Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Explain the concept of the quality of assurance system, Q. Explain the conc...

Q. Explain the concept of the quality of assurance system? Quality assurance is a systematic and planned action to give adequate confidence which a product or item conforms to

Explain quantitative risk so important in risk mitigation, Why is quantitat...

Why is quantitative risk so important in risk mitigation? Explain how you have seen this in action in life or in your organization.

Assume the length of critical path in a project, Suppose the length of crit...

Suppose the length of critical path in a project is 40 days and the standard deviation is 2 days. What due date should be set for the project so that the probability of completing

Capacity implication, how can make a plan for appropriate capacity of a cin...

how can make a plan for appropriate capacity of a cinema by replacing amount of standard seats with luxury seats?

Trans europlastic, #questiApplying the EBQ1 model, what batch size would yo...

#questiApplying the EBQ1 model, what batch size would you recommend for the babybath (143BB)? How long will each batch take to produce, and how many batches per year will be made?

Explain cost savings by cutting the current price, A company has a new desi...

A company has a new design for their product in next year that can reduce their material cost of producing units from $8.14 to $7.32. The company passes on half of all cost savings

Draw a network for the project, Question: (a) "CPM and PERT are two tec...

Question: (a) "CPM and PERT are two techniques widely used in project management." Under what conditions is each one of them used ? Illustrate your answer with examples. (b

Find project labour hours and cost and what profit amount, Midway through t...

Midway through the project your design and production people realize that a 75 percent improvement curve is more appropriate. What impact does this have on the project labour hours

Explain characteristics of organisational development, Explain characterist...

Explain characteristics of organisational development. Characteristics of Organisational Development (i) Organisational progress is an educational strategy for bringing a

Layout: Line balancing., Layout: Line balancing Kiko Teddy Bear is a manu...

Layout: Line balancing Kiko Teddy Bear is a manufacturer of stuffed teddy bears. Kiko would like to be able to produce 40 teddy bears per hour on its assembly line. The followin

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd