Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Contractor to continue concreting works, Question If on-site slump test fai...

Question If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works ? Answer This is an extremely traditional question raised by

Fundamental of physics, state and prove Heisenberg uncertainity principle?

state and prove Heisenberg uncertainity principle?

Angular messurement using total stations, write a short note on angular mes...

write a short note on angular messurement using stations?

Knife edge loads – representation of wheel axles, Q. Knife edge loads – rep...

Q. Knife edge loads – representation of wheel axles? In BS5400 traffic loads for HA loading are given by uniformly distributed loads along loaded length and a knife edge load.

Afflux on account of obstruction to flow, Q. Afflux on account of obstructi...

Q. Afflux on account of obstruction to flow? Even if the river constriction on account of approach banks is not excessive and bridge waterway is wider than that causing critica

Residents building g+3, How analysis of residents building g+3 structure an...

How analysis of residents building g+3 structure analysisl

What is objective method of assessment, Q. What is objective method of asse...

Q. What is objective method of assessment? Track recording consists of objective method of assessment of the quality of track with the help of sophisticated equipments. A conti

Corner reinforcement for concrete pavement, Q. Corner reinforcement for con...

Q. Corner reinforcement for concrete pavement? Let's consider a panel of concrete slab without any load transferring devices at it edges. When concrete panel is subjected to tr

Stabilised pavement layers, Stabilised Pavement Layers: Soil stabilis...

Stabilised Pavement Layers: Soil stabilisation is the process of treating a soil in such a manner as to alter and improve its properties for use as a pavement layer on sub-gr

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd