Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Lead products in construction, What are the advantages and disadvantages of...

What are the advantages and disadvantages of lead products in construction? Ans) Disadvantages: -Lead is very toxic; its use can result in pollution of the ground and more signi

Define hammer efficiency and coefficient of restitution, Q. Define Hammer e...

Q. Define Hammer efficiency and coefficient of restitution? Hammer efficiency refers to ratio of kinetic energy of hammer to the rated energy (or potential energy). Basically i

Design of flexural members, Design of Flexural Members: Here you have ...

Design of Flexural Members: Here you have learnt how to design simple steel beams of rolled steel sections subjected to transverse loading. You have also known how to take

Practice to form washout regulators, Question Why are two gate regulato...

Question Why are two gate regulators necessary in regular practice to form washout regulators ? Answer In fact, situation is analogous to that of fire hydrants in tha

Determine about the prestressed concrete, Determine about the prestressed c...

Determine about the prestressed concrete In prestressed concrete the most important parameter is the prestressing force. Ifthe prestressing force reduces with time, prestresses

Bearing pressure on soil nail, Question What is relation of bearing pr...

Question What is relation of bearing pressure on soil nail head to ratio La/Lb, where La is length of soil nail before potential slip circle as Lb is length of soil nail beyo

Can you explain curved heads, Q. Can you explain Curved heads ? In case...

Q. Can you explain Curved heads ? In case of rivers carrying high discharges of the order of 28300 m 3 Is and above, Gale's recommendations are more conservative than Spring's

Geology class, I want to get answer of each questions that I Have in a sep...

I want to get answer of each questions that I Have in a separate paragraphs, and the information should be from sources so please fro each question that you answer write after it t

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd