Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Examples of stabilised pavement layers, Examples of Stabilised pavement lay...

Examples of Stabilised pavement layers: Examples Sand-clay mixture Sand-gravel mixture Soil-aggregate mixture Soil-soft aggregate mixtures (b)

Land Surveying, What is the difference between accuracy and precision.

What is the difference between accuracy and precision.

Levelling, the cooke''s reversible level

the cooke''s reversible level

California bearing ratio, California Bearing Ratio (CBR): The most wi...

California Bearing Ratio (CBR): The most widely used test for determining the supporting power of a soil for designing the thickness of pavements is the California Bearing Ra

Joint continuity influenced by inclined bridge deck, Q. Joint continuity in...

Q. Joint continuity influenced by inclined bridge deck? Bearings are generally designed to sit in a horizontal plane so as to avoid the effect of extra horizontal force and une

Cone, if the diameter of the base remains constant by what factor should th...

if the diameter of the base remains constant by what factor should the altitude be multiplied to produce a cone with twice volume as the original

Total volume of soil that excavated from the borrow area, Project specifica...

Project specifications require a relative compaction of 95% (modified Proctor).  Construction of a highway embankment requires 10,000-yd 3 of fill.  The borrow soil has an in-situ

Riveted and welded joints, Riveted and Welded Joints: This theory deal...

Riveted and Welded Joints: This theory deals with riveted and welded connections. In riveted connections, you have learnt different types of rivet and various parameters perta

Chain surveying, describe setting out right angle at given point on a chain...

describe setting out right angle at given point on a chain line and when the point lies outside the chain line

Yugty, #quesjjhjhhjtion..

#quesjjhjhhjtion..

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd