Concrete, Civil Engineering

Assignment Help:
Determine the quantity of materials required per batch and probable output from a concrete mixing plant of 1200lts capacity. The design per 1000lts of mixed concrete is as follows :
5.6 bags of cement
923kg of course aggregate
715 kg of sand
195lts of water
Fixing time = 115 seconds

Related Discussions:- Concrete

Impact of possible energy, a) Take into consideration the boiler efficiency...

a) Take into consideration the boiler efficiency, and verify the cost of heating the building, during the heating season, using present oil and gas prices.  b) Investigate the i

Truss, modified pratt truss with detailing in 3D

modified pratt truss with detailing in 3D

Explain the typical wastewater characteristics, Explain the Typical Wastewa...

Explain the Typical Wastewater Characteristics? Total Suspended Solids = 100 - 350 mg/L (200 mg/l is the typical value)    BOD 5 = 100-300 mg/L (200 mg/L is the typical val

State the term- friction in tendon, State the term- friction in tendon ...

State the term- friction in tendon Considerable frictional loss takes place due to friction between the tendon and the material surrounding it, namely the concrete or the sheat

Shear force, what is shear failure and shear force please explian?

what is shear failure and shear force please explian?

Question, The state of stress at a point is given by the stress components ...

The state of stress at a point is given by the stress components sx = 70 MPa, sy = 10 MPa and ?xy = - 40 MPa. Using Mohr''s circle, find (i) Principal stresses, and (ii) Principal

Key reasons for conducting pull-out tests, Question What are key reason...

Question What are key reasons for conducting pull-out tests for soil nails ? Answer There are largely four bases for this examination- (i) To verify and verify bo

Deflection of beam, a simply supported beam with concentric load

a simply supported beam with concentric load

Stop dead restriction, With a clear sketch indicate the system of protectio...

With a clear sketch indicate the system of protection of line for works of short duration where ‘ Stop dead restriction' need to be observed on a single line section on a BG track.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd