Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

What is a projection line, Projection line is the way, in which the earth i...

Projection line is the way, in which the earth is made known on a flat piece of paper.

Reasons of using compressed air as drilling fluid, Q. Reasons of using comp...

Q. Reasons of using compressed air as drilling fluid? For rotary drilling in ground investigation works, drilling fluid is generally used to clear and clean the cuttings from t

Bridge design, criteria for economical span length in bridge

criteria for economical span length in bridge

Cement, uses of heavy weight aggregate

uses of heavy weight aggregate

Choosing between trailer suction hopper and grab dredgers, Question In ...

Question In search reclamation, what are considerations in choosing between trailer suction hopper dredgers and grab dredgers ? Answer Trailer suction hopper dred

Environmental engineering, A nearly horizontal, 12 ft wide rectangular chan...

A nearly horizontal, 12 ft wide rectangular channel carries 60 cfs at a depth of 3.0 ft. The width of the channel is smoothly contracted to 6 ft at the downstream section. (a) Dete

What should be the hydrometer reading, A litre of suspension containing 0.5...

A litre of suspension containing 0.5 N of soil with a specific gravity of 2.70 is prepared for a hydrometer test. When no temperature correction is considered necessary, what shoul

Define hand tools for underwater inspection of bridge, Define Hand Tools fo...

Define Hand Tools for Underwater Inspection of Bridge? Hand tools involve scrapers, wire brushes, chain and wire ropes. Tools of this kind are suited in which cleaning is confi

Formation of holes in pipelines, Question While branch pipelines are co...

Question While branch pipelines are connected to pipelines, now and then Y-junctions or fitting branched pipelines to key pipelines by formation of holes in pipelines are u

Determine the probable period of time, A clay stratum is 4.5 m thick and re...

A clay stratum is 4.5 m thick and rests on a rock surface. The coefficient of consolidation of a sample of this clay was found to be 4.5 × 10-8 m 2 /s in the laboratory. Verify pro

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd