Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Theory of structure, How to convert uniformly varying load to point load

How to convert uniformly varying load to point load

Major considerations in selecting marine plants, Question What are majo...

Question What are major considerations in selecting marine plants and land plants for fitting of band drains? Answer For fitting of band drains by marine plants,

Determine the meaning of prestressed concrete, Determine the meaning of Pre...

Determine the meaning of Prestressed Concrete It is a type of concrete in which permanent internal stresses of  a suitable nature, magnitude and distribution are intentionally

Air traffic control, Air Traffic Control: Importance of Air Traffic...

Air Traffic Control: Importance of Air Traffic Control Air Traffic Control is a system by which routes for flying aircraft are defined, flight rules are framed, and f

Analyse the state of stress, Analyse the state of stress: For the cros...

Analyse the state of stress: For the cross-section shown in above figure, let us take b = 100 mm, d = 300 mm and M = 9 × 10 7 N mm and Q = 18 × 10 4 N and analyse the state

Designing sewer pipes, Question While designing sewer pipes , why vitr...

Question While designing sewer pipes , why vitrified clay pipes commonly is used for pipe size less than 600mm still as precast concrete pipes with PVC lining is used for pipe

Remedial measures for problems in turbid water - absorption, Define Remedia...

Define Remedial measures for Problems in Turbid Water - Absorption? The process of absorption of light can be overcome by using higher powered lighting, or by using more light

Calculate the horizontal distance, Calculate the Horizontal Distance A ...

Calculate the Horizontal Distance A surveyor's total station measured slope distance near station 3245+26.35 is recorded as 437.380-m with a zenith angle of 118º 48' 07" and a

Statics - rigid body of equilibrium, The ball of a trailer hitch is subject...

The ball of a trailer hitch is subjected to a force F. If the failure occurs when the moment of point F around point A reaches 11250 in lbs, determine the largest value F may have

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd