Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Statics - rigid body of equilibrium, The ball of a trailer hitch is subject...

The ball of a trailer hitch is subjected to a force F. If the failure occurs when the moment of point F around point A reaches 11250 in lbs, determine the largest value F may have

Hydraulics, The atmospheric pressure is given 680 mm Hg at a certain mounta...

The atmospheric pressure is given 680 mm Hg at a certain mountain location of elevation 2000 m. air density is 1.007 kg/m3. Find the pressure in kPa.

Determine the ground elevation, The trigonometric levelling from the survey...

The trigonometric levelling from the surveyor's notes is shown below. The ground elevation of T (ft) is most nearly: Solution:  The elevation of point P can be found from: E

Determine the allowable pressue, The data profile as shown in Figure is obt...

The data profile as shown in Figure is obtained. A best average of N values gave N 10 = 21, column loads including dead and live loads ranged from 500 kN to 950 kN. Determine the

Impact of possible energy, a) Take into consideration the boiler efficiency...

a) Take into consideration the boiler efficiency, and verify the cost of heating the building, during the heating season, using present oil and gas prices.  b) Investigate the i

Bulking of sand, what is the permissible limit of sand

what is the permissible limit of sand

Determine the major role of construction, Determine the major role of const...

Determine the major role of construction A major part of civil engineering construction involves the use of cement concrete. Concrete has a good compressive strength and works

Effective span, what do u mean by effective span and its derivation?

what do u mean by effective span and its derivation?

.levelling, differentiate between Dumpy level:The Wye or Y level:Cooke''s r...

differentiate between Dumpy level:The Wye or Y level:Cooke''s reversible level: Cushing''s level:Tilting level and Automatic level

Vertical curves - geometric design of roads, Vertical Curves: When tw...

Vertical Curves: When two vertical gradients meet, it is necessary to provide a vertical curve. Two types of vertical curves are used: (a) Summit curve, where the point of

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd