Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Internal energy, For a system   Q =W+ ΔE where ΔE is the change in E,...

For a system   Q =W+ ΔE where ΔE is the change in E, the stored energy in the  ΔE system. E has various forms   1. Kinetic Energy 2. Potential Energy Work do

State the design process of prestressed concrete, State the Design process ...

State the Design process of Prestressed Concrete Most of the times, the design process is an interactive and trial procedure in which the cycle of analysis - design - analysis

Explain precedence relationships - construction management, Explain the Pre...

Explain the Precedence Relationships a. Finish-to-Start - the most common, the predecessor activity must finish before the successor activity can start b. Finish to Finish

Beneficial points of sliding bearings over roller bearings, What are key be...

What are key beneficial points of sliding bearings over roller bearings ? In roller bearing for a given movement a roller bearing exhibit modify in pressure centre from its un

Calculates the energy required, Write a program called, A1Q1, that reads a ...

Write a program called, A1Q1, that reads a single letter.   It will then display the corresponding ASCII code of the letter and prints the next character and the character which is

Determine the variation of safe bearing capacity of soi, State the algebrai...

State the algebraic equations showing the variation of safe bearing capacity of soil (for clay and sand to be given separately) in shallow foundation with: (i) depth of foundati

Determine difference between stations in feet and in station, The survey ha...

The survey has identified the beginning and ending points along an urban arterial highway that require new sidewalks. The first station is located at 5+88 and the second station is

What is n-value of standard penetration test, Define and discuss the variou...

Define and discuss the various factors that help decide the number and depth of bore holes needed for subsoil exploration. What is 'N-value' of Standard Penetration Test? How do

Fly levelling, what is meant by fly levelling and when it is carried out ?

what is meant by fly levelling and when it is carried out ?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd