Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Explain the ebq model, Applying the EBQ model, what batch size would you re...

Applying the EBQ model, what batch size would you recommend for this product? How long will each batch take to produce, and how many batches per year will be made? Should this mode

Explain downward communication, Explain Downward communication. Downwa...

Explain Downward communication. Downward communication: It moves downward in an organisation. The formal communication in between a subordinate and superior where the superio

Explain actionable claim based on unlawful retaliation, Marta is 57 and has...

Marta is 57 and has been a store manager for Ambrose & Company for 10 years. Ambrose & Company is a retail store for fashion forward women. Ambrose undergoes a restructuring and re

Describe good strategic partner for the company, the e-Activity, identify o...

the e-Activity, identify one firm that you think would make a good strategic partner for the company you researched. Provide specific examples of why you think this firm would be a

Treats older workers differently than the younger workers, Carlos, age 24, ...

Carlos, age 24, and Samuel, age 47, are employed as security officers for Jackson Security Co. In an effort to retain qualified officers and to be more competitive with the salarie

Explain company to suspect there is unmet demand, Describe some of the cues...

Describe some of the cues that might cause a company to suspect there is unmet demand for its products or services. How would you design a test to determine whether your suspicions

CALCULATING THE SLACK, Time (in Days) Activity Immediate Predecess...

Time (in Days) Activity Immediate Predecessor Optimistic Most Likely Pessimistic A - 3 6 8 B - 2 4 4 C - 1 2 3 D C 6 7 8

Explain system of billing, Suppose you are the manager of an accounts recei...

Suppose you are the manager of an accounts receivable unit in a large company. You are switching to a new system of billing and record-keeping and need to train your three supervis

Explain principles for determining product mix, The senior management at Ca...

The senior management at Canine Kernels Company CKC is concerned with the existing capacity limitations so they want to accept the mix of orders that maximizes the company's profit

Prepare a report about process and the process capability, 1. A company man...

1. A company manufactures 1Kg bags of grout (used in tiling).  The specification is given in grams and is 1002.0 ± 7.5 g.  The following data has arisen in a process investigation.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd