4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench pipe = 300 mm diameter.
o Width of trench = 600 mm o Depth of trench = 1000 mm o Bank m 3 = 2150 kg/ m 3 o Loose m 3 = 1935 kg / m 3

Related Discussions:- construction material

Concrete, types of concrete and its uses

types of concrete and its uses

What depth is the intensity of pressure zero, A retaining wall with a smoot...

A retaining wall with a smooth vertical back retains a purely cohesive fill. Height of wall is 12 m. Unit weight of fill is 20 kN/m 3 . Cohesion is 1 N/cm 2 . What is the total act

Degree, what classes do you have to take and what are some school options?

what classes do you have to take and what are some school options?

#title beam design, how to calculate loads acting on a simple supported bea...

how to calculate loads acting on a simple supported beam of 220width by 425 depth #Minimum 100 words accepted#

State the process to calculate the transmission length, State the process t...

State the process to calculate the Transmission Length It is the distance required at the end of a concrete member for developing the maximum tendon stress by bond.

Define the fatigue failure - underwater inspection of bridge, Define the Fa...

Define the Fatigue failure - underwater inspection of bridge? Fatigue failure results in the fracture of structural members as a consequence of repeated high loading.  Fatigue

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd