Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
QuestionIf on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works? AnswerThis is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue. The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers. This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test. The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-
(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures. (ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?
is the seismic joints like falling joints ? thanks :)
Soil pressure enhances with depth due to the overburden or self-weight of the soil and because of loads imposed upon the soil. For example, the pressure variation below the dept
Q. What is the minimum prescribed track structure for LWR / CWR on Broad Gauge? Ans.- 1. General - The minimum length of LWR depends upon - i. Range of temporary variati
Define Reinforcing Steel - Limitations of Ultrasonic System? The sound velocity measurement taken parallel to the reinforcing bars embedded in the concrete will be markedly hig
Cut and Fill Calculation Using Cross Section Method
reparation of subgrade in sqm for a road of span 12 km and width 5.25m,with shoulders of 0.75m span on both the sides...considering extrawidening too......plz help...i m preparing
#how are manholes mantained
What is the difference between shear and tensile strength? Ans) Tensile Strength for a Bolt is explained by applying a Force along it long axis. Shear Strength for a Bolt is exp
length of the line measured with 20m chain found to be 250m.calculate true length if the chain was 10cm long
Q. Residual stresses in steel after welding? Considerable residual stresses are persuaded in connecting steel members after welding operation. Local temperature of steel where
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd