4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench pipe = 300 mm diameter.
o Width of trench = 600 mm o Depth of trench = 1000 mm o Bank m 3 = 2150 kg/ m 3 o Loose m 3 = 1935 kg / m 3

Related Discussions:- construction material

Define the term- erection stresses, Define the term- erection stresses ...

Define the term- erection stresses The creep loss due to live load stress, erection stresses and other stresses of short duration may be ignored. The loss of prestress due to

Rcc and rbc, types mixing,curing,water cement ratio,qualities and workabili...

types mixing,curing,water cement ratio,qualities and workability

Brick mansory, Aim,materials or tools required,procedure for constructing e...

Aim,materials or tools required,procedure for constructing english bond bricks

Track design for line speed improvements, The objective of this module is:-...

The objective of this module is:- For the student to identify the track design issues and there relationships that will need to be considered in the development of a feasibil

Zero energy building, This is our final year project can u suggest some tip...

This is our final year project can u suggest some tips to do well...

BRIDGES, WHAT ARE THE DIFFERENT TYPES OF BRIDGES

WHAT ARE THE DIFFERENT TYPES OF BRIDGES

Mechanics problem, i am facing some problem in solving the problem of elong...

i am facing some problem in solving the problem of elongation due to self weight suspended from fixed support in the conical bar

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd