Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Construction equipments, what is preventive maintenance and state its advan...

what is preventive maintenance and state its advantages

W/c ratio, first of all i want to think you for this helpful website , and ...

first of all i want to think you for this helpful website , and let me ask you this question . how to calculate w/c ratio ? thank you so much for you .

Demonstrate the economical design of concrete, Demonstrate the economical d...

Demonstrate the economical design of concrete A safe, serviceable and economical design of concrete structures requires a comprehensive knowledge of the loads expected to be a

Rcc and rbc, types mixing,curing,water cement ratio,qualities and workabili...

types mixing,curing,water cement ratio,qualities and workability

Inspection and quality control certificate, Q. Inspection and Quality Contr...

Q. Inspection and Quality Control Certificate : A 'lot' under inspection should be accepted by the inspector when no defect is found in the acceptance level tests and so certif

Doors and windows, important considerations in case of doors and windows

important considerations in case of doors and windows

Moment redistribution, how to draw the shear diagram after redistribution o...

how to draw the shear diagram after redistribution of moments

Increasing concrete cover beyond contractual, Question If contractor sugges...

Question If contractor suggests increasing concrete cover beyond contractual such as 40mm to 70mm shall engineers accept suggestion? Answer In contractual part, based on requir

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd