Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Layout planning - facility layout, Layout Planning - Facility Layout L...

Layout Planning - Facility Layout Layout planning occurs at three levels of detail:  1. Layout of departments on the site For a public house, as an exampl

Explain how many crates will it need to plan, A bottling facility with an e...

A bottling facility with an effective capacity of 40,000 crates per day operates with an efficiency of 85%. How many crates will it need to plan for bottling on a day that requires

Explain lean six sigma different than other performance, A key factor that...

A key factor that makes Lean Six Sigma different than other performance improvement models is that it free discusses costs and cost recovery with varying stakeholders.

Define what kind of industries does a localization strategy, What kind of i...

What kind of industries does a localization strategy makes sense? Why? When does a global standardization strategy make most sense? Why?

Decision making approaches, Decision Making Approaches General Framewo...

Decision Making Approaches General Framework Outline the meaning of Rationality, Bounded Rationality and Intuitive approaches to decision making. Individual Components

Steps in layout planning and design, Steps in Layout Planning and Design ...

Steps in Layout Planning and Design For a given product at a stated volume of production a process most appropriate must be determined. The process that is determined like any

Explain benefit of taking the money versus losing control, Your new small b...

Your new small business has really grown, but now it needs a substantial infusion of capital. A venture capitalist firm has agreed to invest the money you need. In return, the vent

Value driven approach, value driven approach to production managemeent

value driven approach to production managemeent

Solve the problem requires an excel solution, The problem requires an excel...

The problem requires an excel solution and an algebraic solution with variables: During the month of July, Pittsburgh resident Bill Fly must make four round trip flights between Pi

Describe difference between two population means, If a manager wishes to de...

If a manager wishes to develop a confidence interval estimate for estimating the difference between two population means, an increase in the size of the samples used will result in

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd