Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Define the types of pump performance curves, Define the types of Pump Perfo...

Define the types of Pump Performance Curves Two types of pump performance curves: x-axis = flow rate; y-axis = head (TDH). Characteristic curves: Provided by the pump m

Necessity for road drainage - road drainage, Necessity for Road Drainage: ...

Necessity for Road Drainage: Poor drainage can cause damage to the various components of a road in the following manner: (a) Water can enter the various pavement layers th

Define design aspects of pot bearing, Define Design Aspects of Pot Bearing?...

Define Design Aspects of Pot Bearing? Basic elements of a POT bearing are: - POT or a shallow cylinder - An elastomeric pad - A set of sealing rings - A piston P

Softening test point, the importance of softening point of a bitumen materi...

the importance of softening point of a bitumen material in the design of a pavement

Determine about the tensile stresses, Determine about the tensile stresses ...

Determine about the tensile stresses Unifody prestressed members designed for equal flexure in opposite directions,without permitting tensile stresses under working loads, requ

Assignment, Need assignment for structure concrete work

Need assignment for structure concrete work

Hydraulic design problems, This assignment is a Hydraulic Design assignment...

This assignment is a Hydraulic Design assignment for Civil Engineering Major in USA. Please try if there is someone professional who can do this work because it''s too sensitive. f

Purpose of using capping layers in pavement construction, Q. Purpose of usi...

Q. Purpose of using capping layers in pavement construction? When California Bearing Ratio of subgrade is checked to be below a specific percentage (for example 5%), a capping

Designing of service reservoirs, Question In designing of service res...

Question In designing of service reservoirs , straight reinforcement in walls of reservoirs is placed at external layer. Give some specific and main reasons?   Answer

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd