Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Construction measurment, calculating quantity of excavation, formwork, conc...

calculating quantity of excavation, formwork, concrete

Review of available records - underwater inspection, Review of available Re...

Review of available Records - Preparation for Underwater Inspection? Before taking up the underwater inspection, a detailed review of drawings and past report should be carried

Importance of tendons in post-tensioned members, Importance of Tendons in p...

Importance of Tendons in post-tensioned members Tendons in post-tensioned members are subjected to different amounts of stresses (among themselves) due to following reasons.

Explain the primary treatment for wastewater, Explain the Primary Treatment...

Explain the Primary Treatment for Wastewater Primary Treatment: to remove the pollutants that floats or settles. Typically 60% of suspended solids and 35% of BOD 5 are removed

Explain detention or retention ponds - hydrology, Explain Detention or Rete...

Explain Detention or Retention Ponds Detention/Retention Ponds: Designed to reduce and contain the peak runoff from developed areas (more impervious). Attempt to limit the runo

Overtaking sight distance, Overtaking Sight Distance: Overtaking sight...

Overtaking Sight Distance: Overtaking sight distance is calculated on the assumption that the overtaking vehicle (i) travels behind the overtaken vehicle to perceive the clear

Landing stages - water transportation, Landing Stages: A landing stage...

Landing Stages: A landing stage is a floating structure, usually a pontoon or a barge, which is secured to the shore by mooring chains. Small ships can dock against the landin

Wall method of estimation, 1. Can you enumerate the benefits of individual ...

1. Can you enumerate the benefits of individual wall method of estimation? 2. Estimate the single room of size 3m x 4m x height 3m  using individual wall method? 3. Which met

Fixed and pinned connection between piles and pile caps, Q. Fixed vs pinned...

Q. Fixed vs pinned connection between piles and pile caps? The type of connection amid piles and pile caps affects the load carrying capacity of pile groups. Fixity of pile hea

Draw the shape of the pressure line, Draw the shape of the Pressure line. ...

Draw the shape of the Pressure line. Solution The locations of resultant force at sections A-A, B-B  and C-C have already been determined. Joining these locations, we can dr

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd