Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Define role of diver in underwater inspection of bridge, Define Role of Div...

Define Role of Diver in Underwater Inspection of Bridge? Diver's role is primarily to point out a potential scour problem. The diver can use one of the following equipment to m

State the term - calculation of deformation of concrete, State the term - c...

State the term - calculation of deformation of concrete For the calculation of deformation of concrete at some stage before the maximum shrinkage is reached, it may be assumed

Explain critical factor in design of shock transmission unit, Explain Criti...

Explain Critical factor in Design of shock transmission unit? (a) STUs are unidirectional devices for load transmission. If out of plane forces will be acting on the STU, the a

Physical evaluation of food grains, Q. Physical evaluation of food grains? ...

Q. Physical evaluation of food grains? Food grains are judged for quality by their physical, chemical and microbiological examination. The physical examination includes chec

Pulverized fly ash as cement replacement, Q. Pulverized fly ash as cement r...

Q. Pulverized fly ash as cement replacement? Pulverized fly ash is a type of pozzolans. It is analuminous or siliceous material that possesses no binding ability by itself. Whe

Explain is vadose zone - ground water, Explain is Vadose Zone - Ground wate...

Explain is Vadose Zone - Ground water In an unconfined aquifer, it is the area located above the water table and aquifer, where the soil and rock are not saturated with water.

Longitudinal steel – an enhancement of shear strength, Q. Longitudinal stee...

Q. Longitudinal steel – an enhancement of shear strength ? Furthermore to shear resistance provided by shear reinforcement, shear forces in a concrete section is also resisted

Time to remove formwork to cater for early thermal movement, Q. Time to rem...

Q. Time to remove formwork to cater for early thermal movement? Let's take a circular column as an illustration to explain effect of internal restraint to thick sections.  W

Fluid mechanics , i have three civil engineering fluid mechanics. 1 manomet...

i have three civil engineering fluid mechanics. 1 manometer problem 2 estimate the discharge for a channel 3 pipe system - direction of flow in line and what the value of flow in l

Design a 10 unit rapid sand filter system, Design a 10 unit rapid sand filt...

Design a 10 unit rapid sand filter system for a flow of 6.3 MGD with a filtration rate of 2 gpm/sq ft. and an L: W ratio of 1.3.   Design flow (Q) = 6.3 MGD = 6.3x106 gpd =

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd