4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench pipe = 300 mm diameter.
o Width of trench = 600 mm o Depth of trench = 1000 mm o Bank m 3 = 2150 kg/ m 3 o Loose m 3 = 1935 kg / m 3

Related Discussions:- construction material

Softening point of bitumen, Hi, i need discussion for softening point of bi...

Hi, i need discussion for softening point of bitumen 7.5 ?C

Determine the depth of exploration, Determine the Depth of Exploration ...

Determine the Depth of Exploration The depth of exploration depends on the following factors: i) Size, type of the structure and loading intensity. ii) Design considerati

Explain influence lines-reactions, Explain Influence lines-reactions 1....

Explain Influence lines-reactions 1.  Remove the support under investigation 2.  Displace the beam vertically a distance of 1 unit.  The resulting beam shape will be the sha

Granite tiles for construction material, Q. Granite Tiles for construction ...

Q. Granite Tiles for construction material? At every important station for public urinals granite may be used as wall cladding drain and foot rest material. The water sinks at

Landing stages - water transportation, Landing Stages: A landing stage...

Landing Stages: A landing stage is a floating structure, usually a pontoon or a barge, which is secured to the shore by mooring chains. Small ships can dock against the landin

Calculate the percent grade of line, 1. The topography of a local valley is...

1. The topography of a local valley is shown. The horizontal distance between point P and Q is 11,456-ft. The percent grade (%) of line P-Q .     2. Based on the info

Digit of cells for concrete box girder bridges, Question How does an engine...

Question How does an engineer determine digit of cells for concrete box girder bridges ? Answer If depth of a box girder bridge exceeds 1/6 or 1/5 of bridge width, then it is o

Cross drainage work, Cross Drainage Work: Several natural streams, ri...

Cross Drainage Work: Several natural streams, rivers and canals cross the road. They have to be led across the road through culverts and bridges. That given structures is kno

Spatial structures loading, Spatial Structures Loading Dead load D...

Spatial Structures Loading Dead load Dead loads include the weight of permanent components such as elements and spheres weight, casing weight, false ceiling weight and uti

#titl, Two readings ie 1.64m and 0.73m were taken during leveling procedure...

Two readings ie 1.64m and 0.73m were taken during leveling procedure to define the slope of a centerline of a bridge at points A and B. If distance AB=50 m, find the slope of line

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd