Concrete compaction in piling works, Civil Engineering

Assignment Help:

Question

What is the reason that vibrators not used in concrete compaction in piling works?


Answer

Concrete for piles must be a high-slump self-compacting mix that is capable of flowing between reinforcement cages with simplicity. As concrete is designed to be self-compacting, vibrators are not used for given that additional compaction. Furthermore, concrete in piles is compacted by power derived from free falling. Though, if vibrators are used, vibrated concrete can be compacted to sides of concrete casings and hinders lifting up of casings.

 


Related Discussions:- Concrete compaction in piling works

Determine the amount of excavated material, The footprint of a proposed off...

The footprint of a proposed office building is overlaid on the existing contours topographic map of a sloping site as shown in the figure. The structural bays which are 65-ft by 65

Euation solving, IFC= f(Ptr,Paccs+Peng) where ptr = 8, paacs =5 and peng =2...

IFC= f(Ptr,Paccs+Peng) where ptr = 8, paacs =5 and peng =2 In this eqn. what does comma means and how to solve this eqn.

Requirements of good building stones , Requirements of Good Building Stones...

Requirements of Good Building Stones          Here described requirements of good building stones: Strength: The stone should be capable to resist the load coming on

Rocks, Define rocks,types of rock,rock formations

Define rocks,types of rock,rock formations

Matrices, How to invert a matrix

How to invert a matrix

Installation of band drains, Question For drained reclamation, what wil...

Question For drained reclamation, what will significance of smear zone bring by installation of band drains ? Answer Throughout installation of band drains, smear zon

Is codes for building design, IS CODES FOR BUILDING DESIGN The codes w...

IS CODES FOR BUILDING DESIGN The codes which help engineers to design buildings are following: 1. IS 456-2000. For the design of plain and reinforced concrete it is code

Reinforced Concrete Design, design a 3-meter cantilever slab to carry a uni...

design a 3-meter cantilever slab to carry a uniform total dead load of 8.2KN/m^2 and a concentrated live load at the free end of 30 KN/m. f''c=28Mpa fy=420Mpa.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd