Computing hedge ratio: the modified duration method, Financial Management

Assignment Help:

Let us consider a situation wherein a position in an interest rate dependent asset such as a bond portfolio or a money market security is hedged by using an interest rate futures contract.

Let us assume that the change in the yield ?y, will be same for all maturities, i.e., only parallel shifts in the yield curve can occur. From the modified duration definition, we have,

         1187_hedge ratio.png

We can also say that to a reasonable approximation, it is also true that,

         1584_hedge ratio1.png

In the first equation, S0 represents value (decimal form) of the asset that is being hedged and MDrepresents modified duration of the asset. In the second equation, F0,T represents quoted price in decimals for the interest rate futures contract and MDrepresents modified duration of the asset underlying the futures contract (i.e., modified  duration of the cheapest to deliver bond).

As ?y is assumed to be the same for all maturities, we have ρΔSΔF = 1.  By combining first and second equation, we get,

         10_hedge ratio2.png

This can be written as,

         1520_hedge ratio3.png

Thus, we get,  

         1239_hedge ratio4.png

Finally, the optimal Hedge Ratio (HR) is used for hedging 

         1593_hedge ratio5.png

By using this equation we can equate the duration of the combined position equal to zero.

However, the hedge obtained using the above equation is not perfect because of following reasons:

  • It assumes that ?y is same for all yields. But, in reality short-term yields are generally more volatile and also have low correlation with long-term yields. Consequently, the performance of the hedge will not be appreciable, particularly when there is large variation between MDS and MDF.

  • It does not consider convexity. In case the convexity of the asset underlying the futures contract is remarkably different from the convexity of the asset being hedged, and at the same time if there is large difference in interest rates, then the performance hedge will be worse than is expected.

  • An assumption with regard to cheapest-to-deliver bond is essential to compute MDF. If the cheapest-to-deliver bond changes, then MDF   as well as optimal number of contracts also changes.

Now, as we know the hedge ratio, let us see the number of futures contracts to be purchased. We have earlier studied that the number of futures contracts required is given as

         651_hedge ratio6.png

In the above equation, NS indicates the number of units of spot asset to be hedged and k indicates the contract size.

We can estimate hedge ratio by using regression also. It can be interpreted as follows:

         1552_hedge ratio7.png

We have earlier studied that,  210_hedge ratio8.png   Here  2120_hedge ratio9.png   represents conversion factor of the cheapest to deliver bond at time 0 and SCTD,0  represents its price. If we replace F0,T in the above formula, we get,

         569_hedge ratio10.png

This can be interpreted as follows:

1461_hedge ratio11.png


Related Discussions:- Computing hedge ratio: the modified duration method

Answer, The standard cost of chemical mixture ~ PQ’ is as follows: 40% of m...

The standard cost of chemical mixture ~ PQ’ is as follows: 40% of material P @ Rs. 400 per kg. 60% of material Q @ Rs. 600 per kg. A standard loss of 10% is normally anticipated in

Show regression analysis to estimate the default probability, 1. The standa...

1. The standard approach here is to calculate some conventional ratios. These ratios can afterwards be used along with regression analysis to estimate the default probability.

Determine the purchasing in leaminger plc, b) Each $1 of outlay prior to 3...

b) Each $1 of outlay prior to 31 December 2003 would mean a loss in NPV on the alternative project of $0·20. There is so an opportunity cost of using funds in 2002. Purchasing

None, Reacher Technology has consulted with investment bankers and determin...

Reacher Technology has consulted with investment bankers and determined the intere Reacher Technology has consulted with investment bankers and determined the interest rate it woul

What is redeemable debt, What is Redeemable debt Company will have to...

What is Redeemable debt Company will have to re-pay the debt at redemption date or between the two redemption dates (i.e. 20X5/20X9, means debt can be redeemed any time betwe

Definition of financial leverage, Q. Definition of financial leverage? ...

Q. Definition of financial leverage? One of the goals of planning an appropriate capital structure is to maximize the return on equity shareholders fund or else maximize the ea

Abnormal earnings valuation model, Abnormal Earnings Valuation Model Ab...

Abnormal Earnings Valuation Model Abnormal Earnings Valuation Model is a method to analyse the value of the firm. The value of the firm can be the sum of three components - the

Interpretations of long term solvency or liquidity ratio''s, Long Term Solv...

Long Term Solvency or Liquidity Ratio's   DE:          The Debt Equity ratio exhibits the relation that exists between debt and proprietor's fund and is considered a very im

Arbitrage-free valuation approach, The main drawback of the tradition...

The main drawback of the tradition approach of valuation is that it discounts every cash flow using the same discount rate. For example, let us take 5-year (7.00 per ce

Buying and selling securities, Buying and Selling Securities One of the k...

Buying and Selling Securities One of the key features that may occur while investing in financial markets is that sometimes investors overlook the essential factors they should c

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd