Control and flexibility in contracts, Other Management

Assignment Help:

Control and Flexibility in Contracts

Contracts form the backbone of project management today. Project management techniques have developed in response to severe pressures such as unfavourable economic factors, inflation, uncertainties in the magnitude and duration of construction projects, and often unpredictable regulatory and environmental requirements. Executive control of a project can therefore be achieved only by controlling the progress of  contracts entered into for the project.

Major projects involving substantial construction are exceptional, one-time or at least infrequent. The popular mode is that you invest in capital works and execute the project through a single entity created for the implementation of the specific project.

The single entity is the project team, which in turn is led by a designated project manager dedicated to the project. This team should be established early in the development of the project concept and be given responsibility for  the  complete  project  life  cycle  from feasibility;  through  schematics, design, and procurement. In this way, managerial unity is established early in the project.

The single entity model can be achieved in three different ways, each way being a contracting mode for an entire project:

1. Award of a single contract (either Lump sum Fixed price or Engineering Procurement Construction (EPC), for the implementation of the project after the basic design of the project is finalised.

2. D-B (Design and Build) mode of contracting 

3. D-B-B (Design, Bid and Build) mode of contracting 


Related Discussions:- Control and flexibility in contracts

Subject headings and catalogue entries - coordinating work, Subject Heading...

Subject Headings: The coordinator must ensure correctness and consistency  in the subject headings used. The subject headings for the  document as a whole and for Cross Refer

Principles and practices of Management , Mr. Vincent, the Manager of a larg...

Mr. Vincent, the Manager of a large supermarket, was taking a management course in theevening programme at the local college. The Professor had given an interesting but disturbingl

Requirements for direct contracting, Requirements for direct contracting  ...

Requirements for direct contracting  Let us now look at the requirements for direct contracting:    The requirement of direct contracting should be such that it can be ju

Stack -circulation area in library building, Stack -Circulation Area in lib...

Stack -Circulation Area in library building-library managenent Stacks are the storage spaces for the various types of documents kept in a library. The types of documents gener

The kardex system - , The Kardex System: This system was introduced by...

The Kardex System: This system was introduced by the Remington Rand of India, Ltd. It is a type of visible record system maintained in a steel filing cabinet. Each unit cabine

Define the term safety culture, Question 1: (a) The accident rate of t...

Question 1: (a) The accident rate of two companies of similar size and producing identical product is found to differ. Explain possible reasons for this difference. (b) Th

Describe the six basic stages of tqm, Question A) Write short notes on the...

Question A) Write short notes on the Quality planning an element of Quality management Question B) What are the steps to the Fade QI model? Question C) Quality costs are

Periodicals procurement, PERIODICALS PROCUREMENT: We have dealt with t...

PERIODICALS PROCUREMENT: We have dealt with the selection of periodicals. Logically, the next step is procurement of the selected periodicals.  Hence,  this section is devoted

Mr. Vincet case study, 1.Critically analyze Mr. Vincent’s reasoning. 2. If ...

1.Critically analyze Mr. Vincent’s reasoning. 2. If you were the professor and you knew what was going through Vincent’s mind, what would you say to Vincent

Important qualities and skills required of negotiators, QUESTION 1 Nego...

QUESTION 1 Negotiators are likely to make systematic errors while processing information. Discuss the cognitive biases that are likely to hold back the performance of negotiato

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd