Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Define well steoning, Q. Define Well Steoning? It is the side wall of w...

Q. Define Well Steoning? It is the side wall of well foundation. It is built of masonry or cement concrete not less than M 10 grade, sufficient bond rods should be provided to

Steel work design, 1) A building constructed from steelwork requires the fo...

1) A building constructed from steelwork requires the following sections to be designed: a. A beam carrying a characteristic permanent load of 11kN/m and a characteristic variable

Drainage of embankment slopes, Drainage of Embankment Slopes: Slopes ...

Drainage of Embankment Slopes: Slopes of high embankments get eroded by rain water. Deep rain cuts are formed, which endanger the pavement. In such cases, it is customary to

Some compound or metal vanishes under certain conditions is , Some compound...

Some compound or metal vanishes under certain conditions is? Answer: Due to Super conductivity some compound or metal vanishes

Physical evaluation of food grains, Q. Physical evaluation of food grains? ...

Q. Physical evaluation of food grains? Food grains are judged for quality by their physical, chemical and microbiological examination. The physical examination includes chec

Define steel substructure - underwater inspection of bridge, Define Steel s...

Define Steel substructure - underwater inspection of bridge? Steel is used as a structural material and as external protective cladding on concrete foundation elements. Steel f

What are the various impurities in water, Q. What are the various impuritie...

Q. What are the various impurities in water? Ans.- Impurities in water - The impurities in water are classified as - i. Suspended Impurities. ii. Colloidal Impuritie

Load transfer mechanism, Question What is load transfer mechanism for p...

Question What is load transfer mechanism for paving blocks in pedestrian footway? Answer In Hong Kong, footway is as a rule designed with paving slabs or interlocking b

Strain due to bending, Beam of arbitrary cross-sectionsubjected to couples ...

Beam of arbitrary cross-sectionsubjected to couples M Bending moment at any sectionis M Consider segment of beam subtended by angle θ Some fibres will shorten e.g. ABand o

Specification of water bound macadam road, Q. Specification of Water bound ...

Q. Specification of Water bound macadam road? Formation - The embankment for road shall be made to the cross section shown on the drawing. The bank shall be raised in regular

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd