Compute the schedule variance and cost performance index, Operation Management

Assignment Help:

A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 63% complete. The planners were only expecting to be 52% through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,422,000 and it was done for only $1,302,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,502,000 but was actually done for $9,002,000. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,502,000. To date they have spent $5,002,000 on the superstructure.

Calculate the schedule variance, schedule performance index, and cost performance index for the project to date. (Round your "performance index" values to 3 decimal places.)


Related Discussions:- Compute the schedule variance and cost performance index

Explain project management profession, Microsoft Project, identify the reso...

Microsoft Project, identify the resource that caught your interest and estimate its usefulness to the project management profession.

Centre of gravity method, Hi, I am looking to find any potential benefits o...

Hi, I am looking to find any potential benefits of the centre of gravity locational theory, in addition to this, would like to know of any potential drawbacks that the theory entai

Effect on costs and employer, Effect on Costs and Employer: Accidents  are...

Effect on Costs and Employer: Accidents  are harmful when  we take into account  the business  of the  concern.  It adds to the  costs of production  directly  as well  as  indire

Capacity utilisation, Benefits of outsourcing and how to improve capacity u...

Benefits of outsourcing and how to improve capacity using ratio rastionalisation and sub contracting

Explain e-activity evaluate the lessons, From the e-Activity, evaluate the ...

From the e-Activity, evaluate the lessons learned in this chapter to determine which single lesson would be most beneficial to the company you researched. Provide specific examples

Explain where will the bottleneck in the system be, The process for renewin...

The process for renewing a driver's license at the Archer County Courthouse is as follows. First, the clerk fills out the application; then the clerk takes the driver's picture; an

How to find the optimal order quantity, Must use Excel for solution Zip ...

Must use Excel for solution Zip Games purchases blank 3.5-inch disks onto which it copies its software for sale through its mail order operation. A disk costs Zip $.20. Processi

What are the advantages of the demand management strategies, What are the a...

What are the advantages of the demand management strategies? The advantages of the demand management strategies are as illustrated here: a. While ‘off peak’ quite than contr

Explain control board meeting to approve a scope change, Which of the follo...

Which of the following is normally not addressed in a change control board meeting to approve a scope change? Answer Cost of the change Which functional unit will perform

Describe how many bags per run are optimal, A chemical firm produces sodium...

A chemical firm produces sodium bisulfate in 100-pound bags. Demand for this product is 20 tons per day. The capacity for producing the product is 50 tons per day. Setup costs $100

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd