Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Track design for line speed improvements, The objective of this module is:-...

The objective of this module is:- For the student to identify the track design issues and there relationships that will need to be considered in the development of a feasibil

Explain the difference in elevation between bm and tp2, Based on the inform...

Based on the information provided in Figure, the difference in elevation between BM and TP 2 is most nearly: Solution: Set up a Table as shown below and insert the kno

Determine the plastic limit of the soil, The liquid limit of a clay soil is...

The liquid limit of a clay soil is 56% and its plasticity index is 15%.  (a) Name the state of consistency is this material at a water content of 45% ? (b) Determine the plas

Piers and piles, what is the difference between piers and piles?

what is the difference between piers and piles?

Principal stresses and strains, Principal Stresses and Strains: Princi...

Principal Stresses and Strains: Principal Stresses and Strains is a very important link in the analysis of solids so as to make sure safe design of different components of str

Define shear slump and collapse slump in slump test, Q. Define Shear slump ...

Q. Define Shear slump and collapse slump in slump test? There are three kinds of slump which can take place in a slumps test, namely, true slump, shear slump and collapse slump

CUBE STRENGTH, IN CASE CUBE IS FAIL WHAT CAN IDO

IN CASE CUBE IS FAIL WHAT CAN IDO

Compute the thermal stresses in steel, Compute the thermal stresses in stee...

Compute the thermal stresses in steel: Consider the compound bar shown in below figure consisting of a steel bolt of diameter 18 mm, surrounded through a copper tube of outer

State the term - calculation of deformation of concrete, State the term - c...

State the term - calculation of deformation of concrete For the calculation of deformation of concrete at some stage before the maximum shrinkage is reached, it may be assumed

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd