Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Write short note on skv process of thermit welding, Q. Write short note on...

Q. Write short note on SKV  process of thermit welding? This term is used for welding by Alumino thermic process with short preheat time. The time required for preheat with pet

Will water damage concrete, As far as only concrete is concerned i.e. plain...

As far as only concrete is concerned i.e. plain concrete, the effect of water seepage is very little (depending upon the grade of concrete) whereas for RCC (reinforced cement concr

Define latitude - transportation, Define Latitude - Transportation Lati...

Define Latitude - Transportation Latitude of a line is the distance that the line extends in a north or south direction. A line that runs towards north has positive latitude; a

Define well steoning, Q. Define Well Steoning? It is the side wall of w...

Q. Define Well Steoning? It is the side wall of well foundation. It is built of masonry or cement concrete not less than M 10 grade, sufficient bond rods should be provided to

Cleaning and greasing of steel sliding bearings, Cleaning and greasing of s...

Cleaning and greasing of steel sliding bearings : Following equipments are required for greasing of steel sliding bearings: 1. Jacks (50 ton capacity) - 2 nos. 2. Hard wo

Surveying, earthen dam and gravity dam

earthen dam and gravity dam

Calculate the specific gravity of the soil particles, A piece of clay taken...

A piece of clay taken from a sampling tube has a wet weight of 1.553 N and volume of 95.3 cm 3 . After drying in an oven for 24 hours at 105°C, its weight 1.087 N. Suppose the spec

Widening on curves, Widening on Curves: Pavements have to be widened ...

Widening on Curves: Pavements have to be widened on curves because of the fact that : (a) the vehicle has a wheel base and overhang on the front and rear, and the vehicle

State the process to calculate the transmission length, State the process t...

State the process to calculate the Transmission Length It is the distance required at the end of a concrete member for developing the maximum tendon stress by bond.

Treatment plant - sewer construction, Treatment plant - sewer construction:...

Treatment plant - sewer construction: Problem: How many kg of primary and secondary dry solids needs to be processed daily from the treatment plant? Solution An a

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd