4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench pipe = 300 mm diameter.
o Width of trench = 600 mm o Depth of trench = 1000 mm o Bank m 3 = 2150 kg/ m 3 o Loose m 3 = 1935 kg / m 3

Related Discussions:- construction material

Specification of flooring for heavy repair shed, Q. Specification of Floori...

Q. Specification of Flooring for heavy repair shed? Scope for use - For flooring for heavy repair shed, Surface hardened concrete flooring can used. In this type of flooring,

Function of a separation membrane amid concrete pavement, Question What...

Question What is main function of a separation membrane amid concrete pavement slab and sub-base ? Answer Division membrane between concrete pavement slab and sub-bas

Insulating washer between steel bolts and aluminium plates, Q. Insulating w...

Q. Insulating washer between steel bolts and aluminium plates? Corrosion of aluminium can be activated by putting it in contact with another metal in the presence of water. Thi

Show the functions of diaphragm walls, Q. Show the Functions of diaphragm w...

Q. Show the Functions of diaphragm walls? The functions of diaphragm walls are as follows: (i)  It is designed to maintain soils during the construction of underground

Concrete, What is Under vibration of fresh concrete?

What is Under vibration of fresh concrete?

Explain the system curves - pumping system, Explain the System Curves - Pum...

Explain the System Curves - Pumping System Non-linear plot beginning on the y-axis at the Total Static Head (TSH) and plotted primarily based on the h f .

Explain the design criteria for sedimentation basin, Explain the Design Cri...

Explain the Design Criteria Sedimentation basin Surface Loading rate (or overflow rate), Vo = Q/A (flow rate/surface area) Detention time t or ? = V/Q (Volume /Flow rate)

Free- fall concrete placement in bored piles, Q. Free- fall concrete placem...

Q. Free- fall concrete placement in bored piles? Based on the research by STS Consultants Ltd it was found that concrete placed by free falling below 120 feet will not suffer f

Explain the purpose of embedding puddle flange, Purpose of embedding puddle...

Purpose of embedding puddle flange inside the walls of closed valve chambers When valves are closed to stop water flow in a pipeline, a thrust is produced along the direction o

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd