Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Explain the forecasted demand for fudge, The forecasted demand for fudge fo...

The forecasted demand for fudge for the next four months is 140, 160, 90 and 70 pounds. A) What is the recommended production rate if a level strategy is adopted with no back order

Case study, Bloomsday Outfitters produces T-shirts for road races. They nee...

Bloomsday Outfitters produces T-shirts for road races. They need to acquire some new stamping machines to produce 30,000 good T-shirts per month. Their plant operates 200 hours per

Describe wholesale pricing, What provision of the Telecommunications Act of...

What provision of the Telecommunications Act of 1996 prohibits ILECs from requiring customers to dial an extra digit when calling someone who subscribes to a competitor's local pho

Operation Management and POM QM sums , The assignment consists of 3 exercis...

The assignment consists of 3 exercises, and the marks for each question varies. Printouts provided with the prose solutions and explanation of the POM-QM solutions must be original

Describe potential for increased profit, Which of the following is a criter...

Which of the following is a criterion used for selecting a target segment? Potential for increased profit Similarity of needs of potential buyers within a segment Differen

What are the advantages of a permanent arbitrator, What are the differences...

What are the differences between the FMCS and the AAA in their methods of selection of arbitrators? What are the advantages of why some employers and unions contract the use of a p

Valuate the production quantity, Using the data, suppose the manufacturer h...

Using the data, suppose the manufacturer has an inflated demand forecast as follows: Quantity Probability 2,200 5% 2,300 6% 2,400 10% 2,500 17% 2,600 30% 2,700

Explain what is customer relationship management, What is Customer Relation...

What is Customer Relationship Management - CRM? Describe the four-step framework for one-to-one marketing that can be adapted to CRM marketing? Provide at least one or two examples

Explain what is the productivity, 1. A manufacturing company has a small pr...

1. A manufacturing company has a small production line dedicated to the production of a particular product. The line has four stations in serial. Inputs arrive at station 1 and the

Discuss factors that can rise complexity of the information, Identify and d...

Identify and discuss factors that can increase the size and complexity of the information system structure (beyond those discussed in the text). •Make at least three recommendation

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd