Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Determine the settlement of the foundation, The thiclcness of the normally...

The thiclcness of the normally consolidated soft clay layer is 6 m. The natural water content is 31 percent. The specific gravity of the soil being 2.68 with a liquid limit of 4

Explain energy grade line (egl), Explain Energy Grade Line (EGL) Graph ...

Explain Energy Grade Line (EGL) Graph of the sum of the potential, pressure and kinetic energies along a pipe or open channel. Energies are plotted along the y-axis above a dat

Single flemish bond, advantages and disadvantages in single flemish bond

advantages and disadvantages in single flemish bond

Verify the earth pressure at rest, A retaining wall, 6 m high, retains dry ...

A retaining wall, 6 m high, retains dry sand with an angle of friction of 30° and unit weight of 16.2 kN/m 3 . Verify the earth pressure at rest. If the water table rises to the to

BESHOOOOO, what are the dimensions of a sheet of paper required for plottin...

what are the dimensions of a sheet of paper required for plotting a traverse ABCDE with 1 : 250 scale if a margin of 4 cm to the right and left sides and a6 cm margin to the other

Derive, Derived condition of economic span of bridge

Derived condition of economic span of bridge

Construction of parabolic shapes, construct parabolic shapes using the enve...

construct parabolic shapes using the envelop method and the offset method with dimensions 80 by 120

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd