Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Impact of multinational enterprises to their firm boundaries, Multinational...

Multinational enterprises (MNEs) have an impact far beyond their firm boundaries. Assume you are working for a small firm that supplies a product or service to an MNE. How might yo

How to determine the capacity requirements, Electronics assembly operates t...

Electronics assembly operates two 8 hours shifts for 275 days per year. Use this information in the table to determine the capacity requirements. Cell Phone Demand forecast (phones

Explain the probable destiny competing products, Consider this: Lee Peterso...

Consider this: Lee Peterson has invented a new product that detects water leaks due to broken pipes and sends out an alarm similar to a smoke alarm. However, Lee has very little pe

Explain the major categories of assumptions, A financial plan is a bridge b...

A financial plan is a bridge between two balance sheets. Describe the major categories of assumptions that must be specified to project a future balance sheet, given a current b

Explain were the british more responsible for losing the war, Were the Brit...

Were the British more responsible for losing the war or were the colonists more responsible for winning it? Use specific examples from this week's readings to support your respons

Explain what makes a constraint critical or active, 1) What makes a constra...

1) What makes a constraint critical or active? Explain. 2) Jim has used the theory of constraints to maximize the production of his active constraints and match the production r

Explain what is the status of the internet contract, Beth advertised her 20...

Beth advertised her 2005 Corvette for sale on the Internet. In her advertisement, she falsely stated that the vehicle had only been driven 60,000 miles when in fact it had been dri

Explain ethics addressed in the business world today, How are leadership tr...

How are leadership traits and ethics addressed in the business world today?

Layouts of supermarkets, pick a supermarket of your choice, observe the lay...

pick a supermarket of your choice, observe the layout and why the layout is like that

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd