Common defects - bituminous roads, Civil Engineering

Assignment Help:

Common defects - bituminous roads:

Cracks can be filled with a bitumen emulsion. Wide cracks can be filled with premix sand asphalt.

If an overlay is to be laid on a cracked surface, it is necessary to ensure that the cracks do not travel upwards in the newly laid material. For this purpose, a Stress Absorbing Membrane (SAM) layer or a Stress Absorbing Membrane Interlayer (SAMI) is used. SAM is an application of polymer modified bitumen and covering it with aggregate chips. SAMI is similar to SAM but is followed by an overlay. SAMI can consist of polymer modified bitumen or bitumen impregnated geotextile.

When cracks are extensive, it is preferable to treat the area with a fog seal or slurry seal. The fog seal consists of spraying a bitumen emulsion followed by blinding with graded grit of size 3 mm and lower sizes. A slurry seal is a mixture of fine aggregate, Portland cement filler, bitumen emulsion and additional water, mixed in a mobile mixer and laid to a uniform thickness of 1.5 mm - 5 mm and rolled.

When the surface of the bituminous carpet is loose or has got oxidized, it is necessary to renew the surface by a thin course, consisting of surface dressing, premix carpet, mix- seal surfacing and a semi-dense carpet, depending upon the traffic and importance of the road. The renewal is done once in 3 to 5 years. The renewal helps in restoring the riding quality.

If the surface becomes fatty, a sprinkling of coarse sand or fine chippings and rolling will help.

If the surface becomes very smooth and slippery and has lost its skid-resistance properties, an application of surface dressing can restore its anti-skid properties.


Related Discussions:- Common defects - bituminous roads

Holes in steel plates connecting to H-piles, Q. Holes in steel plates conne...

Q. Holes in steel plates connecting to H-piles There are two types of holes present in the steel plate associated to H-piles in the pile cap. The first type of holes is design

Determine the daylight factor of a room, QUESTION (a) What is the def...

QUESTION (a) What is the definition of Day light Factor (D)? (b) Determine the daylight factor of a room of an area of 100m 2 with an opening of 50m 2 of glazing. As wha

Zero energy building, This is our final year project can u suggest some tip...

This is our final year project can u suggest some tips to do well...

Calculate the amount of import or export, Calculate the Amount of Import or...

Calculate the Amount of Import or Export For the project site shown in Figure, the amount of import or export to bring the entire site to elevation 90-ft is most nearly:

Explain the hydraulic gradient, Explain the Hydraulic Gradient A measur...

Explain the Hydraulic Gradient A measurement of the movement of water over distances. Change in hydraulic head from one monitoring point to another.  i = ΔH/L  units are typ

Seasoning of timber, Seasoning of Timber It is a process by which moist...

Seasoning of Timber It is a process by which moisture content in a freshly cut tree is reduced to a appropriate level. The durability of timber is increased by doing so. The se

Non-distortional prestressing, Non-distortional Prestressing Concrete m...

Non-distortional Prestressing Concrete members deflect due to their own self weight. If prestressing force is applied in such a way that these deflections are eliminated due to

Advantages and dis advantages of timber, WHAT ARE THE ADVANTAGES AND DISADV...

WHAT ARE THE ADVANTAGES AND DISADVANTAGES OF TIMBER FOR CIVIL ENGINEERING

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd