Computer the schedule variance schedule performance index, Operation Management

Assignment Help:

A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 63% complete. The planners were only expecting to be 52% through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,422,000 and it was done for only $1,302,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,502,000 but was actually done for $9,002,000. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,502,000. To date they have spent $5,002,000 on the superstructure.

Calculate the schedule variance, schedule performance index, and cost performance index for the project to date. (Round your "performance index" values to 3 decimal places.)


Related Discussions:- Computer the schedule variance schedule performance index

Explain brand equity, What is your understanding of the term: Brand Equity?...

What is your understanding of the term: Brand Equity? How do marketers develop brand equity for their products/services relative to competition? Provide an example of a brand/produ

Distribution among between affect international businesses, How do differen...

How do differences in income levels and income distribution among nations affect international businesses?

What are strategies for creating an open environment, 1 Develop an ld score...

1 Develop an ld score for the current layout. What problems can you identify with the current layout? 2. Use trial and error to come up with a better layout that lowers the ld s

Describe what is the average time a car is in the system, Automobiles arriv...

Automobiles arrive at the drive-through window at the downtown Urbana, Illinois, post office at the rate of 4 every 10 minutes. The average service time is 2 minutes. The Poisson d

Design of work systems, A worker machine operation was found to involve 3.5...

A worker machine operation was found to involve 3.5 minutes of machine time per cycle in the course of 40 cycles of stopwatch study. The workers time averaged 2.3 minutes per cycle

Define disputes and the contractual means used for resolving, What is the c...

What is the cause of disputes and the contractual means used for resolving them?

Computed marginal profit for various costing profiles, An HMO requests your...

An HMO requests your hospital services for its obstetrics division. It offers to pay your hospital $2,000 for a vaginal delivery without complications (DRG 373). You look at the St

Explain the common grounds for discharge and the procedural, Describe the c...

Describe the common grounds for discharge and the procedural requirements that are outlined in many collective bargaining agreements. State why the following are important when the

Explain terminals and arrive at a message concentrator, Messages are transm...

Messages are transmitted from low speed terminals and arrive at a message concentrator at a Poisson rate of 600/hr. They are held in a buffer until a hi-speed trunk line is free to

What must a short-term or long-term consequence make, What should a short-t...

What should a short-term or long-term consequence make a difference in resolving an ethical dilemma?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd