Construction activities, such as shoring and bracing of excavations, lifting and rigging activities and scaffolding need to be considered as part of the design.

The primary hazard of trenching and excavation is employee injury from collapse. An excavation design shall include adequate sloping and benching or adequate support and protective system to protect personnel during the construction activities. Soil analysis is an important part of determining the appropriate sloping, benching and shoring. An added hazard exists if excavation extends below the groundwater table.

A number of features need to be addressed during the plant layout including crane access to equipment and drop areas, height of crane to accommodate the size and shape of items to be lifted, clearance over other facilities and sling allowance, personnel access to gantry, and size of buffers and structural steel to accommodate loadings.

Lifting of heavy equipment into place by crane may require the construction of specific foundations or lift pads. Rigging requires careful evaluation of slings for use because of the wide variety of safety factors which must be considered for each case. These factors include but are not limited to:

• Size and type of sling.

• The method of fastening.

• Sheaves, sprockets, and drums.

• Condition of equipment or material.

• Size and shape of load.

• Type of attachment.


Related Discussions:- Construction activities for plant

Calculate drilling speed and machining time, Calculate Drilling Speed and M...

Calculate Drilling Speed and Machining Time Calculate the drilling speed if a 50 mm dia hole of 60 mm depth is to be drilled in a M.S. component. The feed rate is 0.2652 and M

CIM, discuss the main components of computer aided manufacturing

discuss the main components of computer aided manufacturing

Mockup of tube to tubesheet, what are the tests to carried out after mockup...

what are the tests to carried out after mockup preparation

Axis perpendicular to the vertical plane - tetrahedron, Axis perpendicular ...

Axis perpendicular to the vertical plane - tetrahedron: A tetrahedron of side 60 millimeter has its base parallel to the VP, along with an edge of the base inclined at 45 o t

Spot welding of different metals-low carbon steel, Spot welding of differen...

Spot welding of different metals-Low carbon steel Normally, mild steel can be spot welded from the thinnest gauges to a maximum of two pieces of 12 mm thickness. The restrictio

Determine the bending stress, The cantilevered beam made from the Z section...

The cantilevered beam made from the Z section is subjected to the two loadings as shown. (a)  Determine and show the orientation of the neutral axis on the cross section (angle

Lifting machines, Lifting machines: Basic definitions of the lifting m...

Lifting machines: Basic definitions of the lifting machines and some lifting machines have been described. For each of these machines, derivation of the formulae for mechanica

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd