Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Civil engineering drawing, Explain step by step procedure involved in the a...

Explain step by step procedure involved in the analysis and design of balanced cantilever bridge.

Cement, manufacture of cement by dry process

manufacture of cement by dry process

Principles and Practices of Management, How Will You Influence People to St...

How Will You Influence People to Strive Willingly for Group Objectives in Your Organization (Target Based Industry)? Apply Your Interpersonal Influence Through Communication Proces

Compute interior or intersection angle, Compute Interior or Intersection An...

Compute Interior or Intersection Angle for the following circular curve:   Answer- I = 180° - 60° - 60°= 60

Construction of concrete carriageway, Question If construction of conc...

Question If construction of concrete carriageway is carried out in summer, be capable of expansion joints be omitted? Answer If construction of concrete carriageway

Temporary repairs to rail fracture, Q. Temporary Repairs to rail fracture? ...

Q. Temporary Repairs to rail fracture? If a welding party is not readily available, the fracture shall be repaired by using a cut-rail (not less than 4 meter long) and clamped/

Calculate the uniform pressure on the soil, The plan of a proposed spoil he...

The plan of a proposed spoil heap is shown in Fig. The heap will stand on a thick deposit of soft clay with E-value 15 MN/m 2 . The uniform pressure on the soil may be suppose as 1

Void ratio, why void ratio is greater for fine gained soil then course grai...

why void ratio is greater for fine gained soil then course grained soil.

What do you mean by distressing, Q. What do you mean by Distressing? Di...

Q. What do you mean by Distressing? Distressing is the operation under taken with or with out rail tensors to secure stress free condition in the LWR at a desired rail temperat

Determine the allowable bearing pressure of the sand, Two load tests were c...

Two load tests were conducted at a site-one with a 0.5 m square test plate and the other with a 1.0 m square test plate. For a settlement of 25 mm, the loads were found to be 60 kN

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd