Competence - customer satisfaction and service quality, Operation Management

Assignment Help:

Competence - Customer Satisfaction and Service Quality

Means possession of the required skills and knowledge to perform the service. It involves: knowledge and skill of the contact personnel, knowledge and skill of the operational support personnel and research capability of the organisation, e.g. securities brokerage firm.


Related Discussions:- Competence - customer satisfaction and service quality

Explain what issues would a judge decide, Fun Products, Inc. is in the busi...

Fun Products, Inc. is in the business of designing computer games. At the end of a particularly successful year, company management decided to throw a celebration party at which it

Relationship among analysis and planning and implementation, Analyze the re...

Analyze the relationship between analysis, planning, implementation, and control. Provide an example of a product or service that flows through this relationship. Break down the pr

Plant layout, possible quesstions of plant layout

possible quesstions of plant layout

Define compare the effectiveness, Compare the effectiveness of 2 week, 4wee...

Compare the effectiveness of 2 week, 4week 6week. I just need the moving averages. For 2,4 and 6 weeks from managing operations across the supply chain book the question is startin

Thus if a budget is prepared it can only be a crude estimate, Frequently, a...

Frequently, at the time the project charter is prepared there is only a very general understanding of the project, so if a budget is prepared it can only be a crude estimate.

Define a swot analysis for the company, Write an eight to ten (8-10) page p...

Write an eight to ten (8-10) page paper in which you 1. Determine the impact of the companys mission, vision, and primary stakeholders on its overall success. 2. Analyze the

Explain what is the critical path, The following represents a project that ...

The following represents a project that should be scheduled using CPM: Time (DAYS) Activity Immediate Predecessors a m b A - 1 3 5 B - 1 2 3 C A 1 2 3 D A 2 3 4 E B 3 4 11 F

Advantages of the enterprise-wide systems, Q. What are the advantages of th...

Q. What are the advantages of the enterprise-wide systems? Benefits of Enterprise-wide systems (ERP) systems: a. In this system integration of software applications can easi

Compute a tracking signal or determine whether the forecast, The following ...

The following are monthly actual and forecast demand levels for May thur December for units of a products manufactured by the N. tamimi Pharmaceutical Company Month Actual deman

What is usefulness of materials requirement planning, Q. What is usefulness...

Q. What is usefulness of materials requirement planning first to manufacturing operations? Materials requirement planning (MRP I) is an inventory control system that gives an a

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd