Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

P.h.e, procedure for designing of sewage scheme

procedure for designing of sewage scheme

Soil mechanics, Hi, i really need help to done my assignment i have done so...

Hi, i really need help to done my assignment i have done some part but in that case i need professional advice to finish my task. could you please let me know if you can help me. t

Total station, describe in detail the various parts of a total station

describe in detail the various parts of a total station

Design approach for the spacing of min-piles, Design approach for the spaci...

Design approach for the spacing of min-piles For close spacing of min-piles, it would provide substantial cost savings with reduction of pile cap size. Though close spacing of

State about the pre-tensioned concrete beam, State about the pre-tensioned ...

State about the pre-tensioned concrete beam A pre-tensioned concrete beam, 200 mm wide and 300 mm deep, is prestressed by straight wires carrying an initial force of 150 kN at

Soil mechanics, what is the total volume required for the gravel material o...

what is the total volume required for the gravel material of 6.5mx2314mx0.1m with a relative density of 2.919 and a loose bulk density of 1668kg/m3

Determine the types of losses of prestress, Determine the types of losses o...

Determine the types of losses of prestress A loss of prestress will affect the stress distribution on a section of the member. It is therefore necessary to estimate the probabl

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd