Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Explain business model and strategies changed overtime, 1. Why has Southwes...

1. Why has Southwest's business model and strategies changed overtime? 2. In what ways is Southwest Trying to improve its competitive advantage in 2011? 3. Give examples of a

Explain what message did management send through this tactic, Super TV Chan...

Super TV Channel 6 operates in a major Midwestern city and is on the air 24 hours a day. Labour-management relations there have been relatively good over the years. There are three

Illustrate your discussion using a service organisation, Question 1: "Y...

Question 1: "Yield management guides the decision of how to allocate undifferentiated units of capacity to available demand in such a way as to maximize profit or revenue." Cri

Level capacity plan, Level Capacity Plan The inventory size is varied ...

Level Capacity Plan The inventory size is varied keeping the workforce size and utilization of work constant. The number of workers ( working size) is kept constant throughout

Explain method would you pursue to minimize channel conflict, D-Magic is a ...

D-Magic is a new company that has developed a revolutionary 3D television. It uses a new technology that provides a much sharper and realistic 3D experience than their competitors.

Explain how many hours would the average laborer, In December, general moto...

In December, general motors produced 7,200 customized vans at its plant in Detroit. The labor productivity at this plant is known to have been 0.10 vans per labor hour during that

Explain how can product development costs be minimized by, How can product ...

How can product development costs be minimized by entering the market late

Find the probability that both service clerks are idle, Sharp Discounts Who...

Sharp Discounts Wholesale Club has two service desks, one at each entrance of the store. Customers arrive at each service desk at an average of one every twelve minutes. The servic

What kinds of goals will donna likely make, Donna Hamilton is excited to op...

Donna Hamilton is excited to open her own restaurant, the Westminster Inn. Although Donna has worked as a chef and even managed a number of restaurants during her career, she is co

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd