Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Grillage foundation, what are the advantages of grillage foundation and why...

what are the advantages of grillage foundation and why people prefers that?

Compute the negative skin friction of the pile group, A square pile group o...

A square pile group of 9 piles passes by a recently filled up material of 4.5 m depth. The diameter of the pile is 30 cm and pile spacing is 90 cm centre to centre. If the unconfin

Resultant pull, two locomotive moving on opposite bank of a canal can pull ...

two locomotive moving on opposite bank of a canal can pull a vessal parallel to the banks by the means of two rope.the force in the ropes are 20kN and 24kN while the total angle be

Work, Grouted or Penetration Macadam:

Grouted or Penetration Macadam:

How we can check caisson is stable or not, A box caisson, 10 m high, is 18 ...

A box caisson, 10 m high, is 18 m × 9 m at the base. The weight of the caisson is 9 MN and its centre of gravity is 4.2 m above the base. Check whether the Caisson is stable. If

Surveying, earthen dam and gravity dam

earthen dam and gravity dam

Total volume of soil that excavated from the borrow area, Project specifica...

Project specifications require a relative compaction of 95% (modified Proctor).  Construction of a highway embankment requires 10,000-yd 3 of fill.  The borrow soil has an in-situ

Main concern regarding design of pavements, Question If In case a road ...

Question If In case a road passes from side to side a reclaimed land and an existing land, what is key main concern regarding design of pavements? Answer For a breathin

Upper floor, We need all types of Upper floor

We need all types of Upper floor

Calculate the actual water cement ratio, Calculate the Actual Water Cement ...

Calculate the Actual Water Cement Ratio A jobsite delivery ticket is shown below for a grout mix.  The actual w/c ratio is most nearly: Solution:       Note, althou

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd