4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench pipe = 300 mm diameter.
o Width of trench = 600 mm o Depth of trench = 1000 mm o Bank m 3 = 2150 kg/ m 3 o Loose m 3 = 1935 kg / m 3

Related Discussions:- construction material

Concrete surface finish - limitations of ultrasonic system, Define Concrete...

Define Concrete Surface Finish - Limitations of Ultrasonic System? The smoothness of the surface under test is important to ensure proper acoustical contact between the transdu

Indian standard codes, Indian Standard Codes All of the major countrie...

Indian Standard Codes All of the major countries like India, UK, USA, and Australia have their own standards for material standards, design procedures, testing standards, and

Flow, what is maximum flood level

what is maximum flood level

Raft foundation, after formation of the soil under raft some area around th...

after formation of the soil under raft some area around the lift pit for example will be on tipping shape and some column placed in the same area the question how we place the col

Stop dead restriction, With a clear sketch indicate the system of protectio...

With a clear sketch indicate the system of protection of line for works of short duration where ‘ Stop dead restriction' need to be observed on a single line section on a BG track.

What is the meaning of concordant prestressing, Concordant Prestressing ...

Concordant Prestressing In this type of prestressing, tendons follow a concordant profile. The concordant profile of  tendons does not change the support reactions in a statica

Explain flow measurement with weirs, Explain Flow Measurement with Weirs ...

Explain Flow Measurement with Weirs Fixed plates positioned vertically in an open channel over which flow is directed through an opening. The opening linear distance is termed

Loading and unloading cycles for soil nails, In carrying out pull-out tests...

In carrying out pull-out tests for soil nails, it generally requires the unloading and loading of soil nails of several cycles up to 80% of ultimate tensile strength of soil nails.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd