Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
QuestionIf on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works? AnswerThis is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue. The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers. This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test. The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-
(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures. (ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?
Define Abrasion - underwater inspection of bridge? Deterioration of substructures by abrasion is caused by wave action, the velocity of the currents and the action of suspended
Define Circular Channels Flowing Partially Full Two sets of curved lines on the Circular Channel Ratios figure (discharge Q/Q full and velocity v/v full ). 1. "n" variabl
State the method of Pre- Tensioning It is a method of prestressing concrete in which tendons are stretched or tensioned before concreting. In this form of construction, concr
Ask quA contractor has both a 3-cy and a 5-cy shovel in the equipment fleet. Select the minimum size shovel that will excavate 450,000 bcy of common earth in a minimum of 120 worki
How to calculate point of contraflexion on an overhanging beam with udl
what is the water bound macadam road
Write some appplications of lagrange''s mean value thorem
reinforcement.
This is more likely in to Aerospace engineering.. So if there's anyone whose doing his/her major or have any skills regarding that field please help me with this problem. :) a)
Q. Energy absorbed in heeling during vessel berthing? When a vessel berths on a fender system at a pier, point of contact of berthing ship can be below or above the centre of
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd