Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Enumerate the term - superposing the stress variations, Enumerate the term ...

Enumerate the term - superposing the stress variations If the case of concentric pre-stressing is considered, we can appreciate that stress at any section of the beam is compr

Process of lubrication of girder bearing, Q. Process of Lubrication of Gird...

Q. Process of Lubrication of Girder Bearing? Oiling and greasing of bearings is done to ensure that the bearings are well lubricated and working freely to permit expansion and

CAD IN CIVIL ENGINEERING DRAWING LAB, EXPLAIN THE PROCEDURE FOR PREPARATIO...

EXPLAIN THE PROCEDURE FOR PREPARATION OF DRAWING USING AUTOCAD FOR RAPID SAND FILTER

Working from whole to part in survey, a clear illustration about working to...

a clear illustration about working to part principle and some examples

Phase, Each physical homogeneous type (solid, liquid orvapour) is a phase. ...

Each physical homogeneous type (solid, liquid orvapour) is a phase. Two or three phases may coexist.  e.g. Ice and water at 0 o C.  Mixtures of gases (e.g. Air) can only be

Inspection of girder bridge, Q. As an AEN in charge, what inspection will...

Q. As an AEN in charge, what inspection will you under taken at the time of inspection of Girder Bridge 3 x 60 feet. Please explain the important items to be o

Building classification, Why I is the missing after h and J is written in t...

Why I is the missing after h and J is written in the classification of building

Pre-stress girder/ I Beam design and Triaxial lab report, I need urgent su...

I need urgent support in my assignment and also my UU triaxial lab report. thanks Maryam

Road materials, Road Materials Earthwork and pavements constitute a si...

Road Materials Earthwork and pavements constitute a significant part of the cost of a road. Hence it is desirable that thorough investigations be done about the availability o

Explain fluidized-bed incinerators, Explain Fluidized-Bed Incinerators ...

Explain Fluidized-Bed Incinerators sand is heated to 800C by oil or gas and blown around (fluidized) by a blower that sends air from bottom upward heated fluidized san

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd