Common defects - bituminous roads, Civil Engineering

Assignment Help:

Common defects - bituminous roads:

Cracks can be filled with a bitumen emulsion. Wide cracks can be filled with premix sand asphalt.

If an overlay is to be laid on a cracked surface, it is necessary to ensure that the cracks do not travel upwards in the newly laid material. For this purpose, a Stress Absorbing Membrane (SAM) layer or a Stress Absorbing Membrane Interlayer (SAMI) is used. SAM is an application of polymer modified bitumen and covering it with aggregate chips. SAMI is similar to SAM but is followed by an overlay. SAMI can consist of polymer modified bitumen or bitumen impregnated geotextile.

When cracks are extensive, it is preferable to treat the area with a fog seal or slurry seal. The fog seal consists of spraying a bitumen emulsion followed by blinding with graded grit of size 3 mm and lower sizes. A slurry seal is a mixture of fine aggregate, Portland cement filler, bitumen emulsion and additional water, mixed in a mobile mixer and laid to a uniform thickness of 1.5 mm - 5 mm and rolled.

When the surface of the bituminous carpet is loose or has got oxidized, it is necessary to renew the surface by a thin course, consisting of surface dressing, premix carpet, mix- seal surfacing and a semi-dense carpet, depending upon the traffic and importance of the road. The renewal is done once in 3 to 5 years. The renewal helps in restoring the riding quality.

If the surface becomes fatty, a sprinkling of coarse sand or fine chippings and rolling will help.

If the surface becomes very smooth and slippery and has lost its skid-resistance properties, an application of surface dressing can restore its anti-skid properties.


Related Discussions:- Common defects - bituminous roads

WATER SUPPLY, THE DESIGN PERIOD AVERAGE DAILY DEMAND CALCULATE. THE DESIGN ...

THE DESIGN PERIOD AVERAGE DAILY DEMAND CALCULATE. THE DESIGN DEMAND FOR THE WATER RETICULATION OR DISTRIBUTION PERIOD.

Timber, defects in timber?

defects in timber?

Dense Bituminous Macadam, What is DBM?Why use DBM where other binder course...

What is DBM?Why use DBM where other binder courses are available?What is composition and advantages of using DBM?

Main principle of post-grouting for mini-piles, Question What is main p...

Question What is main principle of post-grouting for mini-piles? Answer During course of post-grouting , a tube with a hole at its base is lowered into pile and g

What is the long term effects - concrete, What is the Long Term Effects - C...

What is the Long Term Effects - Concrete Long term effects of  loads on structures consider all the effects including creep and shrinkage.

Define mechanical tool for underwater inspection of bridge, Define Mechanic...

Define Mechanical tool for underwater inspection of bridge? Mechanical devices that involves a Schmidt Test Hammer for computing concrete surface hardness, and rotary coring eq

Construction management, pert disadvantages of software support, datacolle...

pert disadvantages of software support, datacollection , interpretation of results issues

Structure analysis, In a cantilever truss it is very essential to find out ...

In a cantilever truss it is very essential to find out the reactions before analyzing it.

Duration activity for cast-in-place foundation formwork, A concrete contrac...

A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF

Abrassion test., abrasion test is conducted to find what

abrasion test is conducted to find what

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd