Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Water control for sheet pile walls, Q. Water control for sheet pile walls? ...

Q. Water control for sheet pile walls? Ground water flow into excavations constructed by sheet pile walls must be minimized in order to save the cost of the provision of pumpin

Distomat., write a note on distomat

write a note on distomat

Properties of stones, Properties of Stones The following properties of ...

Properties of Stones The following properties of the stones should betake into account before choosing them for engineering works: Structure: The structure of the stone ca

How can a temporary diversion to laid, Q. How can a temporary diversion to ...

Q. How can a temporary diversion to laid a cross flowing river in case of disruption to rail traffic over a major bridge lasting over 6 months. Ans.- Temporary diversion

Factors affecting location decision, Factors Affecting Location Decision: ...

Factors Affecting Location Decision:   Mining, quarrying and heavy manufacturing have capital intensive facilities that are costly to build and cover large area and use large q

Gg, ggggggggggg

ggggggggggg

Remedial proposal to rectify situation, Question During deep excavatio...

Question During deep excavation , neighbouring ground water table is drawn down that might affect settlement of nearby buildings. What is remedial proposal to rectify situatio

Modern marketing-integrated marketing communications, Modern marketing call...

Modern marketing calls for more than just developing a good product, pricing it attractively, and making it available to target customers. Companies must also communicate with thei

Joint continuity influenced by inclined bridge deck, Q. Joint continuity in...

Q. Joint continuity influenced by inclined bridge deck? Bearings are generally designed to sit in a horizontal plane so as to avoid the effect of extra horizontal force and une

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd