4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench pipe = 300 mm diameter.
o Width of trench = 600 mm o Depth of trench = 1000 mm o Bank m 3 = 2150 kg/ m 3 o Loose m 3 = 1935 kg / m 3

Related Discussions:- construction material

Determine the soil shrinkage, Soil at a borrow area has a total unit weight...

Soil at a borrow area has a total unit weight of 120-PCF and a water content of 15 percent.  The soil from the borrow area will be used as structural fill and compacted to an avera

Explain the statements about the critical path method, 1. Determine a netwo...

1. Determine a network diagram method that uses only finish-to-start relationships and may use dummy activities to define logical relationships.  2.  Precedence diagr

Why nautical mile is different from statute mile, One nautical mile is desc...

One nautical mile is described by one latitude minute of arc (there are 60 like minutes to a degree). This equals 1852 meters, and roughly (but coincidentally) 2000 yards or 6000 f

Explain the watersheds - hydrology, Explain the Watersheds - Hydrology ...

Explain the Watersheds - Hydrology The surface area on which runoff generated will flow to a common stream or body of water by gravity. Often separated by higher elevations/top

What is rail lubricators, Q. What is Rail Lubricators? 1. P & M type of...

Q. What is Rail Lubricators? 1. P & M type of lubricators - These lubricators can be used for lubrication of FF rails as well as BH rails. 2. Elgi grease pump - Elgi Bucket

Foundation, Explain briefly shallow foundation?

Explain briefly shallow foundation?

Designing of roadbase material, Question In General Specification for C...

Question In General Specification for Civil Engineering Works, designing of roadbase material is based on recipe approach. Give reason. Answer Designing of roadbase

Determine the analysis of presress, Analysis of presress  In pre-stress...

Analysis of presress  In pre-stressed structural elements, stretched tendons are placed inside concrete. The tensile stresses of the tendons are transferred to concrete in the

Zero energy building, This is our final year project can u suggest some tip...

This is our final year project can u suggest some tips to do well...

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd