Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Designing sewer pipes, Question While designing sewer pipes , why vitrifie...

Question While designing sewer pipes , why vitrified clay pipes commonly is used for pipe size less than 600mm still as precast concrete pipes with PVC lining is used for pipe

Assignment , A cantilever beam is loaded with a concentrated. Force of 5kN ...

A cantilever beam is loaded with a concentrated. Force of 5kN at the free end. The length of the cantilever beam is 1m having cross section of 50×50mm. determine the equation for b

Concrete, What is Polymer Concrete?

What is Polymer Concrete?

Obtain maximum positive moment in a span of continuous beam, Reason of load...

Reason of loading on alternative spans to obtain maximum positive moment in a span of a continuous beam To attain a maximum sagging moment in a span of a continuous beam, gene

Concrete, What is compacting factor

What is compacting factor

Postensioning in raft foundation, how can we post tension a raft foundation...

how can we post tension a raft foundation? what design procedure should we follow to post tension raft foundation in order to decrease the concrete and steel volume and increase th

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd