Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Water absorption test for precast concrete pipes, Purpose of carrying out w...

Purpose of carrying out water absorption test for precast concrete pipes Cement will mix with more water than is essential to ultimately combine during hydration of cement pas

State the importance of structural element, State the importance of structu...

State the importance of structural element If this structural element is used as a beam element, subjected to self load and other imposed transverse loads, then the bottom fibr

Explain rebound hammer - underwater non-destructive testing, Explain Reboun...

Explain Rebound Hammer - Underwater non-destructive testing? The underwater rebound hammer system is a surface hardness tester which can be employed to acquire a general condit

Load carrying element of min-piles, Q. A pipe or groups of bars be adopted ...

Q. A pipe or groups of bars be adopted as load carrying element of min-piles? The design of mini-piles someway differs from other traditional pile types. For example the design

#Paint, whats the mix ratio or proportion of paint components for 1litre

whats the mix ratio or proportion of paint components for 1litre

What do you mean by ozone test, Q. What do you mean by Ozone Test? Some...

Q. What do you mean by Ozone Test? Some research and studies determined that the ozone test was unnecessary as this affects only the surface layer.  In un-stretched rubber, ozo

State the increase in earth pressure at rest, A wall with a smooth vertical...

A wall with a smooth vertical back and 9 metres high retains a moist cohesionless soil with a horizontal surface. The soil weighs 15 kN/m3 and has an angle of internal friction of

What is unimat machine, Q. What is Unimat Machine? The machine has got ...

Q. What is Unimat Machine? The machine has got 16 independently tiltable tamping tools which enable the machine to work on points and crossing as well as on plain track. The ma

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd