Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Explain the service organization worry about world class, Why should a serv...

Why should a service organization worry about being world class if it does not compete outside its own national border? What impact does the Internet have on this?

Compute the npv, Expando, Inc., is considering the possibility of building ...

Expando, Inc., is considering the possibility of building an additional factory that would produce a new addition to their product line. The company is currently considering two op

Compute number of workers needed for each department, Calculate number of w...

Calculate number of workers needed for each department to produce 2000 units per day and complete the table below to assist you in answering questions e.)è?j.). (e) What is the tot

Hard, Ask quesThe Delicious Apple Company has orchards in Red City, Golden,...

Ask quesThe Delicious Apple Company has orchards in Red City, Golden, and Macville Estimated amounts of apples to be available from the three orchards are the following: Red City

Explain competitive strategy relate to value chain structure, How does comp...

How does competitive strategy relate to value chain structure?

Explain if a wireless signal collides with an object, If a wireless signal ...

If a wireless signal collides with an object whose dimensions are much larger than the signal's wavelength, what is the signal most likely to do? a. reflect b. refract c.

Explain the nature of barriers to entry, 1).Under what environmental condit...

1).Under what environmental conditions are price wars most likely to occur in the industry? What are the implications of price wars for a company? How should a company try to deal

Record of operations in an organisation, Record of operations in an organis...

Record of operations in an organisation If the operation to be studied already exists it is important to record its details by direct observation. To help in this, many tools

Explain control board meeting to approve a scope change, Which of the follo...

Which of the following is normally not addressed in a change control board meeting to approve a scope change? Answer Cost of the change Which functional unit will perform

Explain if overachievement is acceptable, If overachievement is acceptable,...

If overachievement is acceptable, the appropriate di+ variable can be dropped from the objective function.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd