Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

How to determine the capacity requirements, Electronics assembly operates t...

Electronics assembly operates two 8 hours shifts for 275 days per year. Use this information in the table to determine the capacity requirements. Cell Phone Demand forecast (phones

After working for 30 years, In the table given below the Distribution Manag...

In the table given below the Distribution Manager is expected to service these DCs as per the demands placed. If the actual sales after completing week one is as follows, what woul

What is the aim of focus factories in manufacturing, What is the aim of foc...

What is the aim of focus factories in manufacturing? Focus factories: The aim of this is to decrease the cost of ‘part finished stock’ for example, work-into-progress. P

Idle time, how to calculae idle time if 8hours shift and cycle time 8 the q...

how to calculae idle time if 8hours shift and cycle time 8 the quantity produed is 40

Compute the estimated sample size needed, Practical Application Scenario 2 ...

Practical Application Scenario 2 To complete this scenario, use the Sample Size Estimator file provided in the Resources. The third shift at Microsoft's Windows' security uni

Define how create a positive climate within the organization, An organizati...

An organization's culture can be a debilitating impediment to the development and implementation of its strategic plan. Discuss the role of culture along with specific strategies

What are the relevant costs involved, Process Solutions provides a computer...

Process Solutions provides a computer-based document processing service. The accountant has produced the following analysis.   Standard Modifi

Explain the 5-s practice, Explain the 5-S practice for improving both the p...

Explain the 5-S practice for improving both the physical and thinking environment of an organisation. The 5-S practice is an approach to achieving an organised, clean and stand

Explain in detail important element and undercharged, Please explain in det...

Please explain in detail what you would do any why for the following scenario: You have just finished a large scope of work and an important subcontractor has sent you her bill. Up

Explain what are supply-chain management strategies used, What are at least...

What are at least four supply-chain management strategies used in Regal Marine? Present and explain them.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd