4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench pipe = 300 mm diameter.
o Width of trench = 600 mm o Depth of trench = 1000 mm o Bank m 3 = 2150 kg/ m 3 o Loose m 3 = 1935 kg / m 3

Related Discussions:- construction material

science and materials, the behaviour of structural materials using compara...

the behaviour of structural materials using comparative statement when they are formed into structural member

#title.cement factor, Aplease provide tables for each design mix and also t...

Aplease provide tables for each design mix and also the, high early strengh.l thanks

Engineering mechanics, Characteristics of couple #Minimum 150 words accepte...

Characteristics of couple #Minimum 150 words accepted#

Verify the optimum value of the spacing of the piles, A 16-pile group has t...

A 16-pile group has to be arranged in the form of a square in soft clay with uniform spacing. Neglecting end-bearing, verify the optimum value of the spacing of the piles in terms

Surveying, if bearing of AB is 190& that of CB is 260,the included angle AB...

if bearing of AB is 190& that of CB is 260,the included angle ABC is how?

Determine the statements about unit area or borrow pit, Determine the State...

Determine the Statements about Unit Area or Borrow Pit? Ans: I.  Sometimes called Average Depth II. Works well for volumes for building sites and surface mines III. Needs

Define fixed instrumentation - sounding or sensing devices, Define Fixed in...

Define Fixed instrumentation - Sounding or Sensing Devices? It is possible to monitor local scour at pier or abutment using fixed instrumentation as an alternative to the sound

Perform a personal skills audit, Perform a Personal Skills Audit Your ...

Perform a Personal Skills Audit Your employer wishes you to become an effective and confident self-directed employee. With this in mind they have set you some tasks. These wil

Purpose of reinforcement in concrete roads, Q. Purpose of reinforcement in ...

Q. Purpose of reinforcement in concrete roads? The major purposes of reinforcement in concrete roads are: (i)  To control the development and pattern of cracks in concrete p

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd