Construction of embankment, Civil Engineering

Assignment Help:

Construction of Embankment:

The following steps describe embankment construction :

(a) The ground is cleared and grubbed and all vegetation, grass, roots, etc. are removed.

(b) The original ground, if loose, is compacted by loosening the soil, adding water and rolling.

(c) The embankment soil is deposited in layers of about 25 cm loose thickness so as to get a compacted thickness of not higher than 15 cm.

(d) The moisture content in the soil should be brought to the optimum, by adding extra water or allowing the moist soil to aerate.

(e) Rolling is done by a road roller giving sufficient number of passes such that the desired density is achieved.

(f) The alignment, cross-section and levels are controlled by previously set temporary Bench Mark pillars and pegs.

(g) It is a good practice to construct the layers of the embankment also to the final camber/cross-slope of the pavement.

(h) The top 300-500 mm of the embankment, known as the sub-grade, is generally made up with soils which are better than that used in the body of the embankment. The density to which the sub-grade soil is compacted is also higher than in the rest of the embankment.


Related Discussions:- Construction of embankment

Laplace transform, Using Laplace transfom, the following differential equat...

Using Laplace transfom, the following differential equation d y dy dt reduces to the algebraic equation of the form Resolve y(s) into partial fractions

The material that have lowest resistivity is , The material that have lowes...

The material that have lowest resistivity is Answer: Silver is the material

Determining the amount of pre-camber, 1. Domes - You are a construction man...

1. Domes - You are a construction manager in the UAE in charge of a project that involves constructing domes.  Discuss briefly, giving examples, a range of different types of dome

Quadratics.., applying quadratics in civil engineering

applying quadratics in civil engineering

Determine the dimension of the vertical side walls, Determine the dimension...

Determine the dimension of the vertical side walls for a rectangular open channel designed to convey 150 cfs of storm water runoff. The runoff is collected in the parking lots and

Determine the uses of prestressed concrete poles, Determine the uses of Pre...

Determine the uses of Prestressed concrete poles Prestressed concrete poles are commonly mass produced and are used in most countries for power transmission, antenna masts etc

Manage civil work design, Ask question #Minimum 1Make a detailed list of al...

Ask question #Minimum 1Make a detailed list of all constraints and requirements to the bridge design00 words accepted#

Benefits of analysis of prestress and bending stresses, Normal 0 ...

Normal 0 false false false EN-IN X-NONE X-NONE

Time to remove formwork to cater for early thermal movement, Q. Time to rem...

Q. Time to remove formwork to cater for early thermal movement? Let's take a circular column as an illustration to explain effect of internal restraint to thick sections.  W

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd