4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench pipe = 300 mm diameter.
o Width of trench = 600 mm o Depth of trench = 1000 mm o Bank m 3 = 2150 kg/ m 3 o Loose m 3 = 1935 kg / m 3

Related Discussions:- construction material

Autocad-introduction, Autocad-Introduction Learning to use a CAD syste...

Autocad-Introduction Learning to use a CAD system is similar to learning a new language. It is necessary tobegin with the basic alphabet and learn how to use it correctly and

Types of stone masonary, random rubble coursed, suare rubble coursed and un...

random rubble coursed, suare rubble coursed and uncoursed, polygonal walling, flint walling

Determine about the lee-mccall system, Determine about the Lee-McCall syste...

Determine about the Lee-McCall system In the Lee-McCall system, high-tensile strength bars of diameter varying from 12 to 40 rnrn are used as tendons. These bars are threaded a

TicketID: EM135335A06, I only want Part 1 of this order, can you adjust the...

I only want Part 1 of this order, can you adjust the quote?

Simple bending, In case of simple bending after simply supported beam, deri...

In case of simple bending after simply supported beam, derive that M/I = s /y = E/R.

coursework (commercial management), Ask que1. Identify the risks involved ...

Ask que1. Identify the risks involved in this project related to cost in the perspective of the customer and analyse the probability of acceptance of such a project by customers. 2

Determine the value of the coefficient of permeability, Determine the value...

Determine the value of the coefficient of permeability A glass cylinder 5 cm internal diameter with a screen at the bottom is used as a falling head permeameter. The thickness

#title.cement factor, Aplease provide tables for each design mix and also t...

Aplease provide tables for each design mix and also the, high early strengh.l thanks

Linear algebra concept, Scenario: You are working for a structural engineer...

Scenario: You are working for a structural engineering firm and you have been assigned the task of computing the code checks on a new structural design. Though another commercial p

Define the precedence diagramming methods, Define the Precedence Diagrammin...

Define the Precedence Diagramming Methods a) Activity on Node (AON) with arrows for dependencies b) Uses all forms of precedence relationships

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd