be achieved independently of other tasks. A formalised WBS is essential for effective control of contracts. A contract to be awarded on the project is identified after deciding the work package units. Consultants and contractors should confirm their agreement to the work package units for which they are responsible. Thumb rules for finalising and controlling work package units are:
  1. It should not  be necessary for the project management team to incorporate into the network schedule, information which is more detailed than the work package level. Progress should be monitored at this level and variances can be investigated through field reports.
  2. Work  packages  should  be  identified  2  to  6  months  prior  to performing the work, and can only be revised with the approval of the project manager and normally as a consequence of a change order.
  3. A project should not be broken down to such an extent, or contain work packages so small, that unnecessary administrative effort is incurred in maintaining the information flow. For example on projects up to, say, Rs.100 crores, a minimum work package value of, say,
  4. 0.1% is a good rule of thumb.
  5. For  schedule  control,  an  integrated network  should  be  drawn  to monitor and forecast progress. This schedule should not be changed unless:
  • A formal reprogramming of the entire project or major part takes place.
  • The target schedule and the current schedule become so far apart that recovery is impossible and target objectives become meaningless.
  • Such    changes    are     recognised     and    approved    by    top management.
  • Recognising the limitations with flexibility: While the D-B-B mode of contracting enables flexibility to make scope and design changes, it must be constantly ensured that the detailed designs with reference to a contract get substantially finalised prior to award of the contract.

Related Discussions:- Control of contracts

Entry - definition, What is an Entry? An entry is a record of informat...

What is an Entry? An entry is a record of information for a specific purpose. This information is entered into a ' kind of a record. Suppose you have the habit of recording in

Describe how you can enter tasks in ms project, Question 1 In order to inc...

Question 1 In order to include the cost aspects in the project scheduling, it is very much essential to first define the cost-duration relationships for various activities in the

Six sigma - cynics view, Six Sigma - Cynics view The Six Sigma has take...

Six Sigma - Cynics view The Six Sigma has taken on the life of its own. The cynics might see it as "the next big thing" which will fade as soon as the new buzzword will come al

Important qualities of a professional screenwriter, Question 1 Explain ...

Question 1 Explain the ten most important qualities of a professional screenwriter and describe why you consider these skills to be important. Question 2 (a) Name and

Research approach, RESEARCH APPROACH: Research approach (design) is th...

RESEARCH APPROACH: Research approach (design) is the researchers overall plan for answering the research questions. The  design  indicates whether or not there is  an  interve

Purpose and objectives of binding - library management, Purpose and Objecti...

Purpose and Objectives of Binding : Unlike private collection, books in libraries are to be used by successive groups-be it a public library or an academic library-and hence n

Explain incremental models of policy-making, Question 1: (a) Describe t...

Question 1: (a) Describe the concept of "modelling' as applied in educational administration. Analyze this concept with respect to the synoptic and the incremental models of po

Guidelines for conducting a competitive negotiation , Guidelines for conduc...

Guidelines for conducting a competitive negotiation  The most important rule in conducting a complex negotiation is that you should have done the planning for it and you should

Weeding - library management, Weeding  In course of time some  books i...

Weeding  In course of time some  books in the library become outdated (e.g. books with statistics). Some time later research result into making information in earlier edition

Planning and organisation, PLANNING AND ORGANISATION: The major items ...

PLANNING AND ORGANISATION: The major items of work are classification and cataloguing. They are of a highly  technical nature and accuracy is the very essence of all technical

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd