Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Mollusca, what is the taxonomy of phylum molluska

what is the taxonomy of phylum molluska

What is a footing foundation for a water tower, A footing foundation for a ...

A footing foundation for a water tower carries a load of 9000 kN and is 3.6 metres square. It rests on dense sand of 9 m thickness overlying a clay layer of 3 metres depth. The cla

State the term - relaxation of stress in steel, State the term - Relaxation...

State the term - Relaxation of Stress in Steel If we keep a high-tensile steel wire stretched and maintained at a constant strain, the value of the force in the wire does not

Total volume of soil that excavated from the borrow area, Project specifica...

Project specifications require a relative compaction of 95% (modified Proctor).  Construction of a highway embankment requires 10,000-yd 3 of fill.  The borrow soil has an in-situ

Calculate the natural frequency of the system, A machine weighing 500 kN is...

A machine weighing 500 kN is mounted on a concrete block resting on soil. The base area of the block is 25 m 2 , and the weight is 100 kN. The coefficient of elastic uniform com

What is the external load acting on a pre-stressed beam, What is the extern...

What is the external load acting on a pre-stressed beam In the elastic range, a variation in the external load acting on a pre-stressed beam results in a change in the location

Surveying, Distance ABC was measured with a 30m. Chain tested and found to ...

Distance ABC was measured with a 30m. Chain tested and found to be correct in the beginning of the work .after measuring AB=1.2 km chain was found to be 10 cm. To long chaining was

Road base and base course in flexible carriageway, Road base vs. base cours...

Road base vs. base course in flexible carriageway Roadbase is the most significant structural layer in bituminous pavement. It's designed to take up the function of distributi

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd