construction material, Civil Engineering

Assignment Help:
4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench pipe = 300 mm diameter.
o Width of trench = 600 mm o Depth of trench = 1000 mm o Bank m 3 = 2150 kg/ m 3 o Loose m 3 = 1935 kg / m 3

Related Discussions:- construction material

Determine the preliminary settlement analysis, Preliminary settlement analy...

Preliminary settlement analysis for a building indicated a settlement of 50 mm in 4 years and an  ultimate  settlement  of  250 mm.  The average pressure increment in the clay stra

Explain the process of directed track maintenance, Q. Explain the process o...

Q. Explain the process of Directed Track Maintenance? DTM is a method to maintain the track is directed every day and not as a prescribed routine. DTM essentially consists of n

Determine the settlement of the foundation, A soft, normally consolidated c...

A soft, normally consolidated clay layer is 18 m thick. The natural water content is 45%. The saturated unit weight is 18 kN/m 3 ; the grain specific gravity is 2.70 and the liqui

Mechanics problem, i am facing some problem in solving the problem of elong...

i am facing some problem in solving the problem of elongation due to self weight suspended from fixed support in the conical bar

Retaining wall, I retained the soil in my yard by brick with 3 levels to a...

I retained the soil in my yard by brick with 3 levels to avoid sliding the soil to the street. the appeared part of the bricks from each level is 3 feet and less.The hidden part o

Define the term - permanent load, Define the term - permanent load Wher...

Define the term - permanent load Where the permanent load is less than or equal to 25% of the design imposed load, deflections may be calculated using any elastic method. When

Maximum shear stress - state of stress, Maximum shear stress - state of str...

Maximum shear stress - state of stress: Consider the state of stress. (a) According to principal stress theory the equivalent stress for this case is simply σ 1 , i.e. 300

Solid block -calculating for design mix, Good evening sir, solid block''s d...

Good evening sir, solid block''s design mix calculated generally please explain and derive .

What are advantages and disadvantage of varnishing, Q. What are advantages ...

Q. What are advantages and disadvantage of varnishing? Varnish is a clear pale solution of a resinous substance ( like amber, common resin, copal, lac, or shellac 0 dissolved i

Sub-base layer be served as a drainage layer , Question Would a sub-bas...

Question Would a sub-base layer be served as a drainage layer to take away water from pavement? Answer As well providing load distribution in post-construction stage a

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd