4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench pipe = 300 mm diameter.
o Width of trench = 600 mm o Depth of trench = 1000 mm o Bank m 3 = 2150 kg/ m 3 o Loose m 3 = 1935 kg / m 3

Related Discussions:- construction material

Methods of contouring by grid points, the elevations of grid points for an ...

the elevations of grid points for an area as follows: 1 2 3 4 5 6 7 8 F 690 709 726 732 735 740 743 747 E 696 715 729 736 740 737 739 740 D 702 723 733 742 737 737 745 747 C 707 72

survey, what is fore bearing and back bearin

what is fore bearing and back bearing

Jacking face for pipe-jacking, Ground settlement occurs ahead or behind the...

Ground settlement occurs ahead or behind the jacking face for pipe-jacking? It's reported by Lake (1992) that settlements are expected at ground surface at a distance of 1-2 ti

Velocity distribution and flow formulae, Q. Velocity distribution and flow ...

Q. Velocity distribution and flow formulae? Variation in velocity along a vertical in channel cross section is known to follow logarithmic distribution, maximum velocity being

Perform a personal skills audit, Perform a Personal Skills Audit Your ...

Perform a Personal Skills Audit Your employer wishes you to become an effective and confident self-directed employee. With this in mind they have set you some tasks. These wil

Soil Mechanics, What relationship between Atterberg limits and cohesion

What relationship between Atterberg limits and cohesion

Topographical survey and preparation of drawings, Topographical Survey and ...

Topographical Survey and Preparation of Drawings: Topographical Survey for a road project consists of three sequential stages: (a) Reconnaissance Survey, including a study

. determine the permeability of the aquifer, An unconfined aquifer is calle...

An unconfined aquifer is called to be 32 m thick below the water table. A constant discharge of 2 cubic metres per minute is pumped out of the aquifer by a tubewell till the water

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd