Common defects - bituminous roads:

Cracks can be filled with a bitumen emulsion. Wide cracks can be filled with premix sand asphalt.

If an overlay is to be laid on a cracked surface, it is necessary to ensure that the cracks do not travel upwards in the newly laid material. For this purpose, a Stress Absorbing Membrane (SAM) layer or a Stress Absorbing Membrane Interlayer (SAMI) is used. SAM is an application of polymer modified bitumen and covering it with aggregate chips. SAMI is similar to SAM but is followed by an overlay. SAMI can consist of polymer modified bitumen or bitumen impregnated geotextile.

When cracks are extensive, it is preferable to treat the area with a fog seal or slurry seal. The fog seal consists of spraying a bitumen emulsion followed by blinding with graded grit of size 3 mm and lower sizes. A slurry seal is a mixture of fine aggregate, Portland cement filler, bitumen emulsion and additional water, mixed in a mobile mixer and laid to a uniform thickness of 1.5 mm - 5 mm and rolled.

When the surface of the bituminous carpet is loose or has got oxidized, it is necessary to renew the surface by a thin course, consisting of surface dressing, premix carpet, mix- seal surfacing and a semi-dense carpet, depending upon the traffic and importance of the road. The renewal is done once in 3 to 5 years. The renewal helps in restoring the riding quality.

If the surface becomes fatty, a sprinkling of coarse sand or fine chippings and rolling will help.

If the surface becomes very smooth and slippery and has lost its skid-resistance properties, an application of surface dressing can restore its anti-skid properties.


Related Discussions:- Common defects - bituminous roads

Counter map, how will you determine the intrtvisibility of a point if the c...

how will you determine the intrtvisibility of a point if the counter map is given to you? explain by giving an exampe

Calculate time taken for consolidation in actual layer, A clay layer 5 m th...

A clay layer 5 m thick has double drainage. It was consolidated under a load of 127.5 kN/m2. The load is enhanced to 197.5 kN/m 2 . The coefficient of volume compressibility is 5.7

What is shock transmission unit in bridges, Q. What is Shock transmission u...

Q. What is Shock transmission unit in bridges? Shock transmission unit is fundamentally a device connecting separate structural units. It's characterized by its ability to tran

Acid test - tests on stones, Acid Test: This test is usually carried...

Acid Test: This test is usually carried out on sand stones to examine the presence of calcium carbonate that weakens the weather resisting quality. In this particular  test,

Chemistry, What is the difference between scale and sludge

What is the difference between scale and sludge

Explain the confined aquifer and piezometric surface, Explain the Confined ...

Explain the Confined Aquifer and Piezometric Surface Confined Aquifer Groundwater is confined by impervious geologic stratums on all sides. The water may be under pressure.

Solid mensuration, a street light is 15 ft directly above the curb. a 6 ft ...

a street light is 15 ft directly above the curb. a 6 ft man starts 10 ft down the street from the light and walks directly across the street which is 10 ft wide. when he reaches th

Define lead lag relationships - construction management, Define Lead Lag Re...

Define Lead Lag Relationships 1. A lead is when the successor task begins before the predecessor task is complete 2. A lag is when a successor task does not

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd