4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench pipe = 300 mm diameter.
o Width of trench = 600 mm o Depth of trench = 1000 mm o Bank m 3 = 2150 kg/ m 3 o Loose m 3 = 1935 kg / m 3

Related Discussions:- construction material

What is froude number - hydrolic system, What is Froude Number? Used to...

What is Froude Number? Used to determine if the flow is rapid, critical or tranquil.  Fr = 1 critical flow; Fr 1 supercritical flow In rectangular open channels:  Fr =

Base isolation, why base isolation is not good for tall building

why base isolation is not good for tall building

Define circular channels flowing partially full, Define Circular Channels F...

Define Circular Channels Flowing Partially Full Two sets of curved lines on the Circular Channel Ratios figure (discharge Q/Q full and velocity v/v full ).  1.  "n" variabl

State the ultimate load capacity of the pile group, A group of 16 piles of ...

A group of 16 piles of 50 cm diameter is arranged with a centre to centre spacing of 1.0 m. The piles are 9 m long and are embedded in soft clay with cohesion 30 kN/m 2 . Bearing r

Solid mensuration, If the diameter of the base remains constant, by what fa...

If the diameter of the base remains constant, by what factor should the altitude be multiplied to produce a cone with twice volume as the original

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd