Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Lines, find the equation of the line with slope 4 and passing through the p...

find the equation of the line with slope 4 and passing through the point of intersection of the line x+6y-4=0 ad 3x-4y+2=10

Illustrate concept of filter design, Q. Illustrate Concept of filter design...

Q. Illustrate Concept of filter design? The material used for filter should satisfy the following normal criteria a. Filter material is more pervious than the base material

Civil Engineering, I. A horizontal 500 lb force acts at a point D of cranks...

I. A horizontal 500 lb force acts at a point D of crankshaft AB which is held in static equilibrium by a twisting couple and by reactions at A and B. Knowing that the bearings are

Reinforcement, Where we can provided overlap in columns

Where we can provided overlap in columns

Purposes of subdivision of tunnelling faces, Purposes of subdivision of tun...

Purposes of subdivision of tunnelling faces in Sprayed Concrete Linings (SCL) method In using sprayed concrete lining methods for lining a large tunnel in soft ground, tunnelli

Cost-volume-profit and break even analysis, Cost-Volume-Profit and Break Ev...

Cost-Volume-Profit and Break Even Analysis: Cost-volume-profit analysis helps us to learn the behaviour of cost and profit in response to varying level of business activity. I

Hybridisation, Why hybridisation never take in isolated atom

Why hybridisation never take in isolated atom

Pavements with Bitumen Emulsion, What is the rate of application of Prime c...

What is the rate of application of Prime coat over WBM

Show the settlement due to vibration, Q. Show the Settlement due to Vibrati...

Q. Show the Settlement due to Vibration? The foundation resting on cohesionless soil and subjected to vibrations will result in settlements of higher magnitude. In sandy soil

Estimate the activity durations - construction management, Estimate the Act...

Estimate the Activity Durations The total labor cost for emergency bridge rehabilitation on an interstate highway is $5,716,440.  The average crew-hour cost is $15,879 for this

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd