Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Centroid, use of centroid in civil engineering

use of centroid in civil engineering

What is the main reason being for the phenomenon, Sometimes side of concret...

Sometimes side of concrete bridges is observed to turn black in colour . What is the main reason being for the phenomenon ?

Chain survey, what are the obstacles in chain survey in brief

what are the obstacles in chain survey in brief

Embankment construction, Embankment Construction: Selection of Soil...

Embankment Construction: Selection of Soil Soil is the material used for embankment construction, though other materials like rock and fly-ash are also used in specia

Binders - cement, Binders : Cement: Cement as a Binder Cement...

Binders : Cement: Cement as a Binder Cement is one of the main ingredients of concrete. When cement sets (with the addition of water), it forms a paste and binds the

Calculate the pressure on the other end, Q. 50 liters per sec of water flow...

Q. 50 liters per sec of water flow in a horizontal pipeline which is 200m long and the centerline of which is 3 m above the datum line. The pipe tapers from 30 cm diameter to 20 cm

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd