Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Explain use debt financing, If you decide to use debt financing, which kind...

If you decide to use debt financing, which kind of loan, fixed-rate or variable-rate, would you prefer? Why? If you decide to use equity financing, where would you find equity f

Explain compensation plan, Do you believe a compensation plan based 100% on...

Do you believe a compensation plan based 100% on commission would ever be justified? Give an example for either option.

Describe the idea that an information system, Discuss the idea that an info...

Discuss the idea that an information system by itself can rarely provide a sustainable competitive advantage?

Explain values and customs of the local workforce, What is the key reason h...

What is the key reason host country nationals are hired to fill most foreign positions? Answer (1) They can more easily understand the values and customs of the local workforce. (2

Linear programing, Ask question #Minimum 100 words acceptNas food produces ...

Ask question #Minimum 100 words acceptNas food produces to kinds of popular dark chocolate bars. the banana and coffee. the banana bar costs 0.22 to make and sells of 0.35, where a

Explain variable costs, Explain Variable costs. Variable costs converse...

Explain Variable costs. Variable costs conversely, tend to vary directly along with the volume of output. Illustrations of variable cost are: - * Direct production labour co

Explain challenges in leading a multi-generational workforce, Challenges in...

Challenges in leading a multi-generational and/or multi-cultural workforces: Need a complete summary for the listed assignment, references. Please at least one page of information

Why is this an vital concern for all businesses today, 1)What should you do...

1)What should you do after the fact when your company's information security has been breached? 2)what can you do to protect your company's data from unauthorized access? 3)W

Explain major considerations regarding logistics alliances, What are the ma...

What are the major considerations regarding logistics alliances, for: a) initiation? b) implementation? c) maintenance? d) termination?

Explain management principles applicable to organizing, The American Red Cr...

The American Red Cross has been asked to oversee the clean-up efforts in Japan after the earthquake and tsunami that occurred in March 2011. Analyze the management principles appli

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd