4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench pipe = 300 mm diameter.
o Width of trench = 600 mm o Depth of trench = 1000 mm o Bank m 3 = 2150 kg/ m 3 o Loose m 3 = 1935 kg / m 3

Related Discussions:- construction material

Steel work design, 1) A building constructed from steelwork requires the fo...

1) A building constructed from steelwork requires the following sections to be designed: a. A beam carrying a characteristic permanent load of 11kN/m and a characteristic variable

Explain frame members effective lengths, Explain Frame Members Effective Le...

Explain Frame Members Effective Lengths a. Effective length is a product of an effective length factor (k) and the actual length of the column. b. k depends on the rel

Concrete surface finish - limitations of ultrasonic system, Define Concrete...

Define Concrete Surface Finish - Limitations of Ultrasonic System? The smoothness of the surface under test is important to ensure proper acoustical contact between the transdu

Explain the process of directed track maintenance, Q. Explain the process o...

Q. Explain the process of Directed Track Maintenance? DTM is a method to maintain the track is directed every day and not as a prescribed routine. DTM essentially consists of n

Obtain maximum positive moment in a span of continuous beam, Reason of load...

Reason of loading on alternative spans to obtain maximum positive moment in a span of a continuous beam To attain a maximum sagging moment in a span of a continuous beam, gene

Earth work in high embankments, Q. Earth work in high embankments? (a) ...

Q. Earth work in high embankments? (a) Borrow pits must not be dug close to telegraph poles, electric poles, level crossings, bridges a culverts, or within 800 meters of the bo

Explain a critical path - construction management, Explain a Critical Path ...

Explain a Critical Path The series of activities which determines the earliest possible date of project completion Usually defined as those activities with minimal or

Calculate equivalent uniform annual cost for the excavator, Calculate Equiv...

Calculate Equivalent Uniform Annual Cost for the Excavator An earthwork contractor is considering the purchase of a new excavator.  Based on 10% interest, the equivalent unifor

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd