Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
QuestionIf on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works? AnswerThis is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue. The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers. This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test. The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-
(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures. (ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?
Draw the shape of the Pressure line. Solution The locations of resultant force at sections A-A, B-B and C-C have already been determined. Joining these locations, we can dr
Q. Necessity of air valves in pressurized pipelines? Air valves are broadly categorized into two major types: single air valves and double air valves. Single air valve comprise
Sub-surface Drainage: Sub-surface drainage is intended to take away the water seeping through the pervious layers of the soil, causing a high water table, or in cut slopes of
Question What is the sucker deck principle for changeable depth bridge decks ? Answer For a variable depth bridge deck, depth of continuous multi-span bridge deck is greate
A piece of clay taken from a sampling tube has a wet weight of 1.553 N and volume of 95.3 cm 3 . After drying in an oven for 24 hours at 105°C, its weight 1.087 N. Suppose the spec
BRIEFLY EXPLAIN THE CLASSIFICATION OF ROCKS
Bronze is an alloy of which materials? Answer : Bronze is an alloy of copper.
Explain the term - Uniaxial - Biaxial -Triaxial Prestressing These terms refer to cases when the concrete is prestressed in only one direction, in two mutually perpendicular di
Determine the horizontal abutment reaction of a rectangular portal frame under increasing central concentrated load
Determine the uses of Screw connectors Screw connectors are normally used to splice large-diameter high-tensile strength bars. The bars are threaded at the ends and a sheet-me
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd