Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Determine the standard time by time study, 1. Is work measurement used in y...

1. Is work measurement used in your own organisation? If not, then give thought to how: alternative methods are compared; load is balanced with capacity; productivity is monitored;

Explain inquiring minds want to know, On companion website Read Case Stu...

On companion website Read Case Study: Inquiring Minds Want to Know 1 Build the management-research question hierarchy. 2 What ethical issues are relevant to this study?

What is the aim of focus factories in manufacturing, What is the aim of foc...

What is the aim of focus factories in manufacturing? Focus factories: The aim of this is to decrease the cost of ‘part finished stock’ for example, work-into-progress. P

Explain mean flow time, Jane Reed bakes breads and cakes in her home for pa...

Jane Reed bakes breads and cakes in her home for parties and other affairs on a contract basis. Jane has only one oven for baking. One particular Monday morning she finds that she

Describe rented books and did not get the discount, Hi I answers a question...

Hi I answers a question and earned 10 percent off my next purchased. I just rented books and did not get the discount how can i reversed this??

Explain changes in the environment, What changes in the environment provide...

What changes in the environment provided the opportunity for the Dewmocracy approach?

Describe the areas needing improvement as a communicator, • From the scenar...

• From the scenarios, we see that Chris and Erica have different communication styles that could potentially have a negative impact on the business. Suggest at least two strategies

What are the advantages of the chase demand strategies, What are the advant...

What are the advantages of the chase demand strategies? The advantages of the chase demand strategies are as illustrated below: a. Flexible utilisation of resources for inst

Define the concept of a career, Discuss the concept of a career. What are t...

Discuss the concept of a career. What are the Four Career Stages- List each one with its specific characteristics

Explain inefficiency factor, A JIT system uses kanban cards to authorize mo...

A JIT system uses kanban cards to authorize movement of incoming parts. In one portion of the system, a work center uses an average of 93 parts per hour while running. The manager

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd