Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

How do we calculate absolute pressure, Absolute is equivalent to gauge pres...

Absolute is equivalent to gauge pressure plus atmospheric.

State the needs for high strength steel and concrete, State the Needs for h...

State the Needs for high strength steel and concrete In  prestressed  concrete construction, tendons have 3  small area of cross-section compared  to the cross-sectional  area

Water or hydraulic horsepower (whp), Water Or Hydraulic Horsepower (whp) ...

Water Or Hydraulic Horsepower (whp) The work performed by a pump is a function of the head added by the pump (h A ), the flow rate required (Q) and the mass of the fluid (accou

Define compression - actions in pot bearings, Define Compression - Actions ...

Define Compression - Actions in POT Bearings? Vertical load is carried through the piston of the bearing and it is resisted by the elastomeric pad. Elastomer is incompressible,

Chain survey, Instruments used in chain survey

Instruments used in chain survey

Beam to column connection, what are the characteristics of the beam to colu...

what are the characteristics of the beam to column connection?

Expansion jiont, some expansion joint(10 mm- 20 mm) on my basement roof.rai...

some expansion joint(10 mm- 20 mm) on my basement roof.rain water leakage in basement i want the solution of expiation joint and water leakes.

Determine the thickness of flexible pavement layer, Determine the thickness...

Determine the thickness of flexible pavement layer 2 given the following:  FACTS: Total Structural Number required = 7.0 Total number of layers = 2 Layer 1 consists of

Calculate the horizontal distance, Calculate the Horizontal Distance A ...

Calculate the Horizontal Distance A surveyor's total station measured slope distance near station 3245+26.35 is recorded as 437.380-m with a zenith angle of 118º 48' 07" and a

Prime coat - road pavements, Prime Coat: A prime coat is the applicat...

Prime Coat: A prime coat is the application of a low viscosity binder, usually a bituminous emulsion, to a gravel, WBM or WMM surface, to enable the binder to fill up the voi

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd