Compute the experience curve, Business Economics

Assignment Help:

Compute the experience curve:

Chuck Raverty, General Manager of Carey Builders, a Baltimoreconstruction company is considering bidding for a construction contract on the new Corey Business School (CBS) building at Hopekeen State University.  Construction is scheduled to start in late summer 2013.  Chuck expects to compete for this contract with Wharton Construction, an out-of-state rival.  There is also a chance that the Smith Corporation, a construction company based in Silver Springs, MD will bid on the contract.

Carey has completed four such university building projects so far and is working currently on a similar project that will be completed before the CBS project starts in 2013.  Thus, Carey will have the experience of having completed five projects when it starts the CBS project, if it wins the contract. The latest completed project (i.e., their fourth) cost Carey a total of $34.3 million, of which $25.8 million was raw material cost.  Also, an internal cost analysis has shown that Carey's second project (completed in 2002) cost a total of $30.0 million, of which the raw material cost was $20.0 million.  Since all the projects that Carey has worked on are structurally similar, Chuck expects this cost dynamic to hold for his future value-added costs and believes that this past cost information may be useful for forecasting purposes.

Hutt and Speh (HS) Corporation, a leading building supplies company has informally agreed to supply all the raw material for the CBS project for $43.9 million. Chuck knows that the costs of gearing up to submit a bid on the CU project would involve incrementalfixed costs of $75,000, nonrefundable contract guarantee fees to HS Corporation amounting to 1% of the contracted raw material cost, and setup costs equal to 2% of the project's value-added costs. Thsee "bid development costs" are not recoverable (and must be written off) if Chuck fails to win the bid.  Hence, Chuck wants to include these costs in figuring his bid.

Phil Ferrari, Chuck's former graduate school buddy is the Senior Contract Manager for Hopekeen University and reminded Chuck that because of priorities favoring in-state awards, Carey has an advantage if it bids on the CBS building. Chuck thought this was encouraging.  He assesses that if bidding only against Wharton, Carey's probabilities of winning the contract at bid prices involving specific markup levels on forecasted total costs are (no intermediate markups, e.g., 7% or 18%, are allowed):

            Markup:                                                            0%       5%       10%      15%      20%      25%

            Probability of contract award to Carey                  1.0        0.8        0.7        0.4        0.3        0.0

A.  Compute the experience curve implied in Carey's past project costs.

B.  Compute what Carey should forecast for value-added costs for the CBS project.

C.Compute Carey' total ($) cost for the CBS project and (for each bid markup level) the associated gross ($) profit margin if it wins the CBS contract.  (Assume that HS Corporation will meet its raw material price commitment)

D. What $ amount should Carey bid for the project (assume Chuckmaximizes expected profit)?

E. Chuck now learns that Smith Builders is also certain to bid on the LSB project.  Carey will then lose the in-state advantage and Chuck's revised estimates of the probability that Carey will win theCBS contract are:

 

            Markup:                                                            0%       5%       10%      15%      20%

            Probability of contract award to Carey                  1.0        0.7        0.4        0.3        0.0

What should Carey bid for the CBS project given this information (recall that Chuck maximizes expected profit)?

F.  How will your answer change if Chuck felt that there was only a 50% probability that South State would bid on the project?  Show your computations and briefly explain your answer.

G.  Chuck wonders if maximizing expected profits is a good approach to making these decisions and seeks your advice on whether to bid higher or lower than the expected profit maximizing bid.  What advice would you give him?

H.  Chucklearns that Hopekeen Statepalns on building an executive education facility in 2015 and that the CBS contract winner will have an inside track in the bidding.  Should this information affect his bid on the CBS project?  Why or why not?


Related Discussions:- Compute the experience curve

Define the planned or command economy system, Define the planned or command...

Define the planned or command economy system. Planned or command economy: Resources are owned through the state. The state assigns resources, and sets production goals a

Bubble burst, Situation: Only a few astute operatives say the crash in rea...

Situation: Only a few astute operatives say the crash in real estate prices as the USA entered the summer of 2007.  You were one of the few that appreciated that real estate price

Explain clearly what inflation is, QUESTION (a) Explain clearly what in...

QUESTION (a) Explain clearly what inflation is and elaborate on its main causes. (b) "There is a trade-off between inflation and unemployment" Do you agree with this stateme

Managerial economics, #question the importance of managerial economics..

#question the importance of managerial economics..

Acknowledge a union through a card check, 1) True or False: Elections under...

1) True or False: Elections under the NLRA were intended to replace the need for striking in order to have a union recognized. 2) True or False: Companies can voluntarily acknow

Needs and wants, Nathan is a successful public relations (PR) consultant, t...

Nathan is a successful public relations (PR) consultant, thanks to an outgoing personality and sharp intelligence. At 35, he is near the height of his earnings potential, at around

What are the national figures, What are the national figures? Nationa...

What are the national figures? National income figures: • Do not measure social, non-economic, quality of life indicators as like life expectancy that access to educatio

Supply, causes of exceptional supply curve

causes of exceptional supply curve

Control the circulation of money in the economy, QUESTION (a) State whe...

QUESTION (a) State whether the following statements are TRUE or FALSE. Clearly explain your answer. (i)The Keynes liquidity Preference theory stipulates that money demand is

Help, Ask quethe monthly revenue of a certain comany is given by R=820p-7^2...

Ask quethe monthly revenue of a certain comany is given by R=820p-7^2p,where p is the price in dollars of the product the company manufacturers. at what price will the revenue be $

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd