Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Johnson''s rule, Please help with sequencing the following jobs; T,U,V,W,X,...

Please help with sequencing the following jobs; T,U,V,W,X,Y,Z (WORK CENTER 1 - 15,7,4,7,10,4,7) (WORK CENTER 2 - 3,9,10,6,9,5,8) RESPECTIVELY TO THE JOBS. THE REST I WILL CALCULATE

Explain first step in your data analytical project, Your final project enta...

Your final project entails systematic extraction of decision-aiding insights out of a dataset provided to you in the Doc Sharing area. This project will provide you with hands-on e

Explain communication is a two-way process, Communication is a two-way proc...

Communication is a two-way process. Communication is a series of loops. A message must be sent and the message must be received. However, the message must also be understood and ac

Mgt455, Discuss an example of a work-related project that is able to be bro...

Discuss an example of a work-related project that is able to be broken down into structure, tasks, subtasks, and work packages, and why project management in the form of a CPM/PERT

Divide items according to category, Drop items into the correct category un...

Drop items into the correct category under "goods company or service company" belonging to which of the 4P's: Goods Company Service Company Product: Price: Place: Pr

Explain contractual claims, Complete the following, placing it in a single ...

Complete the following, placing it in a single Word document- Having a clear understanding of the courts and where to file specific claims has provided your department with a go

Describe management implications of information technology, Briefly explain...

Briefly explain the management implications of information technology

Explain whole foods market has a mission, 1. What evidence do you find in t...

1. What evidence do you find in this case, either explicitly or implicitly, that indicates that Whole Foods Market has a mission, core values, or is practicing decision-making that

Describe culture and values and ethics, Discuss culture, values, ethics, an...

Discuss culture, values, ethics, and other such elements that lead to differences in social culture; 2) Explain the business and economic implications of differences in culture and

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd