Cleaning and greasing of rocker, Civil Engineering

Assignment Help:

Cleaning and greasing of Rocker & Roller bearings of open web through girders : In case of standard open web through girders, no separate jacking arrangement is required as the end cross girders are designed and provided with stiffener and pad plate for provision of jack for lifting. Gap between bottom of cross girder and top of bed block is about 600 mm, hence any type of jack of 100 ton to 200 ton capacity can easily be used for lifting. In case of non standard spans, the end cross girder requires adequate strengthening or special jacking beam below the bottom boom. The equipments required in this case are same as for sliding bearing except that the jacks of higher capacity (100 ton to 200 ton) and wire rope with turn buckle arrangement for holding the free end are required.

Greasing of rocker and roller bearing should be carried out under traffic block under the supervision of an official not below the rank of ADEN/ABE. Following precautions and preliminary arrangements are required:

1. Ensure tightness of rivets connecting end cross girder and end panel point of truss.

2. Provide hard wooden packing below the end cross girder to support the girder in case of failure of jacks. This should be done at three places to prevent tilting of this girder.

3. Remove fish plates and loosen dog spikes of rail over adjacent spans to avoid overloading the jack on account of weight of adjoining span and stiffness of the track.

4. If trolley refuge is connected to both spans on any pier, loosen the bolted connection of adjoining span to avoid overloading of jack and damage to the trolley refuge.

5. While lifting the fixed end, the other end being free, the girder is likely to creep longitudinally. To prevent this, provide hard wood packing
between the ends of girder on pier and between girder and the ballast wall on abutment.

6. Jacks should be kept in working order and tested to 1.5 times the load they are expected to lift. Keep one spare jack as stand by.

7. During lifting of girder, precaution should be taken to prevent creep of rail.


Related Discussions:- Cleaning and greasing of rocker

What is the density index of the natural soil, A sand at a borrow pit is de...

A sand at a borrow pit is determined to have an  in-situ dry unit weight of 18.4 kN/m 3 . Laboratory tests indicate the maximum and  minimum unit weight values of 19.6 kN/m 3 and

Diffraction analysis in determining wave force on piles, The Morison equati...

The Morison equation vs. diffraction analysis in determining wave force on piles The choice between Morison's equation and diffraction analysis in determining the wave forces o

Tension members, Tension Members: You have learnt about the Standard s...

Tension Members: You have learnt about the Standard specification for structural steel and various types of structural steel rolled sections. Different types of loads, stresse

Explain the secondary treatment for wastewater, Explain the Secondary treat...

Explain the Secondary treatment for wastewater Secondary Treatment: to remove soluble BOD that escapes the primary treatment and to provide added removal of suspended solids.

Calculate the most probable value, The most probable value of the following...

The most probable value of the following observations on the same angle (35º 17' 42" ; 35º 17' 38" ; 35º 18' 00" ; 35º 17'; 22"; 35º 17' 42");  is most nearly:   35º 17' 40.8

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd