Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Levellng, introduction of levelling

introduction of levelling

Statics - rigid body of equilibrium, The ball of a trailer hitch is subject...

The ball of a trailer hitch is subjected to a force F. If the failure occurs when the moment of point F around point A reaches 11250 in lbs, determine the largest value F may have

Timber, structure of exogenous trees

structure of exogenous trees

Compression members, Compression Members: Compression members in steel...

Compression Members: Compression members in steel need special care in design. Steel possesses high strength in tension/compression; hence the sections are generally small com

Beam stress, what is the bending stress for a simply supported beam with th...

what is the bending stress for a simply supported beam with three equal concentrated loads that are equally spaced?

Water-bound macadam road construction for unpaved roads, how can I come up ...

how can I come up with the research on the water bound macadam road construction

Calculate the degree of saturation, A sample of clay taken from a natural s...

A sample of clay taken from a natural stratum was originated to be partially saturated and when tested in the laboratory gave the following results. Calculate the degree of saturat

Crushing strength test - tests on stones, Crushing Strength Test: F...

Crushing Strength Test: For conducting this test, specimen of size 40 × 40 × 40 mm is build from parent stone. Then finely the sides are dressed and placed in water for thr

Advantages of using top-down approach, Question What are major advantag...

Question What are major advantages of using top-down approach in basement construction? Answer The main advantages of top-down approach are listed below- (i) Stru

Grouting in segmental linings in tunnels, Q. Grouting in segmental linings ...

Q. Grouting in segmental linings in tunnels? Grouting is typically carried out under pressure in segmental linings at the time of tunnel construction due to the below reasons:

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd