Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Explain the various risks and the affected stakeholders, Minnie Lee is an e...

Minnie Lee is an engineer with a multi-national aerospace company that produces fuel-line components for all types of air and space craft. Minnie discovered a potential defect in a

Analyze on the price of heating oil, Question For the financial year 20...

Question For the financial year 2012-2013, it has been decided the equalization of the tax on heating oil with the tax on fuel, thus increasing the price of heating oil. Do you

Disadvantages of observation methods, Disadvantages of Observation Methods:...

Disadvantages of Observation Methods: According to bailey the disadvantages in observation technique are: 1. Lack of Control: In artificial setting control over variable sis

Explain ennoblement in addition to the primary deliverable, Almost all proj...

Almost all project have deliverables dealing with documentation and customer ennoblement in addition to the primary deliverable

Explain steps in project completion have been finalized, Explain to a new p...

Explain to a new project manager how you ensure that all steps in project completion have been finalized

Explain jit for organization, Just-in-Time (JIT) Please respond to the foll...

Just-in-Time (JIT) Please respond to the following- • Develop three examples that illustrate how a manufacturing company of your choice uses JIT, and then determine three to fou

Explain step of the risk identification process in a project, Describe the ...

Describe the outputs and subsequent steps of the risk identification process in a project.

Explain what is the utilization rate of this service system, "Fast Eddie" F...

"Fast Eddie" Flournoy manages the service equipment division of Delta Airline's Atlanta terminal. He keeps a service crew on call to repair tow tractors that break down. Tractors b

Transportation method, Transportation  Method We  solve the transportati...

Transportation  Method We  solve the transportation  problem using the followings steps in order: a. Structuring the problem  into the  transportation  framework. b. Findi

Explain sow contains words such as nearly or approximately, If the customer...

If the customers SOW contains words such as nearly or approximately, then: Answer The project manager uses his discretion in determining the meaning The sponsor uses his d

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd