Control charts

Control  charts  are  tools  used  for  monitoring,  controlling  and  improving processes over time. These are applicable to administrative processes.

1136_control chart.png

Figure: Control Chart

Steps to use control charts are:

1.  Collect initial data: This is the base line data for the process.

2.  Create the control chart: Plot the data. Calculate and plot the mean, lower and upper limits.

3.  Enter new data: A control chart is not just a snap shot of collected data.

It is a tool used over time to ensure that process remains in statistical control. Using the mean and control limits established by the baseline data, enter new data points and determine if they lie within or outside the control limits.

4.  Do not change the control limits based on new data unless the process changes. Completion of a process improvement effort to reduce random cause variation would be a reason to collect new data and establish a new mean and new control limits.


Related Discussions:- Control charts

Monitoring tasks for project quality management, Question : (a) Any pro...

Question : (a) Any project has a beginning and an end; without a formal closure process, project teams can fail to recognize the end and this can drag the project into unneces

Definitions of performance management, Question: a) Give two definition...

Question: a) Give two definitions of performance management. b) Explain the elements of a performance management system using the Storey & Sisson 1993 model. c) ‘Performa

What is buffering in risk management, What is Buffering in risk management?...

What is Buffering in risk management? Buffering: Buffering or slack is the allowance of additional cost, resources or time for example ‘just in case’ specific events or r

Give an example of critical path by activity and duration, Give an example ...

Give an example of demonstrating a network or critical path by given activity and duration. Activity                      Duration (Wks)                   Preceded by

How important are the stakeholders, Q. How important are the stakeholders? ...

Q. How important are the stakeholders? The most significant stakeholder of course is your client or customer. Conversely that perhaps in excess of one person that the sponsor a

Project, Choose a claim at one of the projects from your organization or an...

Choose a claim at one of the projects from your organization or another one and discuss the following topics (giving reasons for your answers). Submit your answers using PowerPoint

Processes as production systems, Processes as Production Systems A ...

Processes as Production Systems A production system refers to how an organization   organizes material flow using different process technologies. There are five major types

Project process cycle , Project process cycle  Any project professional...

Project process cycle  Any project professionally planned will target specified goals within the framework of time with available resources. The project passes through the foll

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd