Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Define the break-even point for each range, A manager must decide how many ...

A manager must decide how many machines of a certain type to purchase. Each machine can process 100 customers per day. One machine will result in a fixed cost of $2000 per day, whi

Depict a project network that includes all the activities, Operations and S...

Operations and Supply Chain Management : CELL PHONE DESIGN PROJECT 1. Draw a project network that includes all the activities 2. Calculate the start and finish times for each

Evaluate the statement work center to minimize idle time, Evaluate the stat...

Evaluate the statement: "In lean operations, when work is completed at one work center, it is important to immediately move the completed work to the next work center to minimize i

How marketing consultant brought in to help a company, Imagine you are a ma...

Imagine you are a marketing consultant brought in to help a company who has a product that is so successful they cannot keep up with customer demand. What questions would you as

Explain calculated values in descending order on the same, Create a procedu...

Create a procedure in VBA to do the following actions: -Create a linear series of numbers starting at 1 (e.g. 1, 2, 3,) -Display a Message Box asking if you'd like to calculate ano

Find probability that the store is full, A drug store has two windows avail...

A drug store has two windows available for serving customers, who arrive at a Poisson rate of 40/hr. Service time is exponentially distributed with a mean of 2 min. Only one window

Identify the feasible region for the set of constraints, Identify the feasi...

Identify the feasible region for the following set of constraints: 3A - 2B ? 0 2A - 1b ? 200 1A ? 150 A, B >=0 This will need to include graphing or I will not ra

What is image management, After the occurrence of Hurricane Katrina, insura...

After the occurrence of Hurricane Katrina, insurance companies refused to pay claims to insurance holders who paid premiums on time and had binding legal contracts. What do you thi

Activities and advantage that providing facility to customer, Consider the ...

Consider the Gleneagles Hotel in Scotland - it is unique, not part of a chain. It is a six star hotel with world class sports facilities with two championship golf courses, which h

Explain the history and core business of company kodak, 1. Describe The His...

1. Describe The History And Core Business Of Each Company Kodak And Fujifilm. 2. Determine what other management differences have impacted the relative success of Kodak and Fuji

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd