4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench pipe = 300 mm diameter.
o Width of trench = 600 mm o Depth of trench = 1000 mm o Bank m 3 = 2150 kg/ m 3 o Loose m 3 = 1935 kg / m 3

Related Discussions:- construction material

Key reasons for conducting pull-out tests, Question What are key reason...

Question What are key reasons for conducting pull-out tests for soil nails ? Answer There are largely four bases for this examination- (i) To verify and verify bo

Functions of cap block drive cap and pile cushion, Question What are ma...

Question What are main functions of cap block drive cap and pile cushion in driven piles? Answer Cap block is fit amid hammer end and drive cap to manage hammer bl

Enumerate the term - failure due to crushing of concrete, Enumerate the ter...

Enumerate the term - Failure Due to Crushing of Concrete Over reinforced pre-stressed concrete members, provided with a large amount of pre-stressing steel or relatively small

Total station, describe in detail the various parts of a total station

describe in detail the various parts of a total station

State the modulus of elasticity of concrete, State the Modulus of Elasticit...

State the Modulus of Elasticity of Concrete The Young's modulus of elasticity of concrete is primarily influenced by the elastic properties of the aggregate and to a lesser ex

Timber, charring of timber

charring of timber

Centroid, use of centroid in civil engineering

use of centroid in civil engineering

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd