Determine the quantity of materials required per batch and probable output from a concrete mixing plant of 1200lts capacity. The design per 1000lts of mixed concrete is as follows :
5.6 bags of cement
923kg of course aggregate
715 kg of sand
195lts of water
Fixing time = 115 seconds

Related Discussions:- Concrete

Determine the hydraulic radius for rectangular open channel, Determine the ...

Determine the hydraulic radius R for a rectangular open channel with dimensions of 6 ft wide and 4 ft high (side walls) flowing at a depth of 3 ft. Solution: R = A/P Cross-s

Define electrical tool for underwater inspection of bridge, Define Electric...

Define Electrical tool for underwater inspection of bridge? Electrical equipment like Rebar Scanner for scanning of rebars; underwater sonic and ultrasonic equipment for observ

Main advantages of using rubber dams, Question In assortment of dams in...

Question In assortment of dams in drainage channels, what are the main advantages of using rubber dams instead of steel-gate dams ? Answer Key Advantages of rubber d

The regulations and specification that followed for compacti, what are The ...

what are The regulations and specification that followed for compaction works for earth dam in Oman.

List the significant engineering classification system, How do you distingu...

How do you distinguish among clay and silt in the field? State the purpose of identification and categorization of soils. List any three significant engineering classification syst

What is the station at point b, What is the station at Point B? SO...

What is the station at Point B? SOLUTION 3 Station at Point A = Sta 22+45  Station at Point B = (Sta 22+45) + 1028' = 2245'+1028' =3273'  = Sta 32+73

Epoxy-coated bars vs galvanized bars, Bonding performance to concrete: Epox...

Bonding performance to concrete: Epoxy-coated bars vs. galvanized bars  Based on the findings of CEB Bulletin 211 the bonding of galvanized bars to concrete is lower in early

Explain fluidized-bed incinerators, Explain Fluidized-Bed Incinerators ...

Explain Fluidized-Bed Incinerators sand is heated to 800C by oil or gas and blown around (fluidized) by a blower that sends air from bottom upward heated fluidized san

Estimate the activity durations - construction management, Estimate the Act...

Estimate the Activity Durations The total labor cost for emergency bridge rehabilitation on an interstate highway is $5,716,440.  The average crew-hour cost is $15,879 for this

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd