4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench pipe = 300 mm diameter.
o Width of trench = 600 mm o Depth of trench = 1000 mm o Bank m 3 = 2150 kg/ m 3 o Loose m 3 = 1935 kg / m 3

Related Discussions:- construction material

Finite Element Analysis- MATLAB problem, I am currently enrolled in a gradu...

I am currently enrolled in a graduate Civil Engineering course in Finite Element Analysis. The final assignment and project both deal with coding in MATLAB and I am having great di

Example for productivity analysis and improvement, Example for Productivity...

Example for Productivity Analysis and Improvement An excavator with a bucket capacity of 3-yd 3 has a standard production rate of 2,160-yd 3 for an 8-hour day.  The job site

Project management, know the planking and strutting for shallow excavation...

know the planking and strutting for shallow excavation

Mechanics problem, i am facing some problem in solving the problem of elong...

i am facing some problem in solving the problem of elongation due to self weight suspended from fixed support in the conical bar

State about the prestressing steel, State about the Prestressing Steel ...

State about the Prestressing Steel For prestressed concrete members, the high-tensile steel, used generally, consists of wires, bars or strands. The high tensile strength of s

Block contouring, how to calculate contour surveyed area

how to calculate contour surveyed area

Explain hardness - water softening, Explain Hardness - Water Softening ...

Explain Hardness - Water Softening 1) Hardness is used to characterize a water that does not lather well, causes a scum in the bath tub and leaves hard, white, crusty deposits

Graphics, 1. Draw the projections of a line AB that is 50 mm long and is pa...

1. Draw the projections of a line AB that is 50 mm long and is parallel to both the HP and the VP. The line is 40 mm above the HP and 25 mm in front of the VP. 2. A line AB, 50 mm

Explain the departure of a line - transportation, Explain the Departure of ...

Explain the Departure of a line - Transportation Departure of a line is the distance that the line extends in an east or west direction. A line that runs towards east has a pos

Survey, 3-d figure of line ranger

3-d figure of line ranger

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd