4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench pipe = 300 mm diameter.
o Width of trench = 600 mm o Depth of trench = 1000 mm o Bank m 3 = 2150 kg/ m 3 o Loose m 3 = 1935 kg / m 3

Related Discussions:- construction material

Forensic structural engineering, i need journals or articles of forensic st...

i need journals or articles of forensic structural engineering

Determine the term - final tension, Determine the term - Final Tension ...

Determine the term - Final Tension The tension in tendons after losses of prestress have taken place is called as final tension. Final tension is taken to be corresponding  to

Grades of concrete, mixing ratio of different type of ready mix concrete.(R...

mixing ratio of different type of ready mix concrete.(RMC)

Estimating, a 45 cm deep roof beam is provided on 30 cm wall of a room size...

a 45 cm deep roof beam is provided on 30 cm wall of a room size 3.0m*5.0m . calculate the quantity of steel required in beam on percentage basis.

Define continuity equation, Define Continuity Equation Mass in fluid sy...

Define Continuity Equation Mass in fluid systems is always conserved.   Ρ 1 v 1 = ???? 2 v 2   If the fluid density is the same at both points in the flow, the continui

Longitudinal steel – an enhancement of shear strength, Q. Longitudinal stee...

Q. Longitudinal steel – an enhancement of shear strength ? Furthermore to shear resistance provided by shear reinforcement, shear forces in a concrete section is also resisted

Length is constructed in first phase of construction, In construction of a ...

In construction of a two-span bridge (span length = L) by using span-by-span construction, why is the length of about 1.25L bridge segment is constructed in first phase of construc

Inadequate pile founding level, Reasons of common occurrence of "inadequate...

Reasons of common occurrence of "inadequate pile founding level" in piles of piers The most severe load on piers usually is the horizontal load owing to berthing and mooring o

Timer, grading classification

grading classification

Measure the ultimate settlement due to pumping, A clay stratum of 18 metres...

A clay stratum of 18 metres thickness was found above a sand stratum when a boring was made. The clay was consolidated under the present overburden pressure. The hydrostatic pressu

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd