Cleaning and greasing of steel sliding bearings, Civil Engineering

Assignment Help:

Cleaning and greasing of steel sliding bearings :

Following equipments are required for greasing of steel sliding bearings:

1. Jacks (50 ton capacity) - 2 nos.

2. Hard wooden packing below and above jack

3. Grease graphite Grade 3 conforming to IS:508

4. Kerosene or released black oil for cleaning

5. 6 mm thick steel scrapers

6. Mortar pan

7. Cotton waste

Greasing of sliding bearings can be undertaken under traffic with issue of caution order and line protection for temporary works as per provision of IRPWM.

Lifting of girder should be restricted to 8 to 10 mm only, ensuring that the bearing strip does not get lifted over locking strip and guide strip to avoid creep of girder in logitudinal and lateral direction. For lifting, it is not necessary to break the track. Only loosening of fish bolts and dog spikes over a small length on both sides of the pier is sufficient. Only one end of the girder should be lifted at a time and steel scraper inserted between bearing strip and base plate to remove old grease dust and dirt. The contact surface is cleaned with oil and grease applied. Girder is then lowered back over the base plate. Time required for all these activities is approximately 15 to 20 minutes.


Related Discussions:- Cleaning and greasing of steel sliding bearings

Determine the permissible stresses in steel, Permissible Stresses in Steel ...

Permissible Stresses in Steel As per the Indian code, the permissible stresses in the tendons at the time of initial prestressing should not exceed 80% of the characteristic t

Revit , how to use the revit program

how to use the revit program

Calculate distance between top and bottom chord of the truss, A W12x58 memb...

A W12x58 member, which comprises a vertical member in a truss span, is subjected to a factored axial compressive force of 163 kips.  The W12x58 section is oriented such that the st

Calculate the square foot of contact area for the formwork, A concrete crew...

A concrete crew will use the available steel form panels measuring 2'-6" wide x 4'-0" high to construct a 40'-6" long by 3'-2" high by 1'-6" wide concrete knee wall. The square

Calculate equivalent uniform annual cost for the excavator, Calculate Equiv...

Calculate Equivalent Uniform Annual Cost for the Excavator An earthwork contractor is considering the purchase of a new excavator.  Based on 10% interest, the equivalent unifor

Soil testing, what is black cotton soil in dry condition

what is black cotton soil in dry condition

Mini projcts in diaster management.., any new innovative metods to protct b...

any new innovative metods to protct building from disater

AAA, Ask question #MiAAAAnimum 100 wordAs accepted#

Ask question #MiAAAAnimum 100 wordAs accepted#

Diving operation - preparation for underwater inspection, Define Diving Ope...

Define Diving Operation - Preparation for underwater inspection? Use of experienced divers trained and screened by a reputed commercial diving school is critical for successful

Wet mix, how to design wet mix

how to design wet mix

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd