Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Explain major components of information management, Discuss the five (5) ma...

Discuss the five (5) major components of information management / information technology (IM / IT) governance with a focus on how they will collectively improve the quality of heal

Compute annual holding cost plus the annual ordering cost, The current orde...

The current order quantity for Paul's Pasta Pinwheels is 200 boxes. The order cost is $4 per order, the holding cost is $0.40 per box per year, and the annual demand is 500 boxes p

Compute the value of cash flow based on discount rate, Calculate the presen...

Calculate the present value of a stream of cash flows based on a discount rate of 8%. Annual cash flow is as follows 1. Year 1 = $100,000 2. Year 2 = $150,000 3. Year 3 = $200,0

Depict diagram a complex system, Diagram a complex system (a series of caus...

Diagram a complex system (a series of causal loops and their interconnections) for the ecosystem of your choice (desert, rainforest, tidal marsh, etc.).

Explain efficiently report of schedule of a project, Illustrate how to effe...

Illustrate how to effectively and efficiently report on the schedule of a project to the different stakeholder groups. Show calculations and provide rationale for each strategy.

Calculate the economic order quantity, A local nursery greens uses 1560 bag...

A local nursery greens uses 1560 bags of plant food annually. Green works 52 weeks per year. It costs $10 to place an order for plant food. The annual holding cost rate is $5 per b

Linear programming, A paper mill produces two grades of paper viz., X and Y...

A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper i

Explain quality control, Explain Quality Control. Quality Control: Co...

Explain Quality Control. Quality Control: Control is a system for measuring and inspecting (checking) a phenomenon.  This suggests when to inspect, how often to inspect and h

Order losers - operations strategy, Order Losers - Operations Strategy ...

Order Losers - Operations Strategy These are characteristics which denote poor performance in the operations management function and can cause losses in current or future busi

Schmenner''s service-process matrix - operation strategy, Schmenner's Servi...

Schmenner's Service-Process Matrix The service-process matrix was introduced earlier. It is Schmenner's service industry equivalent of the product-process matrix. The service

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd