Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Explain business buying decision processes, Explain the eight general strat...

Explain the eight general strategies in the business buying decision processes.

Explain cost-minimizing production schedule, A motorcycle manufacturer is d...

A motorcycle manufacturer is determining its production schedule for the next 6 months. The cost of manufacturing a motorcycle during each month is Month 1 Month 2 Month 3 Month 4

Explain what internet business model would be appropriate, Please give me t...

Please give me the references as well or I won't' complete the rating. Thank you. E-commerce is the trend that most companies are going toward now a days. You are to select one

Explain what are the correlation coefficient, Mark Gershon, owner of a musi...

Mark Gershon, owner of a musical instrument dis-tributorship, thinks that demand for guitars may be related to the number of television appearances by the popular group Maroon 5 du

Describe some training needs in the work place, Discuss some training needs...

Discuss some training needs in the work place to create a positive cultural diversity work environment.

Explain in detail important element and undercharged, Please explain in det...

Please explain in detail what you would do any why for the following scenario: You have just finished a large scope of work and an important subcontractor has sent you her bill. Up

Make to order - types of operation system, Make to order - Operations Syste...

Make to order - Operations Systems In this case, manufacture of the product does not commence until an order has been placed by the customer. In the best restaurants food is

Number of defects - control chart, Number of Defects - Control Chart S...

Number of Defects - Control Chart Sometimes the attribute of concern is the number of defects (c) in an item rather than the number of defective items in a sample: for example

Find how much does the airport need to set aside now to pay, Orlando Intern...

Orlando International Airport plans to extend passenger capacity of its existing terminal to accommodate its forecasted growth. A new terminal would be needed once the state's busi

Case study on back unopened book for a refund, I recently rented a book and...

I recently rented a book and it turns out that I no longer need to be in the class that requires that book. The book just got here today and I have not opened the package at all. I

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd