construction material, Civil Engineering

Assignment Help:
4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench pipe = 300 mm diameter.
o Width of trench = 600 mm o Depth of trench = 1000 mm o Bank m 3 = 2150 kg/ m 3 o Loose m 3 = 1935 kg / m 3

Related Discussions:- construction material

Horizontal capability of pile bents, Question For classic pile bents in...

Question For classic pile bents in marine piers, how can vertical loads related to horizontal capability of pile bents? Answer At first consider a pile bent with a top

Functions of bedding below storm water drains, Question What are main funct...

Question What are main functions of bedding below storm water drains ? Answer Bedding that is normally made of granular resources or concrete serves four main functions as optio

Define categories of scaling-underwater inspection of bridge, Define the Ca...

Define the Categories of Scaling? Scaling is classified into following three categories: i. Light scale - loss of surface mortar up to 5 mm deep, with surface exposure of co

Write briefly for trolley permits, Q. Write briefly for Trolley Permits? ...

Q. Write briefly for Trolley Permits? It is the permit given to the Moter Trolley / Push Trolley, Cycle / Moped Trolley. It is essential to have Trolley Permit before taking t

Practice to form washout regulators, Question Why are two gate regulato...

Question Why are two gate regulators necessary in regular practice to form washout regulators ? Answer In fact, situation is analogous to that of fire hydrants in tha

Explain sedimentation, Explain Sedimentation 1. Sedimentation bas...

Explain Sedimentation 1. Sedimentation basin or clarifier is used to remove particles that will settle in a reasonable time period 2. Basins are usually rectangular or

Indicate quality of rock foundation, Question During piling works, norm...

Question During piling works, normally founding levels of bored piles are definite by using total core recovery or rock quality designation (RQD). Are there any problems by

Influence Line for shear at Support, I have to draw the IL for the shear at...

I have to draw the IL for the shear at a roller support and am not sure how it should look

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd