Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Behaviour of elastomeric bearings, Q. Behaviour of elastomeric bearings ? ...

Q. Behaviour of elastomeric bearings ? In order to carry out successful design and installation of elastomeric bearings, it is necessary to understand the behaviour of elastome

Uses of lime, Uses of Lime Uses of lime in civil works are following : ...

Uses of Lime Uses of lime in civil works are following : For making mortar  for masonry works and plastering For white washing. For soil stabilization. To produc

Wall method of estimation, 1. Can you enumerate the benefits of individual ...

1. Can you enumerate the benefits of individual wall method of estimation? 2. Estimate the single room of size 3m x 4m x height 3m  using individual wall method? 3. Which met

Contours, how can you draw contours of a non square grid?

how can you draw contours of a non square grid?

Explain condition rating number, Q. Explain Condition Rating Number? 1....

Q. Explain Condition Rating Number? 1. A Condition which warrants rebuilding / re-habilitation immediately. 2. A Condition which requires rebuilding / re-habilitation on pro

Fire resistance of steelwork, Q. Fire resistance of steelwork Because ...

Q. Fire resistance of steelwork Because of the high thermal conductivity of steel, temperature of unprotected steel is almost the same as temperature of fire. Because the yiel

State the modulus of elasticity of concrete, State the Modulus of Elasticit...

State the Modulus of Elasticity of Concrete The Young's modulus of elasticity of concrete is primarily influenced by the elastic properties of the aggregate and to a lesser ex

Calculate the initial height of the stockpile, On a 5-acre level terrain bu...

On a 5-acre level terrain building site, an earthwork contractor has instructed her crew to strip and grub the topsoil of a 60,000-ft 2 proposed building pad to a minus 2-ft sub-g

Bedding of precast concrete paving units, Q. Sand layer vs. cement sand use...

Q. Sand layer vs. cement sand used as bedding of precast concrete paving units Cement sand is a mixture of sand and cement and it behaves as a cohesive mass once mixed. Usuall

Distance between concrete columns in 5 story building, distance between con...

distance between concrete columns in 5 story building and if there is distance 15 feet than what should be the column size and how many bars and diameter of each bar ?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd