Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Depict a project network that includes all the activities, Operations and S...

Operations and Supply Chain Management : CELL PHONE DESIGN PROJECT 1. Draw a project network that includes all the activities 2. Calculate the start and finish times for each

Explain various health care plans, The first step in the Model of Scientifi...

The first step in the Model of Scientific Inquiry is to identify the question or problem needing further study. The following seven situations are typical everyday problems in busi

Behaviour while a person ethic is somewhat questionable, Which of the follo...

Which of the following statement is correct/1. Deep acting and surface acting are two terms reflecting ways of behaviour when a person ethic is somewhat questionable/2. Deep acting

Difference among purchasing and supply management, What is the difference b...

What is the difference between purchasing and supply management?

Explain uninformed aspiring international business executive, Our Internati...

Our International Management text cites in Reading 1.2 that:"U.S Management theories contain a number of idiosyncrasies not necessarily shared by management elsewhere" and then pro

Supply chain, to what extent is SCM applicable to a service operation

to what extent is SCM applicable to a service operation

Explain dummy activity, Explain Dummy Activity. Every project has a num...

Explain Dummy Activity. Every project has a number of job operations or tasks that are termed as activities.  An activity is a component of a project and this may be a process,

Explain affect your overall impression of the candidate, How does the use o...

How does the use of music in political play a role in establishing a candidate's brand? Does a candidate's use of a song you like (or dislike) affect your overall impression of the

Explain milestones and key deliverables, When developing the milestone sche...

When developing the milestone schedule for the project charter it is helpful to identify relatively few milestones and key deliverables

Explain management efforts and employee involvement, The decline in union m...

The decline in union membership has been mainly attributed to what four factors? Answer (1) Change in economy, employee involvement, human resources practices, and government regul

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd