Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

General requirement for civil engineering, Question General requirement for...

Question General requirement for Civil Engineering Works in 1992 Edition, Clause 15.09 details that tying wires for strengthening adjacent to and above Class F4 and F5 closes must

Soil compaction, Soil Compaction: Soils used in road construction nee...

Soil Compaction: Soils used in road construction need to be thoroughly rolled and compacted. Compaction of soil is needed for the following reasons. (a) A well compacted s

Test for determination of shear modulus, Test for determination of Shear Mo...

Test for determination of Shear Modulus Conditioning load : Bearings shall be preloaded with maximum horizontal load Htest (with Ntest or vertical load held constant) and un

Deflection of beams, 1) A propped cantilever beam ABC is 7m long.It has th...

1) A propped cantilever beam ABC is 7m long.It has the point C fixed and Point A on a roller support.It carries a 200Kn point load at a distance 3m from A.There is a moment of 80KN

Rcc and rbc, types mixing,curing,water cement ratio,qualities and workabili...

types mixing,curing,water cement ratio,qualities and workability

Describe types of spurs, Q. Describe types of Spurs? Spurs can be of va...

Q. Describe types of Spurs? Spurs can be of varied types. They may be either permeable or impermeable. Permeable spurs are open structures constructed by driving wooden balties

Calculate the settlement at the centre of the mat, A mat foundation of 15...

A mat foundation of 15 m x 15 m and weighing 20000 N/m 2 is to be constructed on the surface of a soil strata. The profile is given in Figure. The number of squares enclosed i

Cost-volume relationship, Cost-volume relationship: Cost-volume relati...

Cost-volume relationship: Cost-volume relationship is illustrated through a simple example dealing with the cost of operating an automobile. To perform the analysis following

Influenza virus, humans who - are the most likely to contact swine flu

humans who - are the most likely to contact swine flu

Calculate the amount of import or export, Calculate the Amount of Import or...

Calculate the Amount of Import or Export For the project site shown in Figure, the amount of import or export to bring the entire site to elevation 90-ft is most nearly:

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd