4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench pipe = 300 mm diameter.
o Width of trench = 600 mm o Depth of trench = 1000 mm o Bank m 3 = 2150 kg/ m 3 o Loose m 3 = 1935 kg / m 3

Related Discussions:- construction material

Define limitations of radiography - inspection of bridge, Define Limitation...

Define Limitations of Radiography - Underwater Inspection of Bridge? i. Radiography is a costly and time consuming method, which re- quires extensive safety measures to be adop

Moment of Inertia of a T Beam, Calculate the moment of inertia and section ...

Calculate the moment of inertia and section modulus (top and bottom of the beam) about the z-axis of the beam cross section of Fig.

Explain pressure balance method and compressed air method, Pressure balance...

Pressure balance method vs. compressed air method in pipe jacking Pressure balance method generally requires the use of mechanically operated tunnel-boring machine at its cutti

Acidity and alkalinity - chemical characteristics of water, Acidity and Alk...

Acidity and Alkalinity - Chemical Characteristics of Water Acidity: Capacity to neutralize bases and is a measure of acids in water. Acidity is measured by titrating the s

State the total load which the raft can support, A raft, 8 m × 24 m, is fou...

A raft, 8 m × 24 m, is founded at a depth of 4 m in sand with a value of N = 20 up to great depth. Illustrate the total load which the raft can support? What will be the total c

Determine the required stirrup size and spacing requirement, A rectangular ...

A rectangular concrete beam is subjected to a factored design shear force of 200 kips.  For the beam shown below, determine the required stirrup size and spacing requirement. H = 3

Foundation, Explain briefly shallow foundation?

Explain briefly shallow foundation?

Total volume of soil that excavated from the borrow area, Project specifica...

Project specifications require a relative compaction of 95% (modified Proctor).  Construction of a highway embankment requires 10,000-yd 3 of fill.  The borrow soil has an in-situ

Trigo, A pole which leans 11o from the vertical toward the sun casts a shad...

A pole which leans 11o from the vertical toward the sun casts a shadow 12m long when the angle of elevation of the sun is 40o. Find the length of the pole

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd