Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Sub-base for concrete carriageway - non-strength provider, Sub-base for con...

Sub-base for concrete carriageway - non-strength provider Essentially sub-base for a concrete carriageway is provided for the below reasons: (i)  It provides aneven and smo

Construction material, 4. Calculate the loose volume of material needed to ...

4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench

Calculate the poissons ratio, Calculate the Poissons Ratio: In separat...

Calculate the Poissons Ratio: In separate experiments, Young's Modulus and Rigidity Modulus of a material have been determined as 120 GPa and 50 GPa respectively. Calculate th

Water treatment, what is filtration membrane, is it''s type mechanism

what is filtration membrane, is it''s type mechanism

Pavement width - geometric design of roads, Pavement Width: The pavem...

Pavement Width: The pavement widths commonly adopted are : Single lane                 :           3.75 m Intermediate lane     :           5.5 m Two lane

Find the settlement at the centre and at edge of the footing, A load of 300...

A load of 3000 kN is being taken by a square column footing. Side of the column is 3 m, footing rests on a silty soil with a Poisson's ratio = 0.3. Modulus of elasticity of the soi

Protection of lorry on the line, i. On single line by one or two men as req...

i. On single line by one or two men as required following and proceeding the lorry at a distance of 600 m. on the BG and 400 m. on the MG & NG carrying a banner flag across the tra

Surveying, Use of optical square in chain surveying?

Use of optical square in chain surveying?

Reinforced Concrete Design, Design a continuous one-way solid slab supporte...

Design a continuous one-way solid slab supported on beams spaced at 4.2m o.c. the width of the beam is 300mm, leaving clear slab spans of 3.9. The slab carries a uniform DL= 6 KPa.

What is diversion tunnel in a dam, When a dam is to be built, a diversion t...

When a dam is to be built, a diversion tunnel is usually bored by solid rock next to the dam site to bypass the dam construction site. The dam is built while the river flows by the

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd