Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Determine the limit state of serviceability, Determine the Limit State of S...

Determine the Limit State of Serviceability Cracking Cracking of concrete should not affect the appearance or durability of the structure. The criteria of limit state of cracki

What do you know about shallow piers, Q. What do you know about Shallow Pie...

Q. What do you know about Shallow Piers? In case of some of the existing bridges, piers may be shallow and grip may be found to be inadequate. Protection round piers is then re

Geo Technical Project, I have a geo technical Project that I need to be sol...

I have a geo technical Project that I need to be solved correctly and accurately within 15 hours exact, please. Steps and details must be included. Thanks a lot and let me know ASA

Hydrometer analysis - soil mechanics and foundations, Hydrometer Analysis -...

Hydrometer Analysis - soil mechanics and foundations Hydrometer Analysis used to obtain the grain size distribution of fine-grained soils (finer sands, silts and clays) smalle

How can a temporary diversion to laid, Q. How can a temporary diversion to ...

Q. How can a temporary diversion to laid a cross flowing river in case of disruption to rail traffic over a major bridge lasting over 6 months. Ans.- Temporary diversion

Major compensation of using hdpe as compared with cast iron, Question N...

Question Now, mainly flap valves are ended of HDPE. What is the major compensation of using HDPE as compared with cast iron? Answer (i) It has no response with sewage a

Determine the allowable pressue, The data profile as shown in Figure is obt...

The data profile as shown in Figure is obtained. A best average of N values gave N 10 = 21, column loads including dead and live loads ranged from 500 kN to 950 kN. Determine the

How do you maintain water pressure, If you have water pressure and wish to ...

If you have water pressure and wish to handle it, do not cause flow in the line, which will decrease pressure because of friction. To keep pressure up, decrease friction by increas

Difference between painting, Q- What is the difference between painting, p...

Q- What is the difference between painting, polishing and varnishing as for as woodwork is concerned? What are their advantages and disadvantage? Ans. - Painting - P

Distinguish among active and passive earth pressure, Distinguish among  'ac...

Distinguish among  'active' and 'passive' earth pressure. Describe clearly Rebhann's graphical construction method to evaluate the earth pressure on a retaining wall. What are t

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd