Change order management, Other Management

Assignment Help:

Change Order Management

In previous section we learnt that incentives motivate and penalties keep a check for faults that occur in a project. In this section we will understand about a change order management.

A change order is order for work that is added to or deleted from the original  scope  of  work  in  a  contract,  which  alters  the  original  contract amount and/or completion date. A contractor?s claim for such an alteration due to a work perceived by him as additional work remains as a claim until the change order is resolved. A claim is a potential source of dispute. Hence resolution of change order situations knowledgably, fairly and promptly benefits both owner and contractor.

Change  order  is  a  component  of  the  change  management  process  in contract management. The change management process should enable implementation of changes in a system in a controlled manner by following a predefined framework/model. Change order management is hence a critical aspect of any construction job.

The rights of a contractor to a change order arise from the contract. If the contractor?s claim is not consistent with the contract, it will be denied, unless you admit it by oversight.

Project construction contracts always incorporate a Changes clause which provides allows you to order extra work without invalidating the contract or make changes to the existing work by altering, adding to or deducting from the work, with the contract sum.

The reasons this change clause is needed are:

  • Impossibility of perfect drawings and specifications: A fundamental truth in the construction industry is that no design can be made perfect.
  • Impractical risk allocations: The fundamental principle of risk allocation is to assign each risk to the party who is best able to control, manage or absorb that risk, which is the way to achieve maximum efficiency and economy. When contract for construction is taken up by a general contractor, his tendency will be to shift the risks to subcontractors and so on down the line leading to improper risk allocation.
  • Contractor-suggested changes: In many project contracts, value engineering proposals from contractor should be encouraged by owner.
  • Owner-suggested changes: You may discover obstacles or possible efficiencies that require them to deviate from the original plan.

Other than the above reasons, incorrectly estimated work or failure to meet commitments can lead to claims by contractor. Examples are:

  • Unforeseen adverse site conditions or actual site conditions being more adverse than what is mentioned in the contract.
  • Failure to make the site available at the time and in the condition required by the contract.
  • Failure to grant, or delay in granting, legitimate time extensions.
  • Unreasonable or mistaken inspection.

Although you can unilaterally order that changes be made, there is a commensurate duty on you, to make adjustments in the contract sum or contract time. Hence changes provisions in contract should typically provide methods for making these adjustments.

Changes in contract sum or contract time are made on the basis of negotiations between owner and contractor. The basis can be:

  • Unit prices for specific items of work.
  • Recognised mark-ups for contractor?s work and subcontractor?s work.

Related Discussions:- Change order management

Control and flexibility in contracts, Control and Flexibility in Contracts ...

Control and Flexibility in Contracts Contracts form the backbone of project management today. Project management techniques have developed in response to severe pressures such

Discuss the meaning and advantages of containerization, Question 1 Logi...

Question 1 Logistics is one of the key areas in international business. Explain the meaning and objectives of logistics Question 2 Which is the main transport document

Agency method - periodicals procurement, Agency Method: The alternativ...

Agency Method: The alternative to direct ordering with publishers is to acquire the periodicals through a duly appointed subscription agent. A subscription agent is a person o

Many authorities have criticised npm, QUESTION 1 Successful privatizati...

QUESTION 1 Successful privatization rests on government's ability to manage the process of change. Discuss the institutional requirements for successful privatization and the r

State five objectives that the ppa 2006 aims to achieve, QUESTION The P...

QUESTION The Public Procurement Act 2006 (PPA 2006) is a modern procurement legislation based on UNCITRAL Model Law. PPA 2006 was enacted in 2006 and came into force in 2008. A

Paragraph writing management assignment, Situation A caller asked "Wh...

Situation A caller asked "What is the policy on a manager unlocking one of their employees desks after hours in search of something? Is this an invasion of privacy? What righ

What are the challenges that managers face, Question 1: What are the ch...

Question 1: What are the challenges that managers face in implementing successful change? - challenges that managers face in implementing successful change Question 2:

Case let, If you were one of the other foremen, what could you do to make R...

If you were one of the other foremen, what could you do to make Rajinder’s transition easier?

Arranging personnel , Arranging Personnel: Planning for periodicals / ...

Arranging Personnel: Planning for periodicals / serials selection should also cover the personnel or human factor. The people involved in the selection process are the librari

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd