Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Explain why organizations need correct performance metrics, Discuss why org...

Discuss why organizations need to have the correct performance metrics to drive quality. Think of examples in the news and their outcomes.

Describe why financial objectives essential for the company, Why do financi...

Why do financial objectives essential for the company to succeed?

Siting departments for process layout - manufacturing, Siting Departments f...

Siting Departments for Process Layout - Manufacturing One of the most significant features of the siting of departments in a process layout is its surprising complexity. Even

Explain statutory law, Statutory law is: Answer a law enacted by a legislat...

Statutory law is: Answer a law enacted by a legislative body also known as the fundamental law of the nation a form of common law the separation of powers at the federal level all

Explain terms labor, The Stone Company produces three sizes of window fans:...

The Stone Company produces three sizes of window fans: small, medium, and large. The manager has formulated an LP model for fan production: maximize 6 x1 + 8 x2 + 5 x3 (profit) sub

Explain a market-product grid is a framework to relate the, A market-produc...

A market-product grid is a framework to relate the _____ to products offered or potential marketing actions by an organization. estimated expenses for products sold total ant

Explain what purpose does the project charter serve, a. What purpose does t...

a. What purpose does the Project Charter serve? b. What are the main components or sections of the Project Charter? c. What purpose does the Project Definition Document serve

Learning curve concept plays vital role in location decision, This assignme...

This assignment is designed to demonstrate that the learning curve concept plays a vital strategic role in location decision. A company started making a new product simultaneously

Explain should people in all job categories be tested, If you believe that ...

If you believe that urine testing in some form might be acceptable, write down the outlines of sound testing program. Who should be tested? Employees? Job applicants? Should there

What is the influence of losses in the process in inspection, What is the i...

What is the impact of losses in the process in Inspection and Final Test?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd