4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench pipe = 300 mm diameter.
o Width of trench = 600 mm o Depth of trench = 1000 mm o Bank m 3 = 2150 kg/ m 3 o Loose m 3 = 1935 kg / m 3

Related Discussions:- construction material

Water transportation, Water Transportation: Water transport, in its va...

Water Transportation: Water transport, in its various forms, is one of the most efficient forms of transport, because of low fuel consumption, low environmental pollution and

Airport., draw a typical layout of airport ?

draw a typical layout of airport ?

Review of available records - underwater inspection, Review of available Re...

Review of available Records - Preparation for Underwater Inspection? Before taking up the underwater inspection, a detailed review of drawings and past report should be carried

Joints in box culverts and channels, Joints in box culverts and channels - ...

Joints in box culverts and channels - necessity of water tightness The joints for box culverts and channels must be capable of accommodating movements arising from moisture an

Coating on concrete – complete im-permeability to moisture, Q. Coating on c...

Q. Coating on concrete – complete im-permeability to moisture? In designing protective coating on concrete structures, stoppage of water ingress by the coating is generally req

For the plane area shown determine the first moments, for the plane area sh...

for the plane area shown determine the first moments with respects to the x & y axis & the location of the centroid

Compute the maximum allowable concentrated live load, Given for the section...

Given for the section shown in Figure, M * = 250 kNm, f sy = 500 MPa and f c ′ = 25 MPa. Compute A st and (if necessary) A sc . You may assume that eac

Define the cost per square foot of contact area, Define the Cost per Square...

Define the Cost per Square Foot of Contact Area The cost of concrete formwork is influenced by three factors: 1. Initial cost or fabrication cost that contains the cost of t

Engineering mechanics, Characteristics of couple #Minimum 150 words accepte...

Characteristics of couple #Minimum 150 words accepted#

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd