Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Distomat., write a note on distomat

write a note on distomat

Maintenance of steel bearings, Q. Maintenance of steel bearings? Cleani...

Q. Maintenance of steel bearings? Cleaning and greasing of bearings is one of the important maintenance works to avoid premature failure of bearings and reduce recurring heavy

Cement, manufacture of cement by dry process

manufacture of cement by dry process

Mr Kamal Saxena, What is WBM road. How it is constructed?

What is WBM road. How it is constructed?

Finite element analysis (bridge), I am a final year civil and structural st...

I am a final year civil and structural student and i need your help about my final year project. My Final Year Topic: Finite Element Analysis of a bridge using Sap2000 Aim: Fi

Interface between base plates and footings, Interface between base plates a...

Interface between base plates and footings Surface of footings is generally quite rough so that some levelling has to be carried out for base plates. Interface between base pl

Integration of the strain settlement, All soils subjected to stress undergo...

All soils subjected to stress undergo strain. This will be taking place within the soil skeleton. This strain is caused by rolling, slipping, sliding and crushing at the particle c

Float or slack of an activity is positive or negetive, 1. What take place w...

1. What take place when float or slack of an activity is positive Ans: It represents a situation where extra resources are available and the completion of the project is not de

Construction Planning, A contractor has both a 3-cy and a 5-cy shovel in th...

A contractor has both a 3-cy and a 5-cy shovel in the equipment fleet. Select the minimum size shovel that will excavate 450,000 bcy of common earth in a minimum of 120 working day

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd