Common defects - bituminous roads:

Cracks can be filled with a bitumen emulsion. Wide cracks can be filled with premix sand asphalt.

If an overlay is to be laid on a cracked surface, it is necessary to ensure that the cracks do not travel upwards in the newly laid material. For this purpose, a Stress Absorbing Membrane (SAM) layer or a Stress Absorbing Membrane Interlayer (SAMI) is used. SAM is an application of polymer modified bitumen and covering it with aggregate chips. SAMI is similar to SAM but is followed by an overlay. SAMI can consist of polymer modified bitumen or bitumen impregnated geotextile.

When cracks are extensive, it is preferable to treat the area with a fog seal or slurry seal. The fog seal consists of spraying a bitumen emulsion followed by blinding with graded grit of size 3 mm and lower sizes. A slurry seal is a mixture of fine aggregate, Portland cement filler, bitumen emulsion and additional water, mixed in a mobile mixer and laid to a uniform thickness of 1.5 mm - 5 mm and rolled.

When the surface of the bituminous carpet is loose or has got oxidized, it is necessary to renew the surface by a thin course, consisting of surface dressing, premix carpet, mix- seal surfacing and a semi-dense carpet, depending upon the traffic and importance of the road. The renewal is done once in 3 to 5 years. The renewal helps in restoring the riding quality.

If the surface becomes fatty, a sprinkling of coarse sand or fine chippings and rolling will help.

If the surface becomes very smooth and slippery and has lost its skid-resistance properties, an application of surface dressing can restore its anti-skid properties.


Related Discussions:- Common defects - bituminous roads

Surveying, what are obstacles in chaining

what are obstacles in chaining

Meaning, i want the meaning of crete

i want the meaning of crete

Define equipments required for conducting uwmt, Define Equipments required ...

Define Equipments required for conducting UWMT? Equipments required for conducting UWMT are: Inspection Equipment: a) Electronic yoke with power cable b) Ground fault interr

Retaining wall, whether the wall has adequate sliding resistance

whether the wall has adequate sliding resistance

Pavements with Bitumen Emulsion, What is the rate of application of Prime c...

What is the rate of application of Prime coat over WBM

Designing of access ramps for drainage channels, Question Designing of ...

Question Designing of access ramps for drainage channels, why must direction of access ramps is sloping down on the way to downstream ? Answer In designing of access

What is thermodynamics?, Thermodynamics is concerned with the conversion of...

Thermodynamics is concerned with the conversion ofheat into mechanical energy or vice versa.  Heat usually generated through combustion of fossil fuelor nuclear reaction. Exa

Determine about the tensile stresses, Determine about the tensile stresses ...

Determine about the tensile stresses Unifody prestressed members designed for equal flexure in opposite directions,without permitting tensile stresses under working loads, requ

Alum, Aalumsk question #Minimum 100 words accepted#

Aalumsk question #Minimum 100 words accepted#

Coatings at the back faces of abutments, Q. Coatings at the back faces of a...

Q. Coatings at the back faces of abutments? There are many views on the necessity of application of protective coatings (can be in the form of two coats of paint) to the back f

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd