Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Describe the geophysical profileof borings, Describe the Geophysical Profil...

Describe the Geophysical Profileof Borings The variation in the thickness of the soil stratum for engineering application is known as the geophysical profile. Figure 1.2 shows

Define the hazard ranking system (hrs), Define the Hazard Ranking system (H...

Define the Hazard Ranking system (HRS) - A procedure for ranking uncontrolled hazardous waste sites in terms of the potential threat based upon the containment of the route of

Major functions of features observed in a typical manhole, Question Wha...

Question What are the major functions of following features observed in a typical manhole ? Answer (i) Groove near benching, (ii) R.S.J. (iii) double seal manhole cove

Explain the term - circular prestressing, Explain the term - Circular Prest...

Explain the term - Circular Prestressing This term refers to the case when tendon profile is provided in a round shape, such as in water tanks and pipes, etc.

Movement accommodation factor for joint sealant, Movement accommodation fac...

Movement accommodation factor is normally specified by manufacturers of joint sealants for designers to design dimension of joints. It is stated as the total movement that a joint

Determine the area ratio of a thin walled tube, Determine the area ratio of...

Determine the area ratio of a thin walled tube samples having an external diameter of 6 cm and a wall thickness of 2.25 mm. Do you recommend the sampler for getting undisturbed soi

Timber design, design of timber in flexural members in terms of extreme fib...

design of timber in flexural members in terms of extreme fibre stress in bending, maximum horizontal shear stress, deflection and bearing stress perpendicular to the grain. the ful

What is load carrying capacity of a pile, Q-  What are loads and forces ta...

Q-  What are loads and forces taken into account for designing a pile and what is load carrying capacity of a pile. Ans. For designing a pile the following loads and force ar

Properties of ordinary portland cement, Properties of Ordinary Portland Cem...

Properties of Ordinary Portland Cement (i) Chemical properties: Portland cement consists chemical compounds are following: (a) Tricalcium silicate          3 CaO.SiO 2 (C

Importance of geotextiles and sand in reclamation works, Question What ...

Question What is main importance of geotextiles and sand in reclamation works? Answer For geotextiles used in recovery, they serve mainly subsequent two purposes

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd