Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Describe identified the problem and a technology solution, At this point of...

At this point of the project, you have identified the problem and a technology solution for the business. Now, you want the business to accept the idea. Using your text, the pre

Explain exceed the amount invested in auto loans, A bank is attempting to d...

A bank is attempting to determine where its assets should be invested during the current year. At present, $500,000 is available for investment in bonds, home loans, auto loans, an

Corporate social responsibility, explain the concept and practice of corpor...

explain the concept and practice of corporate social responsibility (CSR).

Conscientiousness is a big five dimension that includes, Conscientiousness ...

Conscientiousness is a big five dimension that involve the traits of being-----------------1.unworried; secure and relax/2.imaginative and broad minded/3.responsiable; dependable a

Practice Question.., 4. (32 points) You and your roommate are planning to o...

4. (32 points) You and your roommate are planning to open “Pizza In The Dorm” to make and distribute fresh pizza from your dorm room. You plan to provide 100% fresh, high quality p

Aggreate planning, Identify (a) the demand options for aggregate planning; ...

Identify (a) the demand options for aggregate planning; and (b) the capacity (supply) options for aggregate planning

Financial risk, the importance of the measurtement of market risk for finan...

the importance of the measurtement of market risk for financial institution

Number defective - np chart, Number Defective - Np Chart This type of ...

Number Defective - Np Chart This type of chart can be used when it is possible to establish a constant sample size n. It has the advantage that it is readily understood by use

Process capability index - measure of inherent capability, Process Capabili...

Process Capability Index - Measure of the Inherent Capability This index provides a measure of the inherent capability of a process by simply relating the 6σ spread of the pro

Explain microsoft visio erd, Review the information currently housed in Huf...

Review the information currently housed in Huffman Trucking%u2019s database, in the Entities and Attributes for Fleet Truck Maintenance file on the virtual Organizations site. (Cus

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd