Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
QuestionIf on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works? AnswerThis is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue. The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers. This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test. The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-
(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures. (ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?
explain the importance of following standard procedure
Q. What is Unimat Machine? The machine has got 16 independently tiltable tamping tools which enable the machine to work on points and crossing as well as on plain track. The ma
Treatment plant - sewer construction: Problem: How many kg of primary and secondary dry solids needs to be processed daily from the treatment plant? Solution An a
What do you understand by Pressure line If we determine the locations of resultant force at various sections of a pre-stressed beam, as in Example, we can draw a curve showing
How muct the cost the Mettallis Strips?
A masonry retaining wall of trapezoidal section with the vertical face on the earth side is 1.5 m wide at the top and 3.5 m wide at the base and is 5.0 m high. It retains a sand fi
Explain Flow Measurement with Weirs Fixed plates positioned vertically in an open channel over which flow is directed through an opening. The opening linear distance is termed
Good evening. I have two homework projects from the Soil Mechanics. I am interesting if anybody can solve them.
Wind Force acting on truss
influence diagram with example
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd