Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Harbour layout, Harbour Layout: A harbour has the following constitue...

Harbour Layout: A harbour has the following constituent parts: (a)        An entrance channel, 100-300 m wide (b)       A turning basin, dia 400-600 m (c)        A b

Design nominal reinforcement for staircase, Question Given a 1meter hig...

Question Given a 1meter high staircase resting on solid concrete, could it be adequate to design nominal reinforcement for staircase? Answer For design of staircase,

State the term - total loss of prestress, Total loss of prestress The ...

Total loss of prestress The total amount of losses of prestresses may be accounted for in a prestressed concrete member by adding different losses which may take place for tha

Chain surveying, describe setting out right angle at given point on a chain...

describe setting out right angle at given point on a chain line and when the point lies outside the chain line

AERATED CONCRETE, AIR ENTRAINING AGENT USED IN CONCRETE OTHER THAN ALUMINIU...

AIR ENTRAINING AGENT USED IN CONCRETE OTHER THAN ALUMINIUM POWDER

Bearings, what is the difference between whole circle bearing and reduced b...

what is the difference between whole circle bearing and reduced bearing?

Geometric design, calculating OVERTAKING SIGHT DISTANCE

calculating OVERTAKING SIGHT DISTANCE

Raised check rails for obtuse crossing, Raised Check Rails for obtuse cross...

Raised Check Rails for obtuse crossing In order to provide guided path way in throat portion of 1 in 8 1/2 BG obtuse diamond crossing, the check rails are raised by welding of

Define the categories of corrosion of steel structures, Define the Categori...

Define the Categories of Corrosion of steel structures? Corrosion of steel structures can be classified as under: -   Atmospheric corrosion -   Underwater corrosion -

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd