Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

What is bonded post-tensioning, What is Bonded Post-tensioning In post...

What is Bonded Post-tensioning In post-tensioned construction, ducts, in which tendons are provided, are sometimes grouted after the stressing operation. Though the mechanism

Road base and base course in flexible carriageway, Road base vs. base cours...

Road base vs. base course in flexible carriageway Roadbase is the most significant structural layer in bituminous pavement. It's designed to take up the function of distributi

Building classification, Why I is the missing after h and J is written in t...

Why I is the missing after h and J is written in the classification of building

Roads, wbm road step by step procedure

wbm road step by step procedure

Show the specification of bricks, Q. Show the Specification of Bricks? ...

Q. Show the Specification of Bricks? Specification of Ist class Bricks- 1. Table moulded and wire cut. 2. It should have edges and parallel faces. 3. If struck with ha

Shear lag in typical box-girder bridge, Shear lag in typical box-girder bri...

Shear lag in typical box-girder bridge For multiple-cell box girders, there are normally two arrangements. First one is that independent cells are connected by their top flang

Use pot bearings instead of elastomeric bearings, Question Under which ...

Question Under which situation ought to engineers use pot bearings instead of elastomeric bearings ? Answer In an event of high vertical loads shared with large angl

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd