Common defects - bituminous roads:

Cracks can be filled with a bitumen emulsion. Wide cracks can be filled with premix sand asphalt.

If an overlay is to be laid on a cracked surface, it is necessary to ensure that the cracks do not travel upwards in the newly laid material. For this purpose, a Stress Absorbing Membrane (SAM) layer or a Stress Absorbing Membrane Interlayer (SAMI) is used. SAM is an application of polymer modified bitumen and covering it with aggregate chips. SAMI is similar to SAM but is followed by an overlay. SAMI can consist of polymer modified bitumen or bitumen impregnated geotextile.

When cracks are extensive, it is preferable to treat the area with a fog seal or slurry seal. The fog seal consists of spraying a bitumen emulsion followed by blinding with graded grit of size 3 mm and lower sizes. A slurry seal is a mixture of fine aggregate, Portland cement filler, bitumen emulsion and additional water, mixed in a mobile mixer and laid to a uniform thickness of 1.5 mm - 5 mm and rolled.

When the surface of the bituminous carpet is loose or has got oxidized, it is necessary to renew the surface by a thin course, consisting of surface dressing, premix carpet, mix- seal surfacing and a semi-dense carpet, depending upon the traffic and importance of the road. The renewal is done once in 3 to 5 years. The renewal helps in restoring the riding quality.

If the surface becomes fatty, a sprinkling of coarse sand or fine chippings and rolling will help.

If the surface becomes very smooth and slippery and has lost its skid-resistance properties, an application of surface dressing can restore its anti-skid properties.


Related Discussions:- Common defects - bituminous roads

Rectangular tie, how would you perform a rantangular tie ,using an optical ...

how would you perform a rantangular tie ,using an optical square

Determine the station and elevation of turning point, A -3.00% grade inters...

A -3.00% grade intersects a +1.25% grade at Sta. 85+80 and elevation 210.00 ft.  A 350-ft vertical curve connects the two grades.  Determine the station and elevation of turning po

Explain p trap, Q. Explain P Trap? Trap is a depressed or bent sanitary...

Q. Explain P Trap? Trap is a depressed or bent sanitary fittings which always remains full of water it is water seal. Its functions are to prevent passage of foul air or gas

Diving operation - preparation for underwater inspection, Define Diving Ope...

Define Diving Operation - Preparation for underwater inspection? Use of experienced divers trained and screened by a reputed commercial diving school is critical for successful

Estimate the activity durations - construction management, Estimate the Act...

Estimate the Activity Durations The total labor cost for emergency bridge rehabilitation on an interstate highway is $5,716,440.  The average crew-hour cost is $15,879 for this

Good surface regularity for sub-base in concrete pavement, Q. Good surface ...

Q. Good surface regularity for sub-base in concrete pavement? Surfaces of sub-base material for concrete carriageway must be built in a regular manner due to the following reas

Disparity between fasteners, Question What is major disparity between ...

Question What is major disparity between fasteners , bolts and screws ? Answer Fastener is a broad term to explain something that is used as a restraint for holding

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd