Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Impact of multinational enterprises to their firm boundaries, Multinational...

Multinational enterprises (MNEs) have an impact far beyond their firm boundaries. Assume you are working for a small firm that supplies a product or service to an MNE. How might yo

Explain self-managed teams perform entire jobs, Self-managed teams perform ...

Self-managed teams perform entire jobs, rather than specialized assembly-line work.

Define conditions which exist globally that are contributing, Please answer...

Please answer both questions fully to have points awarded, Thanks! Decreasing the Incidence of CVD" Please respond to the following: 1. Propose the steps that might be taken

Explain what type of culture is desired, What type of culture is desired by...

What type of culture is desired by Mr. Good¬ night to meet his goals? Discuss.

Explain improving productivity, Explain Improving Productivity. Improv...

Explain Improving Productivity. Improving Productivity: The production essence is creation of goods, may be by the transformation of raw materials or through assembling vario

Explain challenges in leading a multi-generational workforce, Challenges in...

Challenges in leading a multi-generational and/or multi-cultural workforces: Need a complete summary for the listed assignment, references. Please at least one page of information

Playground explained in this case study, What does the concept of interacti...

What does the concept of interactive design mean for a service such as the adventure playground described in this case study?

Explain intermediate values are equally likely, Northwest airlines runs dai...

Northwest airlines runs daily flights from Detroit to Amsterdam. They face a fixed cost of $70,000 for each flight independent of the actual number of passengers on the plane. Ther

How is the supply chain cake industry by applying stages, How is the supply...

How is the supply chain cake industry by applying stages? The supply chain cake industry by applying stages as by given factors: • Farmer as like producer of commodities as

Explain guidelines for how management should be treating emp, Which of the ...

Which of the following responsibilities do human resource managers fulfil in their role as employee advocates? A) provide support for employees contesting unfair practices B) provi

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd