Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Function of reinforced concrete infill, Function of reinforced concrete inf...

Function of reinforced concrete infill in marine piling system of steel tubular pile with reinforced concrete infill Reinforced concrete is designed to fill void space inside

Execution compression test for concrete, Question In execution compression...

Question In execution compression test for concrete , have to test cubes .Test cylinders be approved? Answer Essentially, results of compression test carried out by using cu

Retaioning walls, what are the uses of retaining wall?!

what are the uses of retaining wall?!

Segmentally lined and sprayed concrete linings tunnels, Q. Segmentally line...

Q. Segmentally lined and Sprayed Concrete Linings tunnels? The fundamental difference between segmentally lined tunnels and SCL tunnels is that the sprayed concrete in SCL tunn

Survey, how can I use reciprocal type of leveng method to level a ground, a...

how can I use reciprocal type of leveng method to level a ground, and a procedure

Define air chamber and surge tank, Q. Air chamber vs. surge tank in pressur...

Q. Air chamber vs. surge tank in pressurized pipelines? Air chambers and surge tanks are generally installed in water main to ease the stress on the system when valves or pumps

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd