4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench pipe = 300 mm diameter.
o Width of trench = 600 mm o Depth of trench = 1000 mm o Bank m 3 = 2150 kg/ m 3 o Loose m 3 = 1935 kg / m 3

Related Discussions:- construction material

Concrete mixers, what do you mean by buttering mixers

what do you mean by buttering mixers

Surveying, how prepared for surveying?

how prepared for surveying?

Full bore flow in drainage design, Q. Full bore flow in drainage design? ...

Q. Full bore flow in drainage design? In the design of gravity drainage pipes, full bore flow capacity is usually adopted to check against design runoff. Though one should note

Structural analysis_cantilever trusses, Obtain the values and direction of ...

Obtain the values and direction of the supporting reactions of the truss given below. Use the method of section to determine the forces in each member.

Piers and piles, what is the difference between piers and piles?

what is the difference between piers and piles?

General requirement for civil engineering, Question General requirement for...

Question General requirement for Civil Engineering Works in 1992 Edition, Clause 15.09 details that tying wires for strengthening adjacent to and above Class F4 and F5 closes must

Material of steel tendons, Material of steel tendons The material of s...

Material of steel tendons The material of steel tendons also must be of a high strength. Tendons should possess required material and geometrical properties so that a desired

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd