construction material, Civil Engineering

Assignment Help:
4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench pipe = 300 mm diameter.
o Width of trench = 600 mm o Depth of trench = 1000 mm o Bank m 3 = 2150 kg/ m 3 o Loose m 3 = 1935 kg / m 3

Related Discussions:- construction material

What do you mean by ozone test, Q. What do you mean by Ozone Test? Some...

Q. What do you mean by Ozone Test? Some research and studies determined that the ozone test was unnecessary as this affects only the surface layer.  In un-stretched rubber, ozo

Solid mensuration, the base of an isosceles triangle and the altitude is dr...

the base of an isosceles triangle and the altitude is drawn from one of the congruent sides are equal to 18cm and 15cm , respectively . Find the lenghts of the sides of the triangl

Calculate the required length of transition, Q  A transition curve is requi...

Q  A transition curve is required for a circular curve of 200-meter Φ radius, the gauge being 1.5 m. and max super elevation restricted to 15 cm. The transition restricted to 15 cm

Define wastewater treatment processes, Define Wastewater treatment Processe...

Define Wastewater treatment Processes The wastewater treatment processes that we design mimic the processes that occur in the nature (for example processes that occur in a flow

Los Angeles Abrasion Test, LA values of different sizes of materials can be...

LA values of different sizes of materials can be proportionately determined?

What is preset in bridge bearing, Q. What is Preset in bridge bearing? ...

Q. What is Preset in bridge bearing? 'Preset' is a method to decrease the size of upper plates of sliding bearings in order to save cost. Normal length of an upper bearing plat

Compression members, Compression Members: Compression members in steel...

Compression Members: Compression members in steel need special care in design. Steel possesses high strength in tension/compression; hence the sections are generally small com

Define the cost per square foot of contact area, Define the Cost per Square...

Define the Cost per Square Foot of Contact Area The cost of concrete formwork is influenced by three factors: 1. Initial cost or fabrication cost that contains the cost of t

Factors affecting location decision, Factors Affecting Location Decision: ...

Factors Affecting Location Decision:   Mining, quarrying and heavy manufacturing have capital intensive facilities that are costly to build and cover large area and use large q

Problems in turbid water - underwater inspection of bridge, Define Problems...

Define Problems in turbid water - underwater inspection of bridge? There are three main problems, which limit the viewing performance of an underwater camera. These are: -

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd