Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Explain what assignment minimizes the total traffic flow, Six processes are...

Six processes are to be laid out in six areas along a long corridor at Linda Babat Accounting Services. The distance between adjacent work centres is 40 feet. The number of trips b

Explain what strategic objectives in traditional approach, Lincoln electric...

Lincoln electric is gradually moving toward using a more traditional approach to pay, putting less emphasis on earnings at risk. What strategic objectives would lead the company to

Explain what are the pros and cons of bureaucratic controls, What are the p...

What are the pros and cons of bureaucratic controls such as rules, procedures, and supervision? Should all organizations use bureaucratic controls? Why or Why Not?

Explain assembly of power steering pumps, A small assembly line for the ass...

A small assembly line for the assembly of power steering pumps needs to be balanced. Exhibit 8.11 in the text is the precedence diagram. The cycle time is determined to be 1.5 minu

Outline suggestions for stimulate strategic entrepreneurship, As the invest...

As the investment community watches to see if Blockbuster will be able to sustain a double-digit growth rate under the new direction, the CEO is reviewing his actions as the strate

Compute productivity indices and compare rises productivity, 1. Productivit...

1. Productivity is considered by many to be the essence of operations management - suggest reasons to support this assertion.  2. Using the figures in the table, if we use 2000

Factors for plant location choice - proximity to market, Factors for plant ...

Factors for plant Location choice - Proximity to Market Organization s may choose to locate facilities close to their market, not merely to minimize transportation costs, but

Describe how you would manage an hr technological change, Change is a given...

Change is a given. Explain how you would manage an HR technological change. What process might you use (cite theory as appropriate) to implement technological changes in a traditio

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd