4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench pipe = 300 mm diameter.
o Width of trench = 600 mm o Depth of trench = 1000 mm o Bank m 3 = 2150 kg/ m 3 o Loose m 3 = 1935 kg / m 3

Related Discussions:- construction material

Railway bridge, how to measure the waterways of railway bridges

how to measure the waterways of railway bridges

Survey question, Sir morng..i know about WCB AND RB.With diagram..pls help ...

Sir morng..i know about WCB AND RB.With diagram..pls help me sir

Landing systems, Landing Systems: There are two basic types of landin...

Landing Systems: There are two basic types of landing, viz : (a) visual landing, when the weather conditions are favourable, and (b) instrumented landing, when the weat

Simply calculation, If i want to find D, and D=2a, then a=1-5 how can i s...

If i want to find D, and D=2a, then a=1-5 how can i show the ans is:2&4&6&8&10

Closing and opening of expansion joints and contraction join, Question ...

Question In case of for unreinforced concrete carriageway, what will succession of closing and opening of expansion joints and contraction joints? Answer Take a case t

engineering drawings, Triangular prism axis is parallel to both HP and V

Triangular prism axis is parallel to both HP and VP

Mixed ground with soils and boulders, Ground settlement occurs when pipe-ja...

Ground settlement occurs when pipe-jacking machine enters mixed ground with soils and boulders? The rate of cutting through soils is faster than cutting through boulders for pi

Determine about the prestressed concrete, Determine about the Prestressed c...

Determine about the Prestressed concrete Prestressed concrete is a special type of concrete in which internal stresses of a suitable nature, magnitude and distribution are int

3 wire leveling, can you give me some examples and problems in 3-wire level...

can you give me some examples and problems in 3-wire leveling?

WBM.., WHY WBM ROAD SURFACE RENEWE?

WHY WBM ROAD SURFACE RENEWE?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd