Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Discuss about the term - end zone, Discuss about the term - End Zone It...

Discuss about the term - End Zone It is the length of a post-tensioned concrete member, at the end, which is required to get a distribution of prestress over the whole of the c

Define wastewater treatment processes, Define Wastewater treatment Processe...

Define Wastewater treatment Processes The wastewater treatment processes that we design mimic the processes that occur in the nature (for example processes that occur in a flow

The covers of electrical machines are made of what materials, The covers of...

The covers of electrical machines are made of what materials ? Answer: It is made of  soft magnetic materials.

Explain the contracted rectangular weir, Explain the Contracted Rectangular...

Explain the Contracted Rectangular Weir Weir plate has sides which extend above the maximum water surface, directing the flow through an opening (b = weir length). Typically th

Show elastomeric bearings, 1. Elastomeric bearings must not be placed one b...

1. Elastomeric bearings must not be placed one behind the other along the longitudinal axis of the girder on a single line of support under any circumstances. 2. Bearings of dif

Explain transpiration and infiltration, Explain Transpiration and Infiltrat...

Explain Transpiration and Infiltration Transpiration: The part of evaporation in which water vapor enters the atmosphere through the plants. The "transpired" water originated

#tile.., Material for formwork and their specifications

Material for formwork and their specifications

Quantity calculation for subgrade preparation, reparation of subgrade in sq...

reparation of subgrade in sqm for a road of span 12 km and width 5.25m,with shoulders of 0.75m span on both the sides...considering extrawidening too......plz help...i m preparing

How to design marginal embankments, Q. How to design Marginal Embankments? ...

Q. How to design Marginal Embankments? Design aspects of marginal embankments are similar to those of approach banks. The aspects needing special attention are dealt with below

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd