A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 63% complete. The planners were only expecting to be 52% through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,422,000 and it was done for only $1,302,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,502,000 but was actually done for $9,002,000. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,502,000. To date they have spent $5,002,000 on the superstructure.
Calculate the schedule variance, schedule performance index, and cost performance index for the project to date. (Round your "performance index" values to 3 decimal places.)
Dispatching - Production Control The function of routing and scheduling as discussed above are paperwork only. No actual production has yet been started. Dispatching is the part
1. What do you see as the most interesting part of HR as a career field? 2. What do you think are the roles and function of an HR professional?
Question: (a) (i) What are the assumptions to be respected while deriving the Economic Order Quantity formula. (ii) Describe the several components of inventory holding c
Describe the four options highlighted in the case study in terms of their feasibility, acceptability and vulnerability.
Describe how you think contracting fits into the acquisition program. Feel free to use some of your own experiences and examples
An electrical contractor's records during the last 5 weeks indicate the number of actual job requests. Predict the number of requests for week 6 using each of the below methods:
What are the essential components of a well-balanced marketing plan?
How the job of industrial manager becomes more difficult? However, the job of industrial Manager becomes still more difficult because of: (i) Change in technology; (ii) C
Analyze the environment, processes, and procedures at your work or school to determine which aspects can be controlled and which cannot be controlled. Explain your rationale. •From
A manufacturing company preparing to build a plant is considering three potential locations for it.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd