Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Moisture content, What is moisture content for road work

What is moisture content for road work

Digit of cells for concrete box girder bridges, Question How does an engine...

Question How does an engineer determine digit of cells for concrete box girder bridges ? Answer If depth of a box girder bridge exceeds 1/6 or 1/5 of bridge width, then it is o

Explain statically indeterminate structures, Explain Statically Indetermina...

Explain Statically Indeterminate Structures  Fall into two categories:   1.  Beam problems with additional supports/restraints 2.  Axial bar members subjected

PRC, what is the bleeding of concrete?

what is the bleeding of concrete?

Problems formed while design of pre-stressed concrete, Determine the proble...

Determine the problems formed while design of pre-stressed concrete Two types of problems are encountered by  the engineer engaged in the design of pre-stressed concrete membe

Unloaded propped, Ask questa) In an unloaded propped cantilever, the proppe...

Ask questa) In an unloaded propped cantilever, the propped end sinks vertically relative to the fixed end by an amount ? due to poor construction of the foundation of the prop. Wha

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd