Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Between capping beams and ground beams for piles, Question What is majo...

Question What is major disparity between capping beams and ground beams for piles? Answer Capping beams for piles plan to transferring loads from directly spaced c

Dam, tupes of dam

tupes of dam

Show elastomeric bearings, 1. Elastomeric bearings must not be placed one b...

1. Elastomeric bearings must not be placed one behind the other along the longitudinal axis of the girder on a single line of support under any circumstances. 2. Bearings of dif

Explain the ion exchange water softening, Explain the Ion Exchange water So...

Explain the Ion Exchange water Softening Softening is usually done using a resin (natural or synthetic long chain chemical with a sodium ion attached). When water containing ha

Determine the final volume of the compacted soil, 30,000-yd 3 of banked so...

30,000-yd 3 of banked soil from a borrow pit is stockpiled before being trucked to the jobsite.  The soil has 28% swell and shrinkage of 18%.  The final volume of the compacted so

Offset, what is the meaning of offset

what is the meaning of offset

Direct levelling, to find height difference between two or more points in d...

to find height difference between two or more points in different conditions

Timber, structure of exogenous trees

structure of exogenous trees

Supply each tremie pipe with a single concrete truck, Question Througho...

Question Throughout concreting of diaphragm walls , three tremie pipes are used in single time. But, only one concrete truck is obtainable. How have to concreting works been a

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd