Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Define the process of eccentric prestressing, Define the proess of Eccentri...

Define the proess of Eccentric Prestressing In this form of prestressing, the centroid of cross-sectional areas of tendons is not located at the centroid of the cross-section.

Major bridge and important bridge, Major bridge - Major bridge is one of wh...

Major bridge - Major bridge is one of which has a total linear waterway of 18 m or more for multiple span and total linear water way of 12 m or more for single span. Important b

Open chanel flow, A rectangular channel is 3 m in width and draws water fro...

A rectangular channel is 3 m in width and draws water from a lake. The channel slope is 0.001 and the Manning’s n is 0.0013. What will be the discharge in the channel when the lake

Bearing pressure on soil nail, Question What is relation of bearing pr...

Question What is relation of bearing pressure on soil nail head to ratio La/Lb, where La is length of soil nail before potential slip circle as Lb is length of soil nail beyo

Void ratio and dry density of a soil, Q. Define water content, void ratio ...

Q. Define water content, void ratio and dry density of a soil. If wet density of a soil is 1.9 gm per cm at a moisture content of 24%, what will be its dry density?  Ans. - W

Complete embedment of pipelines into thrust blocks, Q. Complete embedment o...

Q. Complete embedment of pipelines into thrust blocks For unreinforced concrete thrust blocks in bends and tees for pressurized pipelines, it's recommended that contact surfac

Stone, Explain the crushing strength test

Explain the crushing strength test

Define carbonation - underwater inspection of bridge, Define Carbonation - ...

Define Carbonation - underwater inspection of bridge? Carbon dioxide is present in the air and attacks the concrete directly. It has the effect of destroying the normal passivi

How should reservoir floors be designed, Question In designing of servi...

Question In designing of service reservoirs, how should reservoir floors be designed to avoid leakage of water because of seasonal and shrinkage movements ? Answer I

Surveying, Distance ABC was measured with a 30m. Chain tested and found to ...

Distance ABC was measured with a 30m. Chain tested and found to be correct in the beginning of the work .after measuring AB=1.2 km chain was found to be 10 cm. To long chaining was

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd