Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Explain attack advertising, In 2007, the Cartoon Network was fined for publ...

In 2007, the Cartoon Network was fined for public disruption of the Bostonian transportation system while using a new form of public relations called: Answer > Guerilla advertising

What are the advantages of the level capacity strategy, What are the advant...

What are the advantages of the Level capacity strategy? The advantages of the Level capacity strategy: a. Employment of operational resources at all times. b. Efficient p

Explain inefficiency factor, A JIT system uses kanban cards to authorize mo...

A JIT system uses kanban cards to authorize movement of incoming parts. In one portion of the system, a work center uses an average of 93 parts per hour while running. The manager

Major concerns confronting thomas regarding the management, Analyze the thr...

Analyze the three primary concerns confronting Thomas regarding the management of this project. Suggest a method of addressing each of the three concerns

Explain the ftc prohibit the use of this commercial, Perfect Face Cream ran...

Perfect Face Cream ran a commercial to showcase its new Wrinkle-Free Face Cream. The commercial showed an older woman with severe wrinkles followed by images of that same woman aft

Explain the factors affecting motivation, Explain the factors affecting mot...

Explain the factors affecting motivation . Factors influencing motivation: Achievement-Personal satisfaction in problem solving and job completion. Advancement-Promot

Linear Program , I have 3 questions involving linear programming, solving u...

I have 3 questions involving linear programming, solving using both a) the enumerating the corner points method and b) the iso-profit line method.

Explain developing a risk matrix, How would you go about developing a risk ...

How would you go about developing a risk matrix? Give an example of the kinds of factors that should be evaluated.

What is the safety stock and rop, Chicago's Hard Rock Hotel distributes a m...

Chicago's Hard Rock Hotel distributes a mean of 1000 bath towels per day to guests at the pool and in their rooms. This demand is normally distributed with a standard deviation of

Explain teplitz decides to increase the weights for quantity, Charles Tepli...

Charles Teplitz's firm wishes to use factor rating to help select and outsourcing provider of logistics services. A) with weights 1-5(5 highest) and ratings 1-100 (100 highest), us

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd