Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Tests on stones, Tests on Stones To ascertain the needed properties of ...

Tests on Stones To ascertain the needed properties of stones, described tests can be conducted: A.   Crushing strength test B.   Water absorption test C.   Abrasion te

Lintel, Ask question #classfication of lintel Minimum 100 words accepted#

Ask question #classfication of lintel Minimum 100 words accepted#

Find a suitable slab thickness, The continuous one-way slab shown below is ...

The continuous one-way slab shown below is loaded with a uniform service live load of 80 psf, and a superimposed dead load of 40 psf. Assume the beam width is 16" and use f'c = 5 k

Purpose of the gap in the road on this bridge, What is the purpose of the g...

What is the purpose of the gap in the road on this bridge? Ans) Purpose of the gap in the road is to permit the road to expand and contract with temperature alters without causi

Explain the frequency of inspection - underwater inspection, Explain the Fr...

Explain the Frequency of Inspection - Underwater Inspection? Underwater inspections must be done on every bridge identified for such inspection as per the Indian Railways Bridg

Define friction pendulum bearing, Define Friction Pendulum Bearing? In ...

Define Friction Pendulum Bearing? In friction pendulum bearings, the lateral displacement is permitted at the interface of the bearing element between the superstructure and th

Determine the head loss due to friction, Determine the Head Loss Due To Fri...

Determine the Head Loss Due To Friction Determine the head loss due to friction using the Darcy-Weisbach equation. The water is pumped at 3.0 gallons per minute, has a temperat

Calculate load distribution factor, Load Distribution Factor: The form...

Load Distribution Factor: The formula for deriving at the number of repetitions of the standard axle load during a design period of n years is: N =365 × A × VDF × F [(1 + r

Bedding of precast concrete paving units, Q. Sand layer vs. cement sand use...

Q. Sand layer vs. cement sand used as bedding of precast concrete paving units Cement sand is a mixture of sand and cement and it behaves as a cohesive mass once mixed. Usuall

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd