Compute the experience curve, Business Economics

Assignment Help:

Compute the experience curve:

Chuck Raverty, General Manager of Carey Builders, a Baltimoreconstruction company is considering bidding for a construction contract on the new Corey Business School (CBS) building at Hopekeen State University.  Construction is scheduled to start in late summer 2013.  Chuck expects to compete for this contract with Wharton Construction, an out-of-state rival.  There is also a chance that the Smith Corporation, a construction company based in Silver Springs, MD will bid on the contract.

Carey has completed four such university building projects so far and is working currently on a similar project that will be completed before the CBS project starts in 2013.  Thus, Carey will have the experience of having completed five projects when it starts the CBS project, if it wins the contract. The latest completed project (i.e., their fourth) cost Carey a total of $34.3 million, of which $25.8 million was raw material cost.  Also, an internal cost analysis has shown that Carey's second project (completed in 2002) cost a total of $30.0 million, of which the raw material cost was $20.0 million.  Since all the projects that Carey has worked on are structurally similar, Chuck expects this cost dynamic to hold for his future value-added costs and believes that this past cost information may be useful for forecasting purposes.

Hutt and Speh (HS) Corporation, a leading building supplies company has informally agreed to supply all the raw material for the CBS project for $43.9 million. Chuck knows that the costs of gearing up to submit a bid on the CU project would involve incrementalfixed costs of $75,000, nonrefundable contract guarantee fees to HS Corporation amounting to 1% of the contracted raw material cost, and setup costs equal to 2% of the project's value-added costs. Thsee "bid development costs" are not recoverable (and must be written off) if Chuck fails to win the bid.  Hence, Chuck wants to include these costs in figuring his bid.

Phil Ferrari, Chuck's former graduate school buddy is the Senior Contract Manager for Hopekeen University and reminded Chuck that because of priorities favoring in-state awards, Carey has an advantage if it bids on the CBS building. Chuck thought this was encouraging.  He assesses that if bidding only against Wharton, Carey's probabilities of winning the contract at bid prices involving specific markup levels on forecasted total costs are (no intermediate markups, e.g., 7% or 18%, are allowed):

            Markup:                                                            0%       5%       10%      15%      20%      25%

            Probability of contract award to Carey                  1.0        0.8        0.7        0.4        0.3        0.0

A.  Compute the experience curve implied in Carey's past project costs.

B.  Compute what Carey should forecast for value-added costs for the CBS project.

C.Compute Carey' total ($) cost for the CBS project and (for each bid markup level) the associated gross ($) profit margin if it wins the CBS contract.  (Assume that HS Corporation will meet its raw material price commitment)

D. What $ amount should Carey bid for the project (assume Chuckmaximizes expected profit)?

E. Chuck now learns that Smith Builders is also certain to bid on the LSB project.  Carey will then lose the in-state advantage and Chuck's revised estimates of the probability that Carey will win theCBS contract are:

 

            Markup:                                                            0%       5%       10%      15%      20%

            Probability of contract award to Carey                  1.0        0.7        0.4        0.3        0.0

What should Carey bid for the CBS project given this information (recall that Chuck maximizes expected profit)?

F.  How will your answer change if Chuck felt that there was only a 50% probability that South State would bid on the project?  Show your computations and briefly explain your answer.

G.  Chuck wonders if maximizing expected profits is a good approach to making these decisions and seeks your advice on whether to bid higher or lower than the expected profit maximizing bid.  What advice would you give him?

H.  Chucklearns that Hopekeen Statepalns on building an executive education facility in 2015 and that the CBS contract winner will have an inside track in the bidding.  Should this information affect his bid on the CBS project?  Why or why not?


Related Discussions:- Compute the experience curve

Research project, 1. Formulate and record possible research project outline...

1. Formulate and record possible research project outline specifications (you are expected to explain your choice of research question, the aims and objectives of the research, and

Curse embodied, a)      What is the curse embodied in the standard producti...

a)      What is the curse embodied in the standard production function? How does technological advance permit  an economy to avoid this curse? b )    In what significant way doe

Is low savings a problem, Is low savings a problem? Countries along wi...

Is low savings a problem? Countries along with low savings are caught into the vicious circle of poverty: there low savings, implies low investment low productivity therefore

Survey of economics, in the banking systems, when clearing checks, the diff...

in the banking systems, when clearing checks, the difference between the Federal Reserve''s credits and debits is the

Commercial banking, advantages and disadvantages of commercial banking

advantages and disadvantages of commercial banking

Regulation and deregulation, how does the buying and selling of stock fit t...

how does the buying and selling of stock fit the model for perfect competition?

Wheeled coach, What is an alternative process strategy to the assembly line...

What is an alternative process strategy to the assembly line that Wheeled Coach currently uses?

Sports Economics , I am given that demand formula P=150-3Q, am told I only ...

I am given that demand formula P=150-3Q, am told I only have 40 tickets to sell and that the MC=0 and I am suppose to figured out how many tickets to sell to maximize total welfare

What is sampling, Sampling and tests of significance are very important too...

Sampling and tests of significance are very important tools in business economics. In fact one cannot do any meaningful marketing research without the requisite knowledge of sampli

Production possiblities curve, 1. Imagine that two countries, Richland and ...

1. Imagine that two countries, Richland and Poorland can produce just two goods, computers and coal. Assume that for a given amount of land and capital, the output of these two pro

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd