Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Define the pump and motor efficiencies - hydrolic system, Define the Pump a...

Define the Pump and Motor Efficiencies Equations account for the loss of power, primarily due to mechanical friction as a result of rotating components in the pump and motor.

Concrete, types of concrete and its uses

types of concrete and its uses

Explain about the hydrogen embrittlement, Explain about the Hydrogen Embrit...

Explain about the Hydrogen Embrittlement As a result of the action of acids on high-tensile steels, liberation of hydrogen takes place. It penetrates into the steel surface an

Particle size distribution - soil compaction, Particle Size Distribution (G...

Particle Size Distribution (Gradation): The particle size distribution is determined by passing the aggregates through a set of standard IS sieves (Figure) and determining th

Turbines, How do we get electricity even when the gates of a dam were close...

How do we get electricity even when the gates of a dam were closed?

Shallow foundations, The drainage system of a cantilever wall shown in Figu...

The drainage system of a cantilever wall shown in Figure As 1 became blocked after a heavy rainstorm and the groundwater level, which was originally below the base, rose to1.5 (m)

Significance of tailwater level in culverts, Significance of tailwater leve...

Significance of tailwater level in culverts Headwater level and tailwater level of culverts are significant parameters in hydraulic design. Headwater level can't be set too la

Calculate the concrete tensile strength, Calculate the concrete tensile str...

Calculate the concrete tensile strength A 6 in. by 12 in. concrete cylinder resisted a transverse force of 55,000-lbf, at 28 days, in a split tensile cylinder test. Calculate t

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd