Change order management, Other Management

Assignment Help:

Change Order Management

In previous section we learnt that incentives motivate and penalties keep a check for faults that occur in a project. In this section we will understand about a change order management.

A change order is order for work that is added to or deleted from the original  scope  of  work  in  a  contract,  which  alters  the  original  contract amount and/or completion date. A contractor?s claim for such an alteration due to a work perceived by him as additional work remains as a claim until the change order is resolved. A claim is a potential source of dispute. Hence resolution of change order situations knowledgably, fairly and promptly benefits both owner and contractor.

Change  order  is  a  component  of  the  change  management  process  in contract management. The change management process should enable implementation of changes in a system in a controlled manner by following a predefined framework/model. Change order management is hence a critical aspect of any construction job.

The rights of a contractor to a change order arise from the contract. If the contractor?s claim is not consistent with the contract, it will be denied, unless you admit it by oversight.

Project construction contracts always incorporate a Changes clause which provides allows you to order extra work without invalidating the contract or make changes to the existing work by altering, adding to or deducting from the work, with the contract sum.

The reasons this change clause is needed are:

  • Impossibility of perfect drawings and specifications: A fundamental truth in the construction industry is that no design can be made perfect.
  • Impractical risk allocations: The fundamental principle of risk allocation is to assign each risk to the party who is best able to control, manage or absorb that risk, which is the way to achieve maximum efficiency and economy. When contract for construction is taken up by a general contractor, his tendency will be to shift the risks to subcontractors and so on down the line leading to improper risk allocation.
  • Contractor-suggested changes: In many project contracts, value engineering proposals from contractor should be encouraged by owner.
  • Owner-suggested changes: You may discover obstacles or possible efficiencies that require them to deviate from the original plan.

Other than the above reasons, incorrectly estimated work or failure to meet commitments can lead to claims by contractor. Examples are:

  • Unforeseen adverse site conditions or actual site conditions being more adverse than what is mentioned in the contract.
  • Failure to make the site available at the time and in the condition required by the contract.
  • Failure to grant, or delay in granting, legitimate time extensions.
  • Unreasonable or mistaken inspection.

Although you can unilaterally order that changes be made, there is a commensurate duty on you, to make adjustments in the contract sum or contract time. Hence changes provisions in contract should typically provide methods for making these adjustments.

Changes in contract sum or contract time are made on the basis of negotiations between owner and contractor. The basis can be:

  • Unit prices for specific items of work.
  • Recognised mark-ups for contractor?s work and subcontractor?s work.

Related Discussions:- Change order management

Care and preservation of library materials, CARE AND PRESERVATION OF LIBRAR...

CARE AND PRESERVATION OF LIBRARY MATERIALS: As should not be shelved too tightly nor too loosely. The former damages the binding en other books are forceful inserted and  the

Define the service providers under foreign trade policy, Question A ) Disc...

Question A ) Discuss the changes in the composition of India's export and import since 1991. How has this affected Balance of payment situation of India? Question B ) Trading

Discuss the significance of world heritage sites, QUESTION World herita...

QUESTION World heritage sites are identified as sites of outstanding global values that should be preserved for all humanity. Sites will be preserved for future generations and

Executing the agreement , Executing the agreement  A successful negotia...

Executing the agreement  A successful negotiation leads to the signing of a contract by the parties after incorporating all the mutual agreements reached during negotiations. E

Importance of media management, Question 1 Well thought sponsorship wil...

Question 1 Well thought sponsorship will be a powerful positioning device in the hands of Public Relations Practitioners. Discuss. Question 2 "It is more difficult to f

Back charging, B ack charging: Back charging the contractor arises ...

B ack charging: Back charging the contractor arises when a certain scope of work included in the contract is either not carried out or carried out defectively. When such an

Debt management policy, ‘The overall objective of debt management is to min...

‘The overall objective of debt management is to minimise the cost of borrowing to the organisation.' Required: I. Explain factors which need to be taken into account, other t

Biology, What are the characteristics of Protozoa?

What are the characteristics of Protozoa?

Introduction to quality, Definition of Quality Quality  can  be  simply...

Definition of Quality Quality  can  be  simply  defined  as  the  measure  of  excellence.  When  a product is manufactured, the customer always looks for its quality, features

Definition, what is the definition for stock exchange

what is the definition for stock exchange

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd