Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Forward scheduling - scheduling techniques, Forward Scheduling - Scheduling...

Forward Scheduling - Scheduling Techniques Forward scheduling means assigning customers orders or job to various work centers based on the as early as possible approach. Thus

Explain these with the actual service delivered, Q1 Evaluate the service to...

Q1 Evaluate the service to club members and casual flyers by completing a table similar to Table 3.1. Q2 Chart the five performance objectives to show the dif¬fering expectations

Explain about the vertical integration, Q. Explain about the vertical integ...

Q. Explain about the vertical integration? Backwards vertical integration a firm integrating backwards into its supply chain, the supplier included in a previous and a various

Explain contemporary theorists emphasize two approaches, 1. As management t...

1. As management theory has evolved, contemporary theorists emphasize two approaches: the "systems approach," and the "contingency approach." Explain each. 2. Regarding ethics a

Explain current business operating on a global scale, Introduce a new speci...

Introduce a new special form of insurance for current business operating on a global scale with a diverse work force, which includes virtual employees.

Describe ethical to reduce the number of employees, 1. Based on GM's ...

1. Based on GM's current condition, do you think it is ethical to reduce the number of employees? Why or why not?

Explain what is the horizon value, Current and projected cash flows for Ran...

Current and projected cash flows for Randell Global Operatons are shown below. Growth is expected to be constant after 2012, and the weighted average cost of capital is 11%. What i

Explain the probability that this person actually has heart, Medical studie...

Medical studies have shown that 10 out of 100 adults have heart disease. When a person with heart disease is given an EKG test, a 0.9 probability exists that the test will be posit

Explain what is the best decision, Let's say you own a small construction c...

Let's say you own a small construction company. You need to decide whether to buy a bulldozer to add to your equipment fleet. You assume that the construction industry could be Goo

Explain what is the productivity, 1. A manufacturing company has a small pr...

1. A manufacturing company has a small production line dedicated to the production of a particular product. The line has four stations in serial. Inputs arrive at station 1 and the

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd