Q. Computation of Settlement?

The settlement  in any soil mass under an applied stress is given by

s = si + sc + ss

where,

S  =  total settlement,

Si =  immediate (or elastic) settlement,

Sc  =  primary consolidation settlement,  and

Ss  =  secondary  consideration'settlement.

In granular soils, elastic settlement is the predominant part. In inorganic  silts and clays, the primary consolidation settlement probably predominates. The secondary consolidation settlement forms the major part of the total settlement in highly organic soils and peats.


Related Discussions:- Computation of settlement

Delay of bituminous laying on top of sub-base, Question In case if ther...

Question In case if there is a delay of bituminous laying on top of sub-base, have to tack coat be applied on the top surface of sub-base? Answer When there is a d

What is collocated network operation, What is Collocated network operation ...

What is Collocated network operation As wireless LANs become more popular, it is likely for two or more wireless LANs to operate in the similar area or in some area where inter

Functions of different reinforcement in a typical pile cap, Functions of di...

Functions of different reinforcement in a typical pile cap Loads from columns transferring to pile cap persuade tensile forces at the bottom of cap. For example, by using trus

Planning and scheduling tutorial, Am looking for .planning and scheduling...

Am looking for .planning and scheduling tutorial , cost engineering tutorials

Maintenance of earth roads, Maintenance of Earth Roads: The main task...

Maintenance of Earth Roads: The main task in maintaining the earth road is to ensure that cross-section is intact and is free from rutting, depressions and corrugations, and

Roads, wbm road step by step procedure

wbm road step by step procedure

Shear force and bending moment, how to draw shear force and bending moment ...

how to draw shear force and bending moment from load intensity

Indicate quality of rock foundation, Question During piling works, norm...

Question During piling works, normally founding levels of bored piles are definite by using total core recovery or rock quality designation (RQD). Are there any problems by

Calculate the total duration for the four activity project, Calculate the T...

Calculate the Total Duration for the Four Activity Project Solution:      Scheduling work activity has associated time duration. The durations shown in the Table were e

Abc, uses concrete slump test

uses concrete slump test

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd