Change order management, Other Management

Assignment Help:

Change Order Management

In previous section we learnt that incentives motivate and penalties keep a check for faults that occur in a project. In this section we will understand about a change order management.

A change order is order for work that is added to or deleted from the original  scope  of  work  in  a  contract,  which  alters  the  original  contract amount and/or completion date. A contractor?s claim for such an alteration due to a work perceived by him as additional work remains as a claim until the change order is resolved. A claim is a potential source of dispute. Hence resolution of change order situations knowledgably, fairly and promptly benefits both owner and contractor.

Change  order  is  a  component  of  the  change  management  process  in contract management. The change management process should enable implementation of changes in a system in a controlled manner by following a predefined framework/model. Change order management is hence a critical aspect of any construction job.

The rights of a contractor to a change order arise from the contract. If the contractor?s claim is not consistent with the contract, it will be denied, unless you admit it by oversight.

Project construction contracts always incorporate a Changes clause which provides allows you to order extra work without invalidating the contract or make changes to the existing work by altering, adding to or deducting from the work, with the contract sum.

The reasons this change clause is needed are:

  • Impossibility of perfect drawings and specifications: A fundamental truth in the construction industry is that no design can be made perfect.
  • Impractical risk allocations: The fundamental principle of risk allocation is to assign each risk to the party who is best able to control, manage or absorb that risk, which is the way to achieve maximum efficiency and economy. When contract for construction is taken up by a general contractor, his tendency will be to shift the risks to subcontractors and so on down the line leading to improper risk allocation.
  • Contractor-suggested changes: In many project contracts, value engineering proposals from contractor should be encouraged by owner.
  • Owner-suggested changes: You may discover obstacles or possible efficiencies that require them to deviate from the original plan.

Other than the above reasons, incorrectly estimated work or failure to meet commitments can lead to claims by contractor. Examples are:

  • Unforeseen adverse site conditions or actual site conditions being more adverse than what is mentioned in the contract.
  • Failure to make the site available at the time and in the condition required by the contract.
  • Failure to grant, or delay in granting, legitimate time extensions.
  • Unreasonable or mistaken inspection.

Although you can unilaterally order that changes be made, there is a commensurate duty on you, to make adjustments in the contract sum or contract time. Hence changes provisions in contract should typically provide methods for making these adjustments.

Changes in contract sum or contract time are made on the basis of negotiations between owner and contractor. The basis can be:

  • Unit prices for specific items of work.
  • Recognised mark-ups for contractor?s work and subcontractor?s work.

Related Discussions:- Change order management

Derivatives section of a bank treasury, Question 1 Discuss the various act...

Question 1 Discuss the various activities carried out by commercial banks these days that are common to clients of both commercial banks and development banks Question 2 What

Define creativity, Question 1 What are special events? Give example. Wh...

Question 1 What are special events? Give example. What is meant by vision statement? What are the components of a good vision statement? Question 2 Every bidding doc

Examine the nature of people-organisation relationship, QUESTION 1 Crit...

QUESTION 1 Critically examine the nature of people-organisation relationship. Why is it important to distinguish between the ‘intent' and the ‘implementation' of management dec

Managing variability, McM Cog is a supplier of industrial parts.  Most orde...

McM Cog is a supplier of industrial parts.  Most orders are received at a call center. The call center currently has 10 phone lines total, i.e., a maximum of 10 callers may be in t

Factors affecting materials handling system, Factors Affecting Materials Ha...

Factors Affecting Materials Handling System  The followings four factors material handling system: Production  System: There  are two  basic  types  of production systems.

An emerging model of responsive governance, The Public Sector Administratio...

The Public Sector Administration has undergone a process of evolutionary reform from the Traditional Public administration to NPM and now to an emerging model of responsive govern

Problems in ordering, Problems in Ordering, Procurement and Receipt: O...

Problems in Ordering, Procurement and Receipt: Ordering and procurement of periodicals are very much inconvenienced due to different locations of their publishers. If the  lib

Discuss how you will formulate the treasury policy, Question 1 The NCDEX t...

Question 1 The NCDEX trading system provides a fully automated screen based trading for futures commodities on basis of nationwide online monitoring and surveillance mechanism. De

Elements of an effective ergonomic program, Question: (a) What, accord...

Question: (a) What, according to you, are the essential elements of an effective ergonomic program? State the reasons for establishing such a program at a place of work. (b

Types of reference work - library management, Types of Reference work: ...

Types of Reference work: a) The conservative approach is based on the fact that the users should be instructed on how to use books and libraries rather than on delivery of inf

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd