Carry out resource levelling for equipment resource, Operation Research

Assignment Help:

Teesside Construction is developing a schedule for a major building project to start in 04/01/2011 in Middlesbrough, UK. The project manager has identified major activities of the project, their dependency and resources needed to run each activity. Appendix 1 provides information about the project, which includes project logic (activity links and their relationship - FS, SS, and SF), activity durations, resource allocation and WBS. Appendix 2 provides definition on different activity relationships.

You have been asked to perform the following planning and scheduling processes with the help of Microsoft Project 2007.

A: CPM & WBS

1.  Draw a Gantt-Chart and CPM network for the project. Calculate EST, EFT, LST, LFT and TF based on As Soon as Possible (ASAP) method and identify critical path. Gantt-Chat should show WBS of the project (use A4 or A3 sheet as required) 

2.  Draw manually  the hierarchy of WBS for  the project  (must include  Level 1,  Level 2, Level 3 and Level 4).use MS Visio or other IT software. You can also draw manually and scan it. 

3.  Explain why identification of the critical path is important? Also comment on the changes to the Critical Path, if the project is developed using As Late as Possible (ALAP) method. (max one page)

B: Resources Histograms

1.  Produce resource histograms for  all  the resources  using ASAP method. Identify  and  discuss  the maximum  resources needed  for this project per day and per month.

2.  If As Late as Possible (ALAP) method is used. Will the number of resource identified in question B.1 changes, explain.

C: Resource Smoothing and Resource Levelling

1.  Produce and draw smoothed resource histograms for the skilled labour resources. Do not use automatic smoothening

2.  Carry-out resource levelling  for equipment resource and discuss how activities might be delayed beyond LST to cater for the limits on equipment resources as a result of levelling.

Consider resource pool for equipment resources as 8 units per day. (use A3 sheet for each histogram, max one page for discussion)

3.  Explain and discuss the process of resource levelling. (max one page)

E: Cost Analysis

1.  Calculate the cost of each activity in the project (level 3). Consider the standard cost of a skilled labour as £10/hr, unskilled labour as £15/hr and equipment as £45/hr.

2.  Identify and analyse those activities  which are expensive, for example Structures; Envelope & claddings; Mechanical & electrical services etc. (max one page)

3.  Draw cumulative cost-time curve for each resources and for the project. Comment on the cost profile. (use A4 or A3 sheet as required)


Related Discussions:- Carry out resource levelling for equipment resource

Types of correlation - correlation & regression analysis, Types of Correlat...

Types of Correlation 1. Positive Correlation : When the values  of two variables move  in the  same direction .e.  when an increase in  the values  of one  variables  is ass

Degrees of freedom, Determining Degrees of Freedom   One of the prer...

Determining Degrees of Freedom   One of the prerequisites for using chi square test is that we should calculate the number of degrees of freedom for the contingency table. T

Solved a.q, Solve the following Linear Programming Problem using Simple met...

Solve the following Linear Programming Problem using Simple method. Maximize Z= 3x1 + 2X2 Subject to the constraints: X1+ X2 = 4 X1 - X2 = 2 X1, X2 = 0

Phase of operation research, The scientific method in O R study generall...

The scientific method in O R study generally involves the followings three phases: 1. Judgment phase, 2. Research phase 3. Action phase

Sequential sampling -sampling decisons, Sequential Samplin The previou...

Sequential Samplin The previous  has shown  that the sampling  units  were drawn  prior  to the drawing of the actual   sample  and has  a fixed  size. But the  sequential  sa

Institutional Characteristics - information resources, Institutional Charac...

Institutional Characteristics:  An approach to an understanding of the fields of interest of individuals to be served and of the organisation as a whole could begin by acquiri

Linear Programming, A paper mill produces two grades of paper viz., X & Y. ...

A paper mill produces two grades of paper viz., X & Y. Because of raw material restrictions, it cannot produce more 400 tons of grade X paper & 300 tons of grade Y paper in a week.

Bibliography format - report writing presentation , Bibliography Format ...

Bibliography Format a. Introduction : Bibliographies  tell  readers  where they can  locate  information  about  a topic. It is a list of sources  of information  for a repo

WEITING MODEL(QUEUING), CONSIDER A BARBER SHOP WITH ONE CHAIR, ONE BARBER A...

CONSIDER A BARBER SHOP WITH ONE CHAIR, ONE BARBER AND NO ROOM FOR CUSTOMER TO WAIT. IF THE CHAIR IS EMPTY WHEN THE CUSTOMER ARRIVES,HE ENTER THE SHOP AND HIS HAIR CUT BEGINS. IF TH

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd