Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

What is the dry density, Q. The field density of a compacted fill is deter...

Q. The field density of a compacted fill is determined by means of a core cutter whose empty weight is 1000 g and volume is 1000 cm 3 . The cutter full of soil weights 2890 g. If

Show constituents of bricks, Q. Show Constituents of bricks? The brick ...

Q. Show Constituents of bricks? The brick is manufactured out of special. Type of brick earth consisting of clay and sand the proportion of clay and earth should be such that w

What is the absolute maximum shear stress, A strip load of considerable len...

A strip load of considerable length and 1.5 m width transmits a pressure of 150 kN/m 2 to the underlying soil. Verify the maximum principal stress at 0.75 m depth below the footin

Solid mensuration, the two sides of a triangle are 17cm and 28 cm long, and...

the two sides of a triangle are 17cm and 28 cm long, and the length of the median drawn to the third side is equal to 19.5. find the distance from an endpoint of this median to the

Distomat., write a note on distomat

write a note on distomat

Retaioning walls, what are the uses of retaining wall?!

what are the uses of retaining wall?!

Compute the ultimate settlement, A 2 m wide strip footing is to be constru...

A 2 m wide strip footing is to be constructed in a sandy stratum of 2 m thick. The depth of the footing is 1 m below ground surface. The sand layer is underlain by lm thick cla

Cost-volume-profit and break even analysis, Cost-Volume-Profit and Break Ev...

Cost-Volume-Profit and Break Even Analysis: Cost-volume-profit analysis helps us to learn the behaviour of cost and profit in response to varying level of business activity. I

Derive, Derived condition of economic span of bridge

Derived condition of economic span of bridge

State the loss of prestress, State the Loss of prestress Loss of prestr...

State the Loss of prestress Loss of prestress due to elastic shortening definitely occurs in pre-tensioned concrete members. But in post-tensioned members it does not occur if

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd