Compute the schedule variance and cost performance index, Operation Management

Assignment Help:

A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 63% complete. The planners were only expecting to be 52% through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,422,000 and it was done for only $1,302,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,502,000 but was actually done for $9,002,000. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,502,000. To date they have spent $5,002,000 on the superstructure.

Calculate the schedule variance, schedule performance index, and cost performance index for the project to date. (Round your "performance index" values to 3 decimal places.)


Related Discussions:- Compute the schedule variance and cost performance index

OPERATION REASERCH.., #question.six operators are to be assinged with 5 job...

#question.six operators are to be assinged with 5 jobs with cost of assingment in rs given in the matrix below 1 2 3 4 5 62526 25877 78698 62345 93897 47468

Explain how many crates will it need to plan, A bottling facility with an e...

A bottling facility with an effective capacity of 40,000 crates per day operates with an efficiency of 85%. How many crates will it need to plan for bottling on a day that requires

Factors affecting productivity improvement, Factors Affecting Productivity ...

Factors Affecting Productivity Improvement  As has already been stressed, productivity improvement is not simply concerned with finding ways of making people work harder, nor

Explain items selected from a population is called, A subset of items selec...

A subset of items selected from a population is called which of the following? Sample Statistic Census Parameter

Explain what kind of data would be considered a nod, What kind of data woul...

What kind of data would be considered a NOD?/ REFERENCE WHERE THE INFO CAME FROM

Explain allocated cells a balanced transportation model, The number of allo...

The number of allocated cells a balanced transportation model with 3 sources and 3 destinations should have in order NOT to be degenerate is

What are policy and operative decisions, What are policy and operative deci...

What are policy and operative decisions? Policy decisions are very significant, they are taken by top management, and they have a long-term impact and mostly relate to fundamen

Explain optimization technique and a heuristic to solve, What is the differ...

What is the difference between using an exact optimization technique and a heuristic to solve a problem?

Explain supply chain is inappropriate for services, Explain why the goods a...

Explain why the goods analogy of a supply chain is inappropriate for services

Design methods, Computer-Aided Design is one of the techniques used by Rega...

Computer-Aided Design is one of the techniques used by Regal Marine in the manufacturing of boats. With the aid of examples, critically discuss FIVE (5) techniques that are import

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd