Change order management, Other Management

Assignment Help:

Change Order Management

In previous section we learnt that incentives motivate and penalties keep a check for faults that occur in a project. In this section we will understand about a change order management.

A change order is order for work that is added to or deleted from the original  scope  of  work  in  a  contract,  which  alters  the  original  contract amount and/or completion date. A contractor?s claim for such an alteration due to a work perceived by him as additional work remains as a claim until the change order is resolved. A claim is a potential source of dispute. Hence resolution of change order situations knowledgably, fairly and promptly benefits both owner and contractor.

Change  order  is  a  component  of  the  change  management  process  in contract management. The change management process should enable implementation of changes in a system in a controlled manner by following a predefined framework/model. Change order management is hence a critical aspect of any construction job.

The rights of a contractor to a change order arise from the contract. If the contractor?s claim is not consistent with the contract, it will be denied, unless you admit it by oversight.

Project construction contracts always incorporate a Changes clause which provides allows you to order extra work without invalidating the contract or make changes to the existing work by altering, adding to or deducting from the work, with the contract sum.

The reasons this change clause is needed are:

  • Impossibility of perfect drawings and specifications: A fundamental truth in the construction industry is that no design can be made perfect.
  • Impractical risk allocations: The fundamental principle of risk allocation is to assign each risk to the party who is best able to control, manage or absorb that risk, which is the way to achieve maximum efficiency and economy. When contract for construction is taken up by a general contractor, his tendency will be to shift the risks to subcontractors and so on down the line leading to improper risk allocation.
  • Contractor-suggested changes: In many project contracts, value engineering proposals from contractor should be encouraged by owner.
  • Owner-suggested changes: You may discover obstacles or possible efficiencies that require them to deviate from the original plan.

Other than the above reasons, incorrectly estimated work or failure to meet commitments can lead to claims by contractor. Examples are:

  • Unforeseen adverse site conditions or actual site conditions being more adverse than what is mentioned in the contract.
  • Failure to make the site available at the time and in the condition required by the contract.
  • Failure to grant, or delay in granting, legitimate time extensions.
  • Unreasonable or mistaken inspection.

Although you can unilaterally order that changes be made, there is a commensurate duty on you, to make adjustments in the contract sum or contract time. Hence changes provisions in contract should typically provide methods for making these adjustments.

Changes in contract sum or contract time are made on the basis of negotiations between owner and contractor. The basis can be:

  • Unit prices for specific items of work.
  • Recognised mark-ups for contractor?s work and subcontractor?s work.

Related Discussions:- Change order management

Sponsorship, Hi, i need to motivate a sponsorship program to exco as part o...

Hi, i need to motivate a sponsorship program to exco as part of my marketing assignment. I have no idea how to do this. Can you help?

Outline kolb''s learning styles model, QUESTION Read the extract below ...

QUESTION Read the extract below and answer the questions that follow There is general consensus among educators that all learners are not the same. However, a single school

Project team activities, P roject team activities There  are  seven  s...

P roject team activities There  are  seven  step  procedures  which  the  organisation  can  use  to introduce the project team activities as a management strategy. The proced

Jewetts rules - british museum cataloguing rules, Jewetts Rules - British m...

Jewetts Rules - British museum cataloguing rules: Jewett, Charles Coffin. Smithsonian report on the construction of catalogues of libraries and their publication by means of s

Ppp needs to satisfy suitable parameters to be acceptable, QUESTION 2 a...

QUESTION 2 a) Due to severe budgetary constraints that is facing the central government, public sector projects are being resorted to on a public-private basis. Explain what is

Nature of documents - library classification, Nature of Documents: The...

Nature of Documents: The problem of collection, storage and retrieval of documents has been complicated by the following factors: The steady growth in the output of various

Categories of information in social sciences, Categories of Information in ...

Categories of Information in Social Sciences  It would be useful, particularly in social sciences, to group information into three categories:  •  Statistical Information

Facility and building management, sir,How to prepare the facility managemen...

sir,How to prepare the facility management exam assignment?

Planning and design for a new property, Question 1: Show the importance...

Question 1: Show the importance of facilities planning and design with regards to: (i) Land (ii) Esthetics (iii) Space (iv) Buildings (v) Innovation (vi) Acces

Dealer library plan and standing order, Dealer Library Plan (DLP): Und...

Dealer Library Plan (DLP): Under this plan, as agreement is reached between the library and the publishers or a group of publishers whereby the publishers send books as soon a

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd