4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench pipe = 300 mm diameter.
o Width of trench = 600 mm o Depth of trench = 1000 mm o Bank m 3 = 2150 kg/ m 3 o Loose m 3 = 1935 kg / m 3

Related Discussions:- construction material

Construction Planning, A contractor has both a 3-cy and a 5-cy shovel in th...

A contractor has both a 3-cy and a 5-cy shovel in the equipment fleet. Select the minimum size shovel that will excavate 450,000 bcy of common earth in a minimum of 120 working day

Zeroth law of thermodynamics, Two systems which are equal in temperature to...

Two systems which are equal in temperature to a third system are equal in temperature to each other

Classification of timber, Classification of Timber Several bases are co...

Classification of Timber Several bases are considered for the classification of timbers. The following are the essential basis: Mode of growth Modulus of elasticity

Physics, about lenses & mirrors for assignment

about lenses & mirrors for assignment

Define reactivity - hazardous waste, Define Reactivity - Hazardous Waste ...

Define Reactivity - Hazardous Waste - Undergoes violent Change w/o detonating - reacts violently with water - Forms potentially explosive mixtures with water - generat

Lime, what is stone lime shall lime and kankar lime

what is stone lime shall lime and kankar lime

Invoice Method, How to raise an invoice with WCT for Civil construction job...

How to raise an invoice with WCT for Civil construction job?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd