Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Illustrate shaft grouting for friction barrettes, Q. Illustrate Shaft grout...

Q. Illustrate Shaft grouting for friction barrettes? For the construction of friction barrettes, some grout pipes are designed at periphery of the barrettes. Within a short dur

Bulking of sand, what is the permissible limit of sand

what is the permissible limit of sand

Explain the categories of air pollution, Explain the Categories of Air Poll...

Explain the Categories of Air Pollution 1. Ambient Air Pollution Out door environment o Involves complex array of sources and pollutants, meteorological transport of th

Lifting of girders, Q. Lifting of girders? Lifting of girders : For gre...

Q. Lifting of girders? Lifting of girders : For greasing the bearings girders are required to be lifted. But the gap between the bottom flange of plate girders and the bed bloc

Surveying, what are tie lines? explain in detail

what are tie lines? explain in detail

Explain the system curves - pumping system, Explain the System Curves - Pum...

Explain the System Curves - Pumping System Non-linear plot beginning on the y-axis at the Total Static Head (TSH) and plotted primarily based on the h f .

Bitumen, unit of kinematic viscosity

unit of kinematic viscosity

3-tap to 6-tap increase water pressure, Will going from a 3-tap to 6-tap i...

Will going from a 3-tap to 6-tap increase water pressure? Ans) No, the pressure will be the similar, you will get more volume only if your pumps can handle the GPM, to enhance p

Shear slump and collapse slump in slump tests, Question What is sign of sh...

Question What is sign of shear slump and collapse slump in slump tests? Answer There are three varieties of slump that might occur in slumps test, specifically, slump, shear

Main principle of post-grouting for mini-piles, Question What is main p...

Question What is main principle of post-grouting for mini-piles? Answer During course of post-grouting , a tube with a hole at its base is lowered into pile and g

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd