M/s XYZ Ltd manufactures a product “PLVS” at its plant at Meerut, the maximum capacity of which is 200 units per month. Details of raw materials which go into the making of 1 units of “PLVS” are provided to you below:-
Sl.No Raw material description Standard Qty per finished unit (No) Standard purchase price per unit (Rs. 00)
1 A 1 6
2. B 2 5
3. C 3 4
4. D 4 3
5. E 5 2
6. F 6 1

Standard fixed overheads are Rs. 20,00,000/- per month whereas the standard variable overhead rate has been estimated as equal to Rs.1,400/- per unit of finished good.

You are required to compute the
a) Standard cost of the product.
b) Compute the production volume variance in case the company produces and sells only 100 units of finished goods in the concerned month.
c) Compute the usage and material price variances considering the following actual data (actual production and sale: 100 units)

Related Discussions:- case study

Risk Analysis, how would I find assistance with such toics as: probability ...

how would I find assistance with such toics as: probability assessment methods, risk modeling, stochatic dominance and multi-attribute methods?

Composite materials - rotational stability equations, Rotational stability ...

Rotational stability equations  The torque T applied to any rigid vehicle with moving c.g. is in general determined by T = ∂HVE/∂t|E + uvE ×MugE where E is the inertial a

Biology, Any Biology Modeling software?

Any Biology Modeling software?

Heat transfer, Q. 1 A 50 cm diameter pipeline in the Arctic Carries hot oi...

Q. 1 A 50 cm diameter pipeline in the Arctic Carries hot oil at 30 0C and exposed to a coefficient surrounding temperature of -20 0C. Special powder insulation 5 cm thick surround

Integrated circuits, Integrated circuits: Integrated circuits, or IC's,...

Integrated circuits: Integrated circuits, or IC's, have changed the entire electronics industry. Before IC's were developed, all electronic circuits consisted of individual (d

Time value of money-inflation-interest rate-opportunity cost, Time Value of...

Time Value of Money Consider your cheese steak hoagie business. Assume that Phillies will win another World Series, and your business will be hired to serve a party that will

Statistical Quality control, Pls solve the problem 13-7 in Statistical Qual...

Pls solve the problem 13-7 in Statistical Quality control by Montgomery

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd