Concrete compaction in piling works, Civil Engineering

Assignment Help:

Question

What is the reason that vibrators not used in concrete compaction in piling works?


Answer

Concrete for piles must be a high-slump self-compacting mix that is capable of flowing between reinforcement cages with simplicity. As concrete is designed to be self-compacting, vibrators are not used for given that additional compaction. Furthermore, concrete in piles is compacted by power derived from free falling. Though, if vibrators are used, vibrated concrete can be compacted to sides of concrete casings and hinders lifting up of casings.

 


Related Discussions:- Concrete compaction in piling works

Survey, what is road survey ?

what is road survey ?

Civil engineering drawing, Explain step by step procedure involved in the a...

Explain step by step procedure involved in the analysis and design of balanced cantilever bridge.

Computer programming, write algorithm and flowchart that displays your name...

write algorithm and flowchart that displays your name 10 times

Bitumen tests, discussion of each bitumen test, its significance and import...

discussion of each bitumen test, its significance and importance in understanding and working with bitumen

Closed traverse, closed traverse maths problems at list 5 station

closed traverse maths problems at list 5 station

Main concern regarding design of pavements, Question If In case a road ...

Question If In case a road passes from side to side a reclaimed land and an existing land, what is key main concern regarding design of pavements? Answer For a breathin

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd