Carry out resource levelling for equipment resource, Operation Research

Assignment Help:

Teesside Construction is developing a schedule for a major building project to start in 04/01/2011 in Middlesbrough, UK. The project manager has identified major activities of the project, their dependency and resources needed to run each activity. Appendix 1 provides information about the project, which includes project logic (activity links and their relationship - FS, SS, and SF), activity durations, resource allocation and WBS. Appendix 2 provides definition on different activity relationships.

You have been asked to perform the following planning and scheduling processes with the help of Microsoft Project 2007.

A: CPM & WBS

1.  Draw a Gantt-Chart and CPM network for the project. Calculate EST, EFT, LST, LFT and TF based on As Soon as Possible (ASAP) method and identify critical path. Gantt-Chat should show WBS of the project (use A4 or A3 sheet as required) 

2.  Draw manually  the hierarchy of WBS for  the project  (must include  Level 1,  Level 2, Level 3 and Level 4).use MS Visio or other IT software. You can also draw manually and scan it. 

3.  Explain why identification of the critical path is important? Also comment on the changes to the Critical Path, if the project is developed using As Late as Possible (ALAP) method. (max one page)

B: Resources Histograms

1.  Produce resource histograms for  all  the resources  using ASAP method. Identify  and  discuss  the maximum  resources needed  for this project per day and per month.

2.  If As Late as Possible (ALAP) method is used. Will the number of resource identified in question B.1 changes, explain.

C: Resource Smoothing and Resource Levelling

1.  Produce and draw smoothed resource histograms for the skilled labour resources. Do not use automatic smoothening

2.  Carry-out resource levelling  for equipment resource and discuss how activities might be delayed beyond LST to cater for the limits on equipment resources as a result of levelling.

Consider resource pool for equipment resources as 8 units per day. (use A3 sheet for each histogram, max one page for discussion)

3.  Explain and discuss the process of resource levelling. (max one page)

E: Cost Analysis

1.  Calculate the cost of each activity in the project (level 3). Consider the standard cost of a skilled labour as £10/hr, unskilled labour as £15/hr and equipment as £45/hr.

2.  Identify and analyse those activities  which are expensive, for example Structures; Envelope & claddings; Mechanical & electrical services etc. (max one page)

3.  Draw cumulative cost-time curve for each resources and for the project. Comment on the cost profile. (use A4 or A3 sheet as required)


Related Discussions:- Carry out resource levelling for equipment resource

LPP, USE SIMPLE METHOD TO SOLVE THE FOLLOWING LPP MAXIMISE Z=4X1+10X2 SUBJE...

USE SIMPLE METHOD TO SOLVE THE FOLLOWING LPP MAXIMISE Z=4X1+10X2 SUBJECT TO CONSTRAINS, 2X1+X2 2X1+5X2 2X1+3X2 X1, X2>0

Linear programming , the application areas of linear programming

the application areas of linear programming

LPP, A paper mill produces two grades of paper viz., X and Y. Because of ra...

A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper i

Theoretical framework, Ask questiAvatars are virtual characters that can be...

Ask questiAvatars are virtual characters that can be used as representatives of a company that is using the Internet as a distribution channel. For instance, avatars can be used as

Demerits of range - measure of dispersion , Demerits  of Range a.It g...

Demerits  of Range a.It gives  importance  to the  two  extreme  values and is very much affected by the extreme items. b.The range  provides  no information  about the  st

Analytical and decision- making skills, This assessment aims to provide stu...

This assessment aims to provide students with the opportunity to hone their analytical and decision- making skills. It also aims to help students develop their ability to think cre

Application of operation reserch., how i make project report on "applicatio...

how i make project report on "application of or".i want help from you.can you give me idea to complete this report..

Big M method, Maximize p = (3)x + 2y subject to 2x + y 3x + 4y >= 12

Maximize p = (3)x + 2y subject to 2x + y 3x + 4y >= 12

process technolgy, 1 strategic implication of product and process decision...

1 strategic implication of product and process decisions 2 process planning and design 3 work measurement

Machine tabulation, Machine  Tabulation This methods  of tabulating i...

Machine  Tabulation This methods  of tabulating information  is generally used in  case of extensive  large scale  surveys. Mechanical sorting and tabulating equipments and su

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd