Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Define the finish-to-start dependency, Sheet rock cannot be installed in th...

Sheet rock cannot be installed in the new house you are building until a building inspector approves the plumbing, electrical, HVAC, and insulation.  This is an example of:

Trigo, A pole which leans 11o from the vertical toward the sun casts a shad...

A pole which leans 11o from the vertical toward the sun casts a shadow 12m long when the angle of elevation of the sun is 40o. Find the length of the pole

Find out the joint distribution, Find out the joint distribution: Let ...

Find out the joint distribution: Let X I and X 2 be two independent random variables each distributed uniformly in the interval [ 0, a ], where a > 0 is a constant. Find out

Explain the system curves - pumping system, Explain the System Curves - Pum...

Explain the System Curves - Pumping System Non-linear plot beginning on the y-axis at the Total Static Head (TSH) and plotted primarily based on the h f .

Solid mensuration, a street light is 15 ft directly above the curb. a 6 ft ...

a street light is 15 ft directly above the curb. a 6 ft man starts 10 ft down the street from the light and walks directly across the street which is 10 ft wide. when he reaches th

IRC Class AA loading in existing industrial areas, For IRC Class AA loading...

For IRC Class AA loading in existing industrial areas, what is load (kN/m) has to applied base don the wheel loads. especially raft foundation & roads are at same level.

Trigo, a pilot entering a bay on course

a pilot entering a bay on course

Remedial measures for problems in turbid water - reflection, Remedial measu...

Remedial measures for Problems in Turbid Water - Reflection? The problem of reflection can be minimised by carefully placing the flash away from the axis of the camera and at a

Bearing, difination of magnative bearing

difination of magnative bearing

Compatibility condition, Compatibility Condition: Total strain in ste...

Compatibility Condition: Total strain in steel = Total strain in copper i.e. 3 × 10 -4 + 1.965 × 10 -5 P s   = 4.5 × 10 -4 + 1.8421 × 10 -5 P c Recognising that P

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd