Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Obtain maximum positive moment in a span of continuous beam, Reason of load...

Reason of loading on alternative spans to obtain maximum positive moment in a span of a continuous beam To attain a maximum sagging moment in a span of a continuous beam, gene

Types of surveys and investigations, Types of Surveys and Investigations: ...

Types of Surveys and Investigations: For preparing a good road project, the following surveys and investigations are needed: (a)        Traffic Surveys (b)       Topogr

State about the prestressing steel, State about the Prestressing Steel ...

State about the Prestressing Steel For prestressed concrete members, the high-tensile steel, used generally, consists of wires, bars or strands. The high tensile strength of s

Nonsymmetrical loading of the snow, Nonsymmetrical loading of the snow ...

Nonsymmetrical loading of the snow A decrease in snow weight in some parts of a roof because of the wind, or melting from the heath, or the sun light would reduce internal powe

Concrete carriageway comparatively, Question Why is slump specified in ...

Question Why is slump specified in concrete carriageway comparatively low like 30mmwhen compared with normal concrete like 75mm? Answer Slump of concrete carriageway

Reinforcement, Where we can provided overlap in columns

Where we can provided overlap in columns

Necessity of air valves in pressurized pipelines, Q. Necessity of air valve...

Q. Necessity of air valves in pressurized pipelines? Air valves are broadly categorized into two major types: single air valves and double air valves. Single air valve comprise

Cement, Ask What is the density of cement?

Ask What is the density of cement?

What is the negative skin friction, A square pile group of 16 piles passes ...

A square pile group of 16 piles passes by a filled up soil of 3 m depth. The pile diameter is 25 cm and pile spacing is 75 cm. If the unit cohesion of the material is 18 kN/m 2 an

Define ways of providing the anti slip device - by stops, Define Ways of pr...

Define Ways of providing the anti slip device - By stops? In this method stopper plates or angles are welded to the underside of the girder and embedded in the bed block. It sh

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd