4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench pipe = 300 mm diameter.
o Width of trench = 600 mm o Depth of trench = 1000 mm o Bank m 3 = 2150 kg/ m 3 o Loose m 3 = 1935 kg / m 3

Related Discussions:- construction material

What is the unit weight of water, In a pipette analysis, 0.5 N of dry soil ...

In a pipette analysis, 0.5 N of dry soil (fine fraction) of specific gravity 2.72 were mixed in water to form half a litre of uniform suspension. A pipette of 10 ml capacity was

An alternative test to confirm concrete strength, Question If concrete comp...

Question If concrete compression test not pass, So Schmidt hammer test will be adopted as an alternative test to confirm concrete strength ? Answer Schmidt hammer test is

Explain resultant force on a area of a vertical plane, Resultant Force on a...

Resultant Force on a Given Area of a Vertical Plane The resultant force is calculated from the average pressure: R = (AVERAGE Ρ)(A)

Define the ignitability - hazardous waste, Define the Ignitability - Hazard...

Define the Ignitability - Hazardous Waste - is a liquid with flash point - Not a liquid and capable of spontaneous and sustained combustion under normal conditions - Ign

Designing of pipe jacking, Question While designing of pipe jacking , ...

Question While designing of pipe jacking , what particular areas on pipe joints have to engineers make sure of? Answer While in pipe jacking, jacked pipes may well ha

#title., desirable properties in green concrete

desirable properties in green concrete

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd