Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
QuestionIf on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works? AnswerThis is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue. The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers. This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test. The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-
(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures. (ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?
Define Compression - Actions in POT Bearings? Vertical load is carried through the piston of the bearing and it is resisted by the elastomeric pad. Elastomer is incompressible,
Define the meaning of Grout - Concrete Grout should be made with any type of recommended cement and using water of a required quality. If very large size ducts are to be groute
Airport Lighting: Lighting of Approach to Runway A good system of identification of the runway when landing is to provide six transverse cross-bars of lights placed a
Solve the following three questions of the beam ABCD. Note that A is a fixed end; B is apin connection; C is a roller support; and D is a free end. 1) Sketch the quantitative
Q. Corner reinforcement for concrete pavement? Let's consider a panel of concrete slab without any load transferring devices at it edges. When concrete panel is subjected to tr
Explain Influence lines-reactions 1. Remove the support under investigation 2. Displace the beam vertically a distance of 1 unit. The resulting beam shape will be the sha
Raised Check Rails for obtuse crossing In order to provide guided path way in throat portion of 1 in 8 1/2 BG obtuse diamond crossing, the check rails are raised by welding of
if the WBM Road is constructed with 80mm , 40mm metal what will be the depreciation factor per year, how much thickness of the layer will be reduced per year due to trafic and rai
how surface water can be controlled in road pavement
Problems on Roof truss
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd