4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench pipe = 300 mm diameter.
o Width of trench = 600 mm o Depth of trench = 1000 mm o Bank m 3 = 2150 kg/ m 3 o Loose m 3 = 1935 kg / m 3

Related Discussions:- construction material

Disparities b/w epoxy grout cement grout and cement mortar, Question What a...

Question What are the key disparities between epoxy grout cement grout and cement mortar ? Answer Epoxy grout contains of epoxy resin, epoxy hardener and sand or aggregates.

coursework (commercial management), Ask que1. Identify the risks involved ...

Ask que1. Identify the risks involved in this project related to cost in the perspective of the customer and analyse the probability of acceptance of such a project by customers. 2

Discuss about the post-tensioning systems, Discuss about the post-tensionin...

Discuss about the post-tensioning systems In most of post-tensioning systems, when the cable is tensioned and the jack is released to transfer prestress to concrete, the fricti

Ocf, location of hydrolic jump

location of hydrolic jump

Determine the size of the standpipe which should be used, A sample in a var...

A sample in a variable head permeameter is 8 cm in diameter and 10 cm high. The permeability of the sample is estimated to be 10 × 10 -4 cm/s. If it is desired that the head in th

Advantages of casings for mini-piles, Question Advantages of casings ...

Question Advantages of casings for mini-piles ? Answer Left-in casings for mini-piles have next advantages as follows- (i) recover resistance to corrosion of ma

Avoidance of designing acute angle of concrete pavement, Q. Avoidance of de...

Q. Avoidance of designing acute angle of concrete pavement The stress persuaded in acute angle corners of concrete pavement is far much higher than right-angle corners of the

Concrete technology, what is the actual quantity of water to be mixed in va...

what is the actual quantity of water to be mixed in various grade of concrete and also the size of gravel to be mixed with in RCC work. Also I want to know the difference between a

Chain survey, what are the obstacles in chain survey in brief

what are the obstacles in chain survey in brief

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd