4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench pipe = 300 mm diameter.
o Width of trench = 600 mm o Depth of trench = 1000 mm o Bank m 3 = 2150 kg/ m 3 o Loose m 3 = 1935 kg / m 3

Related Discussions:- construction material

Explain about noise absorptive materials, Q. Explain about Noise absorptive...

Q. Explain about Noise absorptive materials? The fundamental mechanism of noise absorptive material is to change the acoustic energy into heat energy. Amount of heat produced i

Dissimilarity b/w air chamber and surge tank, Question What is dissimil...

Question What is dissimilarity between air chamber and surge tank ? Answer Air chambers and surge tanks are usually set up in watermain to ease stress on schem

Show the concrete pressure on formwork, Q. Relation of pouring rate and tem...

Q. Relation of pouring rate and temperature with concrete pressure on formwork Freshly placed concrete exerts pressure on formwork at the time of the placing operation. It's i

Define inspection of pier or abutment, Define Inspection of Pier or Abutmen...

Define Inspection of Pier or Abutment? Inspection of pier/abutment may then be carried out as under: i. Conduct visual inspection of the entire surface using up and down swe

Explain dielectric breakdown, Explain Dielectric breakdown Dielectric ...

Explain Dielectric breakdown Dielectric breakdown means failure or deterioration of the dielectric material because of various reasons.

Write a short note on economic span of a bridge, Q. Write a short note on E...

Q. Write a short note on Economic Span of a Bridge? The span for which the total cost of bridge will be minimum is known as the economic span. The ratio of Cost of super str

Key reasons for conducting pull-out tests, Question What are key reason...

Question What are key reasons for conducting pull-out tests for soil nails ? Answer There are largely four bases for this examination- (i) To verify and verify bo

Explain the dynamic or vibration tests, Explain the Dynamic or Vibration Te...

Explain the Dynamic or Vibration Tests Tests of this type, also known as sonic integrity test, involve sub- jecting the element to a single impulsive blow or cyclic load, and

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd