4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench pipe = 300 mm diameter.
o Width of trench = 600 mm o Depth of trench = 1000 mm o Bank m 3 = 2150 kg/ m 3 o Loose m 3 = 1935 kg / m 3

Related Discussions:- construction material

Dock wall and dry dock, Dock Wall and Dry Dock: Dock Wall Fig...

Dock Wall and Dry Dock: Dock Wall Figure gives the diagram of a dock wall. Figure: Mass Concrete Dock Wall Dry Dock Figure 9 gives the details

Application of bitumen to driven piles, Q. Application of bitumen to driven...

Q. Application of bitumen to driven piles? In a certain area of H-piles subjected to ground water table fluctuation, painting is occasionally applied on the surface of H-piles

Explain the wetted perimeter, Explain the Wetted Perimeter (P) The line...

Explain the Wetted Perimeter (P) The linear length of the interface between the fluid's cross-sectional plane edges in contact with the pipe or channel wall.

Surveying land, principle of working from whole to part

principle of working from whole to part

Test on specially moulded test piece, Test on specially moulded test piece ...

Test on specially moulded test piece The test piece shall be moulded by the manufacturer with identical compound and under identical vulcanizing conditions as used in manufact

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd