Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

What are the causes of settlement, Q. What are the causes of settlement? ...

Q. What are the causes of settlement? The various causes of settlement are: 1) increasing load on the surrounding soil deposit, 2) excavation, 3) lowering of water tab

Water absorption test for precast concrete pipes, Question What is the ...

Question What is the major purpose of carrying out water absorption test for precast concrete pipes? Answer Cement will mix with additional water than is compulsory t

Surveying, if bearing of AB is 190& that of CB is 260,the included angle AB...

if bearing of AB is 190& that of CB is 260,the included angle ABC is how?

Reasons of ground heaving during pipe-jacking, Reasons of ground heaving du...

Reasons of ground heaving during pipe-jacking It is commonly recognized that ground settlement is one of the significant concern in pipe jacking operation. Though engineer mus

Define chlorides - underwater inspection of bridge, Define Chlorides - unde...

Define Chlorides - underwater inspection of bridge? Chlorides do not attack plain concrete when present in the concentrations that normally exist in seawater, but may greatly a

Structure, what is the different between axial force and shear force?

what is the different between axial force and shear force?

Hydraulics, what is hydraulic grid line

what is hydraulic grid line

Design approach for the spacing of min-piles, Design approach for the spaci...

Design approach for the spacing of min-piles For close spacing of min-piles, it would provide substantial cost savings with reduction of pile cap size. Though close spacing of

Continuous beam reaction by equilibrium equation, Solve problem of continu...

Solve problem of continuous beam with equilibrium equation

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd