Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Explain what conflicts might you anticipate, As CEO of Ashford Medical Cent...

As CEO of Ashford Medical Center, the Board has authorized you to work with the Medical Director, the Chief of Staff, and Medical Staff in the development of an exciting new progra

Describe affirmative action and managing diversity, What distinctions can y...

What distinctions can you make between affirmative action and managing diversity

Explain the first step in the process is idle, A bottleneck is an operation...

A bottleneck is an operation that has the lowest effective capacity of any operation in the process. TRUE/FALSE. Write 'T' if the statement is true and 'F' if the statement i

Explain objective of value stream mapping is to improve data, 1) Bill of ma...

1) Bill of material errors can cause serious problems for MRP system calculations of dependant demands 2) No matter what forecasting technique is used, the probability of a prod

Define mathematics tends to lull the unsuspecting, C.W. Churchman once said...

C.W. Churchman once said that "mathematics tends to lull the unsuspecting into believing that he who thinks elaborately thinks well." Do you think that the best QA models are the o

MBA-2, What do you understand by"line balancing"?What happens if balance do...

What do you understand by"line balancing"?What happens if balance doesn''t exist?

Organisational behaviour, #ques 2. What, in your opinion, could be the rea...

#ques 2. What, in your opinion, could be the reasons for different Managerial thinking in this case? tion..

As a result of testing 20, As a result of testing 20,00 electric bulbs manu...

As a result of testing 20,00 electric bulbs manufactured by a company it was found that the lifetime of the bulbs was normally distributed with a mean of life of 2040 hours with st

Describe costco''s inventory before it is sold, The following table shows f...

The following table shows financial data for Costco and wal mart: CostcoInventories: $3,643Sales (net): $48106COGS: $41651 Wal Mart:Inventories: $29447Sales (net): $286103COG

What is queuing theory in operation management, What is queuing theory in o...

What is queuing theory in operation management? Queuing theory is usually seems a branch of operations management since the results can be used to plan for resources require

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd