Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Explain what is a serial entrepreneur, 1. What is a serial entrepreneur? Is...

1. What is a serial entrepreneur? Is this a new phenomenon? 2. What does it take to be a successful serial entrepreneur? 3. Steve Chen, former PayPal engineer who co-founded

Define fddi network must be practicing what type of bridging, A bridge that...

A bridge that is used to connect an Ethernet network with a FDDI network must be practicing what type of bridging. a. a cut-through mode bridging b. source-route bridging

Answer the this question as I found on the google search, Ask questioAn ups...

Ask questioAn upscale home fixture supplier has four locations. Each location manages its ordering independently. The specialized lighting fixture sells for $300 and sales are on a

Outline suggestions for stimulate strategic entrepreneurship, As the invest...

As the investment community watches to see if Blockbuster will be able to sustain a double-digit growth rate under the new direction, the CEO is reviewing his actions as the strate

Cheapest car rental rents cars why getting loses, Cheapest Car Rental rents...

Cheapest Car Rental rents cars at the Chicago airport. The car rental market consists of two segments: the short term segment, which rents for an average of .5 weeks, and the mediu

Product or service design and process selection, Product or Service Design ...

Product or Service Design and Process Selection  Can the products/services be designed to satisfy the needs of both the market and the producers/providers? For example, it may

Straighten(seiton)&sustion(shitsuke), explain and give for examples hotels ...

explain and give for examples hotels services...how them service ?

Types of process technologies - batch production, Types of Process Technolo...

Types of Process Technologies - Batch Production Under this system the manufacturing is done in batches or groups or lots either on the basis of customer order or with a hope

Explain situation where instruction is not necessary, What would be an exam...

What would be an example of a situation where instruction is not necessary to solve a performance problem?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd