Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Purpose of using capping layers in pavement construction, Q. Purpose of usi...

Q. Purpose of using capping layers in pavement construction? When California Bearing Ratio of subgrade is checked to be below a specific percentage (for example 5%), a capping

Road location in dune areas, Road Location in Dune Areas: The followi...

Road Location in Dune Areas: The following principle should be observed in locating a road in dune areas : (a) Align a road where sand is covered by vegetation. (b) Sel

Beam to column connection, what are the characteristics of the beam to colu...

what are the characteristics of the beam to column connection?

Compute interior or intersection angle, Compute Interior or Intersection An...

Compute Interior or Intersection Angle for the following circular curve:   Answer- I = 180° - 60° - 60°= 60

M.o.c, lime saturation factor meaning with simple english

lime saturation factor meaning with simple english

Calculate snow weight, Snow weight In spatial trusses, Snow load is muc...

Snow weight In spatial trusses, Snow load is much more important than building. As in buildings snow load is only a small proportion of the overall weight of the building, it w

Revit , how to use the revit program

how to use the revit program

Industrial steel floor fire proof, i want to know the construction details ...

i want to know the construction details of industrial steel floor?

Explain critical factor in design of shock transmission unit, Explain Criti...

Explain Critical factor in Design of shock transmission unit? (a) STUs are unidirectional devices for load transmission. If out of plane forces will be acting on the STU, the a

Epoxy-coated bars vs galvanized bars, Bonding performance to concrete: Epox...

Bonding performance to concrete: Epoxy-coated bars vs. galvanized bars  Based on the findings of CEB Bulletin 211 the bonding of galvanized bars to concrete is lower in early

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd