A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 63% complete. The planners were only expecting to be 52% through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,422,000 and it was done for only $1,302,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,502,000 but was actually done for $9,002,000. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,502,000. To date they have spent $5,002,000 on the superstructure.
Calculate the schedule variance, schedule performance index, and cost performance index for the project to date. (Round your "performance index" values to 3 decimal places.)
Why are unions exploring new collaboration solutions in the face of economic/work adversity?
• Explain why some states do and other states don't have a public-sector bargaining law or laws that cover some public employees but not others. • From the second e-Activity, co
As a library or Internet assignment, find the US productivity rate (increase) last year for the (a) national economy, (b) manufacturing sector, and (c) service sector. Where can yo
Are the following objective functions for an LP model equivalent? That is, if they are both used, one at a time, to solve a problem with exactly the same constraints, will the opti
can you please give me a simple example of markov analysis
What do you understand by “line balancing
Owner Kay Fay is considering franchising her Oriental Express restaurant concept. She believes people will pay $5.50 for a large bowl of noodles. Variable costs are $2.75 a bowl. F
Limitations of E-Business 1. Problems relating to the security of the data 2. Limitations of bandwidth (speed of data transmission) 3. Standardisation o
In terms of developing the project plan, identify which, if any, of the project steps are more integral to the project plan than any others. Support your response
This assignment requires you to look in some detail at one quality issue arising in your organisation. Some of the exercises in Units 4 and 5 have already suggested that you consid
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd