construction material, Civil Engineering

Assignment Help:
4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench pipe = 300 mm diameter.
o Width of trench = 600 mm o Depth of trench = 1000 mm o Bank m 3 = 2150 kg/ m 3 o Loose m 3 = 1935 kg / m 3

Related Discussions:- construction material

Mechanism of taking up loads for concrete paving blocks, Mechanism of takin...

Mechanism of taking up loads for concrete paving blocks  Paving for concrete blocks comprises closely packed paving blocks in pre-determined patterns and tiny joint spaces bet

Failure analysis in designing of a structure, Modes of failure • For sa...

Modes of failure • For safe design, a knowledge of the possible modes of failure is also necessary, e.g. failure of the structure could occur due to - Tensile fracture due t

Instruments, description and details about distomat

description and details about distomat

Write short notes on bulking of sand, Q. Write short notes on Bulking of Sa...

Q. Write short notes on Bulking of Sand? Volume of sand fluctuates with variations in moisture content when sand is wet then each particle sets coating of water due to surface

Surveying, 3 types of obstacles in chaining detail

3 types of obstacles in chaining detail

Define chlorides - underwater inspection of bridge, Define Chlorides - unde...

Define Chlorides - underwater inspection of bridge? Chlorides do not attack plain concrete when present in the concentrations that normally exist in seawater, but may greatly a

What is the pre-tensioned concrete, What is the Pre-tensioned concrete ...

What is the Pre-tensioned concrete In Pre-tensioned concrete tendons are kept stretched with suitable mechanisms and concrete is cast into the forms through which stretched ten

Show disadvantages of excessive concrete covers, Q. Disadvantages of excess...

Q. Disadvantages of excessive concrete covers? In reinforced concrete structures cover is generally provided to protect steel reinforcement from corrosion and to provide fire r

Estimation, What are the various methods of recording measurements? List fi...

What are the various methods of recording measurements? List five items each for various methods of recoding measurements?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd