4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench pipe = 300 mm diameter.
o Width of trench = 600 mm o Depth of trench = 1000 mm o Bank m 3 = 2150 kg/ m 3 o Loose m 3 = 1935 kg / m 3

Related Discussions:- construction material

Effect of bridge piers across a stream, Presence of bridge piers across a s...

Presence of bridge piers across a stream causes constricted flow in the openings due to the decrease of width of stream owing to presence of the piers. Furthermore it creates the f

Define the pump and motor efficiencies - hydrolic system, Define the Pump a...

Define the Pump and Motor Efficiencies Equations account for the loss of power, primarily due to mechanical friction as a result of rotating components in the pump and motor.

Calculate roller production, Calculate Roller Production An excavating ...

Calculate Roller Production An excavating contractor determined through a test strip, that a smooth steel-wheel vibrating roller compactor operating at 3-mph can compact a 6-in

Timber, uses of timber in civil engineering field and its physical state an...

uses of timber in civil engineering field and its physical state and chemical formula or symbol?

How should reservoir floors be designed, Question In designing of servi...

Question In designing of service reservoirs, how should reservoir floors be designed to avoid leakage of water because of seasonal and shrinkage movements ? Answer I

Determine the limit states of serviceability, Limit States of Serviceabilit...

Limit States of Serviceability These are those limit states which point out to the inability of a structure or a structural component in functioning properly as per the intende

Hydraulics, What is the head loss in 350 ft of 12 inch diameter 20 years ol...

What is the head loss in 350 ft of 12 inch diameter 20 years old cast iron pipe carrying 1.2 MGD?

Structural analysis & design, This is an optional team assignment. This gra...

This is an optional team assignment. This grade will replace your lowest two homework grades. You may work in teams of 3-4 students. Design the lightest concrete cantilever beam

Illustrate shaft grouting for friction barrettes, Q. Illustrate Shaft grout...

Q. Illustrate Shaft grouting for friction barrettes? For the construction of friction barrettes, some grout pipes are designed at periphery of the barrettes. Within a short dur

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd