Cleaning and greasing of rocker, Civil Engineering

Assignment Help:

Cleaning and greasing of Rocker & Roller bearings of open web through girders : In case of standard open web through girders, no separate jacking arrangement is required as the end cross girders are designed and provided with stiffener and pad plate for provision of jack for lifting. Gap between bottom of cross girder and top of bed block is about 600 mm, hence any type of jack of 100 ton to 200 ton capacity can easily be used for lifting. In case of non standard spans, the end cross girder requires adequate strengthening or special jacking beam below the bottom boom. The equipments required in this case are same as for sliding bearing except that the jacks of higher capacity (100 ton to 200 ton) and wire rope with turn buckle arrangement for holding the free end are required.

Greasing of rocker and roller bearing should be carried out under traffic block under the supervision of an official not below the rank of ADEN/ABE. Following precautions and preliminary arrangements are required:

1. Ensure tightness of rivets connecting end cross girder and end panel point of truss.

2. Provide hard wooden packing below the end cross girder to support the girder in case of failure of jacks. This should be done at three places to prevent tilting of this girder.

3. Remove fish plates and loosen dog spikes of rail over adjacent spans to avoid overloading the jack on account of weight of adjoining span and stiffness of the track.

4. If trolley refuge is connected to both spans on any pier, loosen the bolted connection of adjoining span to avoid overloading of jack and damage to the trolley refuge.

5. While lifting the fixed end, the other end being free, the girder is likely to creep longitudinally. To prevent this, provide hard wood packing
between the ends of girder on pier and between girder and the ballast wall on abutment.

6. Jacks should be kept in working order and tested to 1.5 times the load they are expected to lift. Keep one spare jack as stand by.

7. During lifting of girder, precaution should be taken to prevent creep of rail.


Related Discussions:- Cleaning and greasing of rocker

Explain the equalization basins - hydraulic system, Equalization Basins - H...

Equalization Basins - Hydraulic System For influent flow to publicly owned treatment works (POTWs), flow rates may be excessive for short or long durations, especially in combi

Soil particles for geotechnical design, Question Will it worthwhile to ...

Question Will it worthwhile to take out tests on particle density of soil particles for geotechnical design? Answer Particle density of soils is definite by ratio of

Doors and windows, important considerations in case of doors and windows

important considerations in case of doors and windows

State about the pre-tensioned concrete beam, State about the pre-tensioned ...

State about the pre-tensioned concrete beam A pre-tensioned concrete beam, 200 mm wide and 300 mm deep, is prestressed by straight wires carrying an initial force of 150 kN at

Water absorption test - tests on stones, Water Absorption Test: In t...

Water Absorption Test: In this test cube specimen weighing approximate 50 grams are prepared and the test is carried out in the steps following: 1.    Note down the weigh

Describe the boussinesq theory, A raft of size 4 m-square carries a load of...

A raft of size 4 m-square carries a load of 200 kN/m 2 . Verify the vertical stress increment at a point 4 m below the centre of the loaded area using Boussinesq's theory. Compare

Kerb overflow weirs – horizontal bars vs. vertical bars, Q. Kerb overflow w...

Q. Kerb overflow weirs – horizontal bars vs. vertical bars? Overflow weirs must be provided for steep roads (longitudinal gradient>5%), flat roads (longitudinal gradient Ess

Explain dissolved impurities in water, Q. Explain Dissolved Impurities in w...

Q. Explain Dissolved Impurities in water? The impurities which are caused by the action of water and water forming Acids with organic matter and carbon dio

Sucker deck principle for changeable depth bridge decks, Question What is t...

Question What is the sucker deck principle for changeable depth bridge decks ? Answer For a variable depth bridge deck, depth of continuous multi-span bridge deck is greate

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd