Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

What do you understand by pressure line, What do you understand by Pressure...

What do you understand by Pressure line If we determine the locations of resultant force at various sections of a pre-stressed beam, as in Example, we can draw a curve showing

Explain the soil texture and soil structure, (a) Explain the 'Soil Texture'...

(a) Explain the 'Soil Texture' and 'Soil structure'. What are the various terms used to explain the above properties of the soil? (b) A clay sample having natural moisture conte

Distomat, write short note on distomat with applications

write short note on distomat with applications

Cocrete, preparation and uses of concrete

preparation and uses of concrete

Estimate total dissolved solids, Estimate total dissolved solids, Alkalinit...

Estimate total dissolved solids, Alkalinity and Hardness A sample of water from Brazos River at Brenham was collected and analyzed for water quality characteristics and the dat

Classification of timber based on availability:, Classification Based on Av...

Classification Based on Availability: Forest departments categorized timbers based on the availability as X=Most common. 1415 m 3 or more per year Y=Common. 355 m 3 to 1415

Truss, modified pratt truss with detailing in 3D

modified pratt truss with detailing in 3D

Abrassion test., abrasion test is conducted to find what

abrasion test is conducted to find what

Stress corrosion of pre-stressing steel, Stress corrosion of pre-stressing ...

Stress corrosion of pre-stressing steel Stress corrosion is crystalline cracking of metals under tensile stresses in the presence of corrosive agents. Conditions for stress cor

Main purpose of conducting load test for piling works, Question What is...

Question What is main purpose of conducting load test for piling works ? Answer Pile load test gives information on ultimate bearing ability but not settlement be

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd