4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench pipe = 300 mm diameter.
o Width of trench = 600 mm o Depth of trench = 1000 mm o Bank m 3 = 2150 kg/ m 3 o Loose m 3 = 1935 kg / m 3

Related Discussions:- construction material

Estimate the jam density in one lane of trucks, At a large port facility ne...

At a large port facility near New York City tractor-trailer trucks are lined-up in long queues as their drivers wait to have their containers inspected and documents processed.  As

I have a take home quiz, Hello I have a take home final needs be ordered, d...

Hello I have a take home final needs be ordered, do you have very well skilled professionals to make it?

Purpose of setting minimum amount of longitudinal steel area, Q. Purpose o...

Q. Purpose of setting minimum amount of longitudinal steel areas for columns? In some design codes it specifies that area of longitudinal steel reinforcement must be not less

Illustrate bituminous surfacing over concrete structures, Q. Illustrate Bit...

Q. Illustrate Bituminous surfacing over concrete structures? Usage of bituminous surfacing over concrete structures (for instance existing concrete roads) is widespread to impr

Explain forty-five degree spread rule for driven piles, Q. Explain Forty-fi...

Q. Explain Forty-five degree spread rule for driven piles ? For driven piles the length of piles driven into the ground is generally based on dynamic driving formula such as Hi

Physics, about lenses & mirrors for assignment

about lenses & mirrors for assignment

Main purpose of conducting load test for piling works, Question What is...

Question What is main purpose of conducting load test for piling works ? Answer Pile load test gives information on ultimate bearing ability but not settlement be

Water absorption test for precast concrete pipes, Purpose of carrying out w...

Purpose of carrying out water absorption test for precast concrete pipes Cement will mix with more water than is essential to ultimately combine during hydration of cement pas

Functions of a column in a building, What are the functions of a column in ...

What are the functions of a column in a building? Ans) A column is used to handle the weight of the roof and/or the upper floors. Now days, many columns are used for decorative

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd