4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench pipe = 300 mm diameter.
o Width of trench = 600 mm o Depth of trench = 1000 mm o Bank m 3 = 2150 kg/ m 3 o Loose m 3 = 1935 kg / m 3

Related Discussions:- construction material

Shear force, what is shear failure and shear force please explian?

what is shear failure and shear force please explian?

Friction dampers, what is friction damper and there types?

what is friction damper and there types?

Soil Mechanics, What relationship between Atterberg limits and cohesion

What relationship between Atterberg limits and cohesion

Dam, how many types of drainage galleries and foundation treatment

how many types of drainage galleries and foundation treatment

Define corrosion - deterioration of steel structures, Define Corrosion - De...

Define Corrosion - Deterioration of Steel Structures? Corrosion is the principle cause of deterioration of steel structures. Corrosion of steel is an electrochemical process th

What are the parasitic forces for prestressing, Q. What are the Parasitic f...

Q. What are the Parasitic forces for prestressing? In statically determinate structures, prestressing forces will cause the concrete structures to end upwards. Therefore precam

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd