Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Transitional jacks designed in pipe jacking projects, Question Why are ...

Question Why are transitional jacks designed in pipe jacking projects? Answer While development of pipe jacking stops, building up of confrontation is extremely

Tests on bricks, Tests on Bricks The following laboratory tests can be...

Tests on Bricks The following laboratory tests can be conducted on the bricks to find their suitability: 1.    Crushing strength 2.    Absorption 3.    Shape and size

Corrosion protection of lifting anchors in precast concrete, Q. Corrosion p...

Q. Corrosion protection of lifting anchors in precast concrete? Corrosion of lifting anchors in precast concrete units has to be prevented since the corroded lifting units caus

Som, derive the expression for stress in arbitrary plane in a body subjecte...

derive the expression for stress in arbitrary plane in a body subjected to bi axial stress condition

What is standard penetration test, a) Describe the recommended construction...

a) Describe the recommended construction practices to avoid deterimental differential settlement in large structures. (b) What is meant by bearing capacity of soil? How will ver

Explain the methods of underwater inspection, Explain the Methods of Underw...

Explain the Methods of Underwater Inspection? There are three common methods of carrying out underwater inspection of bridge elements. a)  Wading inspection b)  Scuba div

., WHAT IS PILE CORROSION

WHAT IS PILE CORROSION

Assignment, do u do drawing assignment ( 3rd angle projection)

do u do drawing assignment ( 3rd angle projection)

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd