Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Comparison of pre and post-tensioning, Comparison of pre and post-tensionin...

Comparison of pre and post-tensioning A comparison between pre-tensioned and post-tensioned concrete members can be made on the basis of the following considerations. (a) T

Explain the variable conditions of river flow - bridges, Explain the Variab...

Explain the Variable Conditions of River Flow and Health State? The variable conditions of river flow and health state of structure demands constant supervision.  Although scou

Masonry, Sketches for English bond, Stretcher bond, Header bond, Flemish bo...

Sketches for English bond, Stretcher bond, Header bond, Flemish bond in first & second layer plan, elevation and 3 dimensional view of brick bond.

Show the filter below the revetment, Q. Show the filter below the revetment...

Q. Show the filter below the revetment? A filter placed between the revetment / protection works at the surface and the soil bed below the revetment / protection works. Main fu

Define chlorides - underwater inspection of bridge, Define Chlorides - unde...

Define Chlorides - underwater inspection of bridge? Chlorides do not attack plain concrete when present in the concentrations that normally exist in seawater, but may greatly a

Determine the magnetic declination at a place, Example : Determine th...

Example : Determine the declination at a place, if at noon the magnetic bearing to the sun is (a) 358° (b) 185° Solution: (a) Referring to given figure (a) since the ma

The effects of earthquake on spatial trusses, Evaluation of various reports...

Evaluation of various reports regarding the effects of earthquake on spatial trusses History and static In this section we aim to provide a summary report of what was happ

Verify the optimum value of the spacing of the piles, A 16-pile group has t...

A 16-pile group has to be arranged in the form of a square in soft clay with uniform spacing. Neglecting end-bearing, verify the optimum value of the spacing of the piles in terms

Bituminous concrete, Bituminous Concrete: Bituminous Concrete (BC) is...

Bituminous Concrete: Bituminous Concrete (BC) is a hot-mix superior type of bituminous surfacing, having a low voids (3-5 per cent), good durability high imperviousness and g

Joint filler in concrete expansion joints - a must, Joint filler in concret...

Joint filler in concrete expansion joints - a must?? Presence of joint filler is required to the proper functioning of concrete joints however some may doubt its value. For a c

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd