Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Water control for sheet pile walls, Q. Water control for sheet pile walls? ...

Q. Water control for sheet pile walls? Ground water flow into excavations constructed by sheet pile walls must be minimized in order to save the cost of the provision of pumpin

Direction of approaching velocities of ships during berthing, Q. Direction ...

Q. Direction of approaching velocities of ships during berthing? One of the key effects of angle of approaching velocities of ships is its influence of energy to be absorbed by

Function of reinforced concrete infill, Function of reinforced concrete inf...

Function of reinforced concrete infill in marine piling system of steel tubular pile with reinforced concrete infill Reinforced concrete is designed to fill void space inside

Vibrocoring in marine ground investigation, Vibrocoring in marine ground in...

Vibrocoring in marine ground investigation If only shallow marine ground geotechnical information is essential for design purpose, vibrocoring is certainly a good choice for s

Explain the principles involved in successful stabilisation, Normal 0 ...

Normal 0 false false false EN-IN X-NONE X-NONE MicrosoftInternetExplorer4

Solid mensuration, the two sides of a triangle are 17cm and 28 cm long, and...

the two sides of a triangle are 17cm and 28 cm long, and the length of the median drawn to the third side is equal to 19.5. find the distance from an endpoint of this median to the

Distortion energy theory, Distortion energy theory: Let us now conside...

Distortion energy theory: Let us now consider the solid shown in Figure. (a)        By inspection we may see that the solid is safe according to principal stress theor

What is portal cranes, Q. What is Portal Cranes? The Portal crane is a ...

Q. What is Portal Cranes? The Portal crane is a hydraulically driven four wheeled machine and is meant for carrying sleepers or track panels. The power for running and working

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd