Common defects - bituminous roads, Civil Engineering

Assignment Help:

Common defects - bituminous roads:

Cracks can be filled with a bitumen emulsion. Wide cracks can be filled with premix sand asphalt.

If an overlay is to be laid on a cracked surface, it is necessary to ensure that the cracks do not travel upwards in the newly laid material. For this purpose, a Stress Absorbing Membrane (SAM) layer or a Stress Absorbing Membrane Interlayer (SAMI) is used. SAM is an application of polymer modified bitumen and covering it with aggregate chips. SAMI is similar to SAM but is followed by an overlay. SAMI can consist of polymer modified bitumen or bitumen impregnated geotextile.

When cracks are extensive, it is preferable to treat the area with a fog seal or slurry seal. The fog seal consists of spraying a bitumen emulsion followed by blinding with graded grit of size 3 mm and lower sizes. A slurry seal is a mixture of fine aggregate, Portland cement filler, bitumen emulsion and additional water, mixed in a mobile mixer and laid to a uniform thickness of 1.5 mm - 5 mm and rolled.

When the surface of the bituminous carpet is loose or has got oxidized, it is necessary to renew the surface by a thin course, consisting of surface dressing, premix carpet, mix- seal surfacing and a semi-dense carpet, depending upon the traffic and importance of the road. The renewal is done once in 3 to 5 years. The renewal helps in restoring the riding quality.

If the surface becomes fatty, a sprinkling of coarse sand or fine chippings and rolling will help.

If the surface becomes very smooth and slippery and has lost its skid-resistance properties, an application of surface dressing can restore its anti-skid properties.


Related Discussions:- Common defects - bituminous roads

Find out load carrying capacity, Q.for ISMB200 having 6.70 m span simply su...

Q.for ISMB200 having 6.70 m span simply supported so find out load carrying capacity.

State the problem and phases of site investigation, State the Problem and p...

State the Problem and phases of site investigation The site investigation is to be performed to obtain the solution for the following problems: i)  Foundation problems ii

What is sedimentation tank, Q. What is Sedimentation tank ? This is a p...

Q. What is Sedimentation tank ? This is a process in which the water is passed through bases or tanks in which the velocity of water is so reduced or water is given a period of

Verify the earth pressure at rest, A retaining wall, 6 m high, retains dry ...

A retaining wall, 6 m high, retains dry sand with an angle of friction of 30° and unit weight of 16.2 kN/m 3 . Verify the earth pressure at rest. If the water table rises to the to

Fixed end moments, For fixed beam(say for example fixed with a point load a...

For fixed beam(say for example fixed with a point load at midspan) how did we end up getting P*L/8...??

Water or hydraulic horsepower (whp), Water Or Hydraulic Horsepower (whp) ...

Water Or Hydraulic Horsepower (whp) The work performed by a pump is a function of the head added by the pump (h A ), the flow rate required (Q) and the mass of the fluid (accou

Rb slab, #questionshow me picture..

#questionshow me picture..

Distomat, Ask quetypes of stion #Minimum 100 words accepted#

Ask quetypes of stion #Minimum 100 words accepted#

Cement, List the ingredients of cement And their functions

List the ingredients of cement And their functions

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd