Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Explain what are competencies, What are "competencies?" Explain, and provid...

What are "competencies?" Explain, and provide two or three examples.

Must adobe establish a policy for granting flexible work, Should Adobe esta...

Should Adobe establish a policy for granting flexible work schedule? If yes what might that policy contain?

Explain a product at each stage of the plc, Using the product life cycle, d...

Using the product life cycle, describe a product at each stage of the PLC and support your choice.

Performance measures - operation strategy, Performance Measures - Operation...

Performance Measures - Operation Strategy It is common to find that measures are made of operational factors which do not contribute to the winning of orders, whilst key facto

Explain industrial disputes act, Explain Industrial Disputes Act. The I...

Explain Industrial Disputes Act. The Industrial Disputes Act intend at settling disputes between Employer and Employees.

Describe specific strategies, What challenges may arise if a U.S. project m...

What challenges may arise if a U.S. project manager moves to a foreign country to manage a project for 5 years? Discuss specific strategies that the U.S. project manager could use

Define what can companies and organizations do to facilitate, What can comp...

What can companies and organizations do to facilitate diversity?

Explain supply chain activities, Compile a list of major system life-cycle ...

Compile a list of major system life-cycle activities. For each activity on the list, try to find the related supply chain activities. Present your finding in a table with the syste

Describe decision making, Q1. What is SWOT Analysis.? Q2. Explain Decision ...

Q1. What is SWOT Analysis.? Q2. Explain Decision making.

Explain dual chains of command can create more problems, Some people argue ...

Some people argue that the matrix structure should be adopted only as a last resort because the dual chains of command can create more problems than they solve. Discuss. Do you agr

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd