4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench pipe = 300 mm diameter.
o Width of trench = 600 mm o Depth of trench = 1000 mm o Bank m 3 = 2150 kg/ m 3 o Loose m 3 = 1935 kg / m 3

Related Discussions:- construction material

Diaphragms necessary in concrete box girder bridges, Are diaphragms necessa...

Are diaphragms necessary in designing of concrete box girder bridges ?

Deflection of beam, a simply supported beam with concentric load

a simply supported beam with concentric load

Uses of alloys in daily life , What are the uses of alloys in daily life an...

What are the uses of alloys in daily life and how are alloys made? Ans) Alloying is not always done to make a 'superior' material, but to produce materials having a desired requ

Define underwater magnetic particle testing, Define Underwater Magnetic Par...

Define Underwater Magnetic Particle Testing? Underwater magnetic particle testing (UWMT) is a non-destructive testing suited for detection of surface cracks or discontinuities

Meaning, i want the meaning of crete

i want the meaning of crete

Radial contour, how to calculate distance for radial contour

how to calculate distance for radial contour

Load transfer mechanism, Question What is load transfer mechanism for p...

Question What is load transfer mechanism for paving blocks in pedestrian footway? Answer In Hong Kong, footway is as a rule designed with paving slabs or interlocking b

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd