Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Residual stresses in steel after welding, Q. Residual stresses in steel aft...

Q. Residual stresses in steel after welding? Considerable residual stresses are persuaded in connecting steel members after welding operation. Local temperature of steel where

Free- fall concrete placement in bored piles, Q. Free- fall concrete placem...

Q. Free- fall concrete placement in bored piles? Based on the research by STS Consultants Ltd it was found that concrete placed by free falling below 120 feet will not suffer f

Application of levelling, how do I draw sections(longitudinal and cross sec...

how do I draw sections(longitudinal and cross sections)?

Test for determination of shear modulus, Test for determination of Shear Mo...

Test for determination of Shear Modulus Conditioning load : Bearings shall be preloaded with maximum horizontal load Htest (with Ntest or vertical load held constant) and un

Joints in concrete pavements, Joints in Concrete Pavements: Concrete ...

Joints in Concrete Pavements: Concrete pavements in India are of the jointed plain (unreinforced type). The following types of joints are needed in them : (a) Transverse C

Manage civil work design, Ask question #Minimum 1Make a detailed list of al...

Ask question #Minimum 1Make a detailed list of all constraints and requirements to the bridge design00 words accepted#

Computer programming, compare 2 numbers and print either the message identi...

compare 2 numbers and print either the message identifying the greater than number(or) the message starting that both number are equal

Timber, TIMBER Timber refers to wood utilized for construction works. A...

TIMBER Timber refers to wood utilized for construction works. Actually the word timber is derived from an old English word 'Timbrian' that means 'to build'. A tree that yields

Survey 1, describe how you would range a surveying line betwen two point wi...

describe how you would range a surveying line betwen two point wich are not entervisible?

Verify the total active thrust on the wall per lineal metre, A smooth backe...

A smooth backed vertical wall is 6.3 m high and retains a soil with a bulk unit weight of 18 kN/m 3 and φ = 18°. The top of the soil is level with the top of the wall and is horiz

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd