Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Breakwaters - harbour layout, Breakwaters: A breakwater is an artific...

Breakwaters: A breakwater is an artificial structure constructed in the sea to protect ships from the effect of waves and storms. Three types of breakwaters are common :

Reinforcement of concrete in contact with internal vibrators, Reinforcement...

Reinforcement of concrete in contact with internal vibrators  At the time of concreting, if internal vibrators are placed accidentally in contact with some of the reinforcemen

Planning of water transport facilities, Planning of Water Transport Facilit...

Planning of Water Transport Facilities: Definition of Terms In water transport system, a number of terms are used. It is necessary for a civil engineer to know the pr

Simply supported beam, draw the shear force and bending moments of a beam

draw the shear force and bending moments of a beam

Define the arrow diagramming method, Define the Arrow Diagramming Method ...

Define the Arrow Diagramming Method Activity-on-Arrow (Branch) with nodes as dependencies Uses finish-to-start precedence only. The solution method for an activity on

What is objective method of assessment, Q. What is objective method of asse...

Q. What is objective method of assessment? Track recording consists of objective method of assessment of the quality of track with the help of sophisticated equipments. A conti

Define the phreatic line and phreatic zone, Define the Phreatic Line and Ph...

Define the Phreatic Line and Phreatic Zone Phreatic Line: In an unconfined aquifer, it represents the water table.   Phreatic Zone: In an unconfined aquifer, it is located b

Explain the clearance interval - signalized intersections, Explain the Clea...

Explain the Clearance Interval - Signalized Intersections  Also known as "Red Clearance Interval" and "All Red"        r = (w+L) / V - If there is no pedestrian traffic r

Water bound macadam, Water Bound Macadam: Water Bound Macadam (WBM) i...

Water Bound Macadam: Water Bound Macadam (WBM) is a dense and compact course of a road pavement composed of stone aggregates held together by a film consisting of gravel or s

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd