Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Want help creating database using microsoft access, Need help creating data...

Need help creating database using Microsoft access. Please see question. Please create a new database called Automobiles for North East Honda dealership. The database will have

Objectivise and benefits of work study, Objectivise and Benefits of Work St...

Objectivise and Benefits of Work Study Objectivise of Work Study a)Provide more and improved physical means to motivate the workers. b)Improve the basic process by resear

Explain some of the near-term and long-term results, As the industry watche...

As the industry watches to see how United Airlines' strategy performs against American Airlines' strategy, management at United Airlines is anxiously monitoring market signs to det

Explain how does the pursuit of outsourcing align, Should Galanz continue t...

Should Galanz continue to expand its capacity through outsourcing arrangements? How does the Pursuit of outsourcing align with its operations strategy?

What are the advantages of the chase demand strategies, What are the advant...

What are the advantages of the chase demand strategies? The advantages of the chase demand strategies are as illustrated below: a. Flexible utilisation of resources for inst

Draw a schematic layout, The flow of materials through eight departments. E...

The flow of materials through eight departments. Even though the table shows flows into and out of the different departments, assume that the direction of flow is not important. In

Assignment, Analyze the strategic role of operations management in terms of...

Analyze the strategic role of operations management in terms of organizational and operational objectives.

What are the pros and cons of flexible schedules for staff, What are the pr...

What are the pros and cons of flexible schedules from an employee's perspective?

Explain the system utilization rate and the probability, Sid Das Brick Dist...

Sid Das Brick Distributors currently employs 1 worker whose job is to load bricks on outgoing company trucks. An average of 24 trucks per day, or 3 per hour, arrive at the loading

Explain the amount of time covered by the basic mrp, The amount of time cov...

The amount of time covered by the basic MRP record is called the _____. time bucket new horizon time horizon planning horizon

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd