Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Explain project supply and materials budget, Case 11-3 Budget the topic for...

Case 11-3 Budget the topic for this week's assignment is taken from our text (INF336 2010, Mcgraw-Hill) and refers to the City of Granston Case 11-3 at the end of Chapter 11. Using

Explain what is managerial problem solving, What is managerial problem solv...

What is managerial problem solving and how does it affect a business job?

Depict an activity on arrow network, Project involves 12 activities and the...

Project involves 12 activities and the precedence relationship is provided below in brackets. (1) Draw an activity on arrow network to represent the project tasks and their depende

Show role as an employee of an organization in the is field, Briefly descri...

Briefly describe your role as an employee of an organization in the IS field. Give examples of what you need to know about information systems and how it can help with your job per

Alternative process sequences - services, Alternative Process Sequences - S...

Alternative Process Sequences - Services Just as in the selection of processes for product production, typically there will be alternative ways of delivering a service. Consid

Explain an engine system consists of three main components, An engine syste...

An engine system consists of three main components in a series, all having the same reliability. Determine the level of reliability required for each of the components if the engin

Explain the annual interest payment, A bond has a coupon rate of 15%, a yie...

A bond has a coupon rate of 15%, a yield to maturity of 10.55%, and a market price of $850. Therefore, the annual interest payment is: a.) $850 b.) $150 c.) $105.50. d.) $120.0

Explain what are the schedule and cost variances, I need to find the schedu...

I need to find the schedule and cost variances for a project Actual cost at month 16 = $540,000 Scheduled cost = $523,000 Earned value = $535,000 Provided this information,

Explain manager of a production department, Suppose that you are the manage...

Suppose that you are the manager of a production department that uses 400 boxes of rivets per year. The supplier quotes you a price of $8.50 per box for an order size of 199 boxes

Explain organization''s structure and culture, Why would an organization ch...

Why would an organization choose a corporate level strategy to expand its value-creation activities beyond its core domain? Discuss how an organization's structure and culture migh

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd