Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Sequencing.., program to find optimal sequence, total elapsed time and tota...

program to find optimal sequence, total elapsed time and total idle time in 6 jobs and 3 machines

Explain what are they and how do lenders use them, Hatten (2009) discusses ...

Hatten (2009) discusses the of credit. What are they and how do lenders use them? As you consider the possibility of being an entrepreneur, which of the 5 Cs is most important for

Explain multifactor productivity, The following table shows data on the ave...

The following table shows data on the average number of customers processed by several bank service units each day. The hourly wage rate is $15, the overhead rate is 1.0 times labo

Define whether each of the following is sufficiently support, Explain wheth...

Explain whether each of the following is sufficiently supported by consideration to be a contract. Provide examples, laws, or other relevant information to support your answer. Mag

Explain marketing is considered both an art and a science, Marketing is con...

Marketing is considered both an art and a science. How do the 4Ps, or marketing mix, help us bridge the gap between art and science? a. Marketing is about advertising.

Describe do you see any points of conflict, Write about your understanding ...

Write about your understanding of the assumptions of new science and their implications for leaders in the 21st Century. 1. How are they supported by The Thinking Habits of Mind

Explain is herzog a partner in the a1a car wash business, White, Fring, and...

White, Fring, and Pinkman are partners in the operation of the A1A car wash. Without Fring's knowledge, White and Pinkman sold 10 percent of their interest in the business and its

Explain criminally liable for actions of a few employees, Respondeat superi...

Respondeat superior is the theoretical basis for holding companies criminally liable for actions of their employees. Companies oftentimes have little defense against prosecution. C

Explain what is risk, What is risk? How does risk differ from uncertainty? ...

What is risk? How does risk differ from uncertainty? How does it impact a business?

Linear trend equation, A cosmetics manufacturers marketing department has d...

A cosmetics manufacturers marketing department has developed a linear trend equation that can be used to predict annual sales of its popular Hand and Foot Cream. We are given F sub

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd