Compute the shape yield percentage, Operation Management

Assignment Help:

You punch multiple parts from a sheet of Aluminium. The sheet is a 1728 square-inches rectangle and you get 18 parts that are 70 square-inches each. The machine is old so you include a 5% scrap allowance for damaged parts. Calculate the shape yield percentage


Related Discussions:- Compute the shape yield percentage

Compute the answers for the missing cells in the table, Process Analytics C...

Process Analytics Case let 1 Overview respond to this case let, which is based in a health care setting.. Preparation Read through the following case let. You are an operations man

Define challenges has the european union consortium faces, Describe what ch...

Describe what challenges has the European Union Consortium faced in the last 2-3 years

Global operations management, what are the key issues to be considered when...

what are the key issues to be considered when managing global management operations

Explain what are the risks and opportunities of the strategy, What are the ...

What are the risks and opportunities of the strategies followed by Pepsi? of Coca Cola?

Explain six sigma principles to health care organizations, Type two savings...

Type two savings are the least likely to occur when applying Six Sigma principles to health care organizations

Explain drink equally appealing to men, Do you think Diet Coke could have b...

Do you think Diet Coke could have been repositioned to change consumers' perceptions of it enough to be considered a drink equally appealing to men? Why or why not?

Factors for best path for data among two points on a network, Name three fa...

Name three factors that a router must consider when determining the best path for data between two points on a network?

Explain statistical process control, Which one of the following is NOT one ...

Which one of the following is NOT one of the basic elements of the strategic management process A. Strategy formulation B. Strategy implementation C. Statistical process control D.

Describe international compensation, Existing salary for managers is 45,000...

Existing salary for managers is 45,000 euros (58,567 us dollars) plus bonuses. Average salary for managers in range is 60,000 euros (78,090), no bonuses. Recommendations must inclu

Explain what is the basic problem causing this conflict, You are the plant ...

You are the plant manager at Acme Plastics. You are running two shifts, a day shift and an evening shift. Before the day shift leaves each day, the workers must get an adequate sup

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd