Common defects - bituminous roads:

Cracks can be filled with a bitumen emulsion. Wide cracks can be filled with premix sand asphalt.

If an overlay is to be laid on a cracked surface, it is necessary to ensure that the cracks do not travel upwards in the newly laid material. For this purpose, a Stress Absorbing Membrane (SAM) layer or a Stress Absorbing Membrane Interlayer (SAMI) is used. SAM is an application of polymer modified bitumen and covering it with aggregate chips. SAMI is similar to SAM but is followed by an overlay. SAMI can consist of polymer modified bitumen or bitumen impregnated geotextile.

When cracks are extensive, it is preferable to treat the area with a fog seal or slurry seal. The fog seal consists of spraying a bitumen emulsion followed by blinding with graded grit of size 3 mm and lower sizes. A slurry seal is a mixture of fine aggregate, Portland cement filler, bitumen emulsion and additional water, mixed in a mobile mixer and laid to a uniform thickness of 1.5 mm - 5 mm and rolled.

When the surface of the bituminous carpet is loose or has got oxidized, it is necessary to renew the surface by a thin course, consisting of surface dressing, premix carpet, mix- seal surfacing and a semi-dense carpet, depending upon the traffic and importance of the road. The renewal is done once in 3 to 5 years. The renewal helps in restoring the riding quality.

If the surface becomes fatty, a sprinkling of coarse sand or fine chippings and rolling will help.

If the surface becomes very smooth and slippery and has lost its skid-resistance properties, an application of surface dressing can restore its anti-skid properties.


Related Discussions:- Common defects - bituminous roads

Earth work in high embankments, Q. Earth work in high embankments? (a) ...

Q. Earth work in high embankments? (a) Borrow pits must not be dug close to telegraph poles, electric poles, level crossings, bridges a culverts, or within 800 meters of the bo

Distomat., write a note on distomat

write a note on distomat

Dissimilarity in methods of compaction, Question Are there any dissimil...

Question Are there any dissimilarity in methods of compaction between clayey soil material and sandy material ? Answer The three key actions of compaction are static

What is uniformly distributed surcharge, A retaining wall with a smooth ve...

A retaining wall with a smooth vertical back, 4.5 m high, retains a dry cohesionless backfill level with the top of the wall. γ = 18.6 kN/m 3 and φ = 30°. The backfill carries a u

Geodesy, what is the difference between geodesy and plane survey

what is the difference between geodesy and plane survey

Show the side clearance of pipes in trenches, Side clearance of pipes in tr...

Side clearance of pipes in trenches From the design point of view, it's predominant to minimize the width of pipe trenches due to thebelow reasons: (i)  Higher cost of exca

Jacking face for pipe-jacking, Ground settlement occurs ahead or behind the...

Ground settlement occurs ahead or behind the jacking face for pipe-jacking? It's reported by Lake (1992) that settlements are expected at ground surface at a distance of 1-2 ti

State the laws governing compaction of cohesion less soils, a) What are th...

a) What are the laws governing compaction of (i) cohesion less soils like sand and (ii) moderately cohesive soils like sandy clay ? b) To what compaction pressure does the

Doors, About Doors,windows&vendilators

About Doors,windows&vendilators

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd