Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

What is initial prestress, What is Initial Prestress From the transfer ...

What is Initial Prestress From the transfer stage, tensile stresses in tendons apply compressive stresses in concrete. The initial value of  these stresses (in tendons or in co

In marine pile type of steel tubular piles, Question In marine pile typ...

Question In marine pile type of steel tubular piles with reinforced concrete infill, least toe level is frequently specified in contract drawings. What is the purpose in your v

Tremie pipes are normally used with aid of hoppers, Question For underw...

Question For underwater concreting, tremie pipes are normally used with aid of hoppers. From time to time tubes are put in inside the hoppers and with reasons? Answer

Mr Kamal Saxena, What is WBM road. How it is constructed?

What is WBM road. How it is constructed?

Dense bituminous macadam, Dense Bituminous Macadam: A Dense Bituminou...

Dense Bituminous Macadam: A Dense Bituminous Macadam (DBM) is a close-graded premix material having a voids content of 5-10 per cent. Two gradings are normally adopted :

State the term - calculation of deformation of concrete, State the term - c...

State the term - calculation of deformation of concrete For the calculation of deformation of concrete at some stage before the maximum shrinkage is reached, it may be assumed

State the coulomb earth pressure theory, A masonry wall with vertical back ...

A masonry wall with vertical back has a backfill 5 m behind it. The ground level is horizontal at the top and the ground water table is at ground level. Measured the horizontal pre

Truss, modified pratt truss with detailing in 3D

modified pratt truss with detailing in 3D

Calculate the equivalent uniform annual cost, A contractor purchased an exc...

A contractor purchased an excavator for $100,000. The life expectancy is 10-years. With the annual interest rate at 7%, the annual cost for the excavator is most nearly: Solutio

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd