Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Which new market was opened when apple introduced itunes, 1. When App...

1. When Apple introduced iTunes, a new market was opened. Which of the following describes this type of innovation? a. Value capture b. Presence c. O

Describe why firms conduct marketing research, Why do successful firms cond...

Why do successful firms conduct marketing research for their product and services?

Digitra; cell phone, Ask que Prepare Paul Jordan’s report to John Smithers ...

Ask que Prepare Paul Jordan’s report to John Smithers using regression analysis. Provide a summary of the cell phone industry outlook as part of Paul’s response. stion #Minimum 100

Explain the concept of the quality of assurance system, Q. Explain the conc...

Q. Explain the concept of the quality of assurance system? Quality assurance is a systematic and planned action to give adequate confidence which a product or item conforms to

Transportation and assignment problem, Transportation and Assignment Proble...

Transportation and Assignment Problem: Transportation  problem is the  problem of determining the minimum  cost for  allocating a product from  several supply sources to sever

Compute xpected top-down estimated cost for project, You have been asked to...

You have been asked to estimate the costs for a project to build an industrial power plant. Based on historical data, the steam turbine accounts for 30 percent of the total costs f

Explain international union, Most day-to-day interaction between labour and...

Most day-to-day interaction between labour and management involves the: Answer (1) national union. (2) International union. (3) Industrial union. (4) Local union.

Explain briefly the vrooms expectancy theory of motivation, Question 1: ...

Question 1: More and more organizations are showing greater reliance on team building and team work as opposed to individual work. Please discuss. i. Give characteristics o

Explain what is the union relations environment, What is the union relation...

What is the union relations environment today and what are the future trends in labour relations?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd