Control and flexibility in contracts, Other Management

Assignment Help:

Control and Flexibility in Contracts

Contracts form the backbone of project management today. Project management techniques have developed in response to severe pressures such as unfavourable economic factors, inflation, uncertainties in the magnitude and duration of construction projects, and often unpredictable regulatory and environmental requirements. Executive control of a project can therefore be achieved only by controlling the progress of  contracts entered into for the project.

Major projects involving substantial construction are exceptional, one-time or at least infrequent. The popular mode is that you invest in capital works and execute the project through a single entity created for the implementation of the specific project.

The single entity is the project team, which in turn is led by a designated project manager dedicated to the project. This team should be established early in the development of the project concept and be given responsibility for  the  complete  project  life  cycle  from feasibility;  through  schematics, design, and procurement. In this way, managerial unity is established early in the project.

The single entity model can be achieved in three different ways, each way being a contracting mode for an entire project:

1. Award of a single contract (either Lump sum Fixed price or Engineering Procurement Construction (EPC), for the implementation of the project after the basic design of the project is finalised.

2. D-B (Design and Build) mode of contracting 

3. D-B-B (Design, Bid and Build) mode of contracting 


Related Discussions:- Control and flexibility in contracts

Problems in ordering, Problems in Ordering, Procurement and Receipt: O...

Problems in Ordering, Procurement and Receipt: Ordering and procurement of periodicals are very much inconvenienced due to different locations of their publishers. If the  lib

The computer misuses and cybercrimes that are punishable, QUESTION 1 Wh...

QUESTION 1 What are the principles that one should take into consideration when dealing with data protection? QUESTION 2 What are the institutions set up for the protec

Need and purpose of library classification, NEED AND PURPOSE OF LIBRARY CLA...

NEED AND PURPOSE OF LIBRARY CLASSIFICATION: Library classification invariably requires written has of damps and their subdivisions arranged in a systematic way along with corr

Explain clearly the knowledge management processes, QUESTION 1 Explain ...

QUESTION 1 Explain how the Wiig Knowledge Management model is related to the Nonaka and Takeuchi model QUESTION 2 Explain clearly the three major stages of an integrate

Managerial Economics, Explain the discounting principle. using the discount...

Explain the discounting principle. using the discounting principal calculate the present value of an annuity of five years at rs.500 payments made at the end of each of the next fi

Non-conventional-modern forms, Non-Conventional-Modern Forms: In many ...

Non-Conventional-Modern Forms: In many western countries, modern and sophisticated forms of library catalogue are slowly replacing the card catalogue. Some of these forms a

Investment management, You are a manager in the investment industry, whose ...

You are a manager in the investment industry, whose role is to provide investment portfolio advice and managementto a client, who is your investorprincipal. You should identify t

Binding and preservation work, BINDING AND PRESERVATION WORK: Preserva...

BINDING AND PRESERVATION WORK: Preservation and binding are those aspects of librarianship that have frequently been neglected. It is generally acknowledged that in the presen

Incentives, I ncentives These are rewards given when vendor/contractor...

I ncentives These are rewards given when vendor/contractor exceeds your expectation. Incentives should increase contractor?s profit. Incentives can be categorised as:

Subject access to opac, Subject Access to OPAC   The typical OPAC inter...

Subject Access to OPAC   The typical OPAC interaction process requires the matching or crude translation of user vocabulary to system vocabulary. It became apparent that the am

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd