Carry out resource levelling for equipment resource, Operation Research

Assignment Help:

Teesside Construction is developing a schedule for a major building project to start in 04/01/2011 in Middlesbrough, UK. The project manager has identified major activities of the project, their dependency and resources needed to run each activity. Appendix 1 provides information about the project, which includes project logic (activity links and their relationship - FS, SS, and SF), activity durations, resource allocation and WBS. Appendix 2 provides definition on different activity relationships.

You have been asked to perform the following planning and scheduling processes with the help of Microsoft Project 2007.

A: CPM & WBS

1.  Draw a Gantt-Chart and CPM network for the project. Calculate EST, EFT, LST, LFT and TF based on As Soon as Possible (ASAP) method and identify critical path. Gantt-Chat should show WBS of the project (use A4 or A3 sheet as required) 

2.  Draw manually  the hierarchy of WBS for  the project  (must include  Level 1,  Level 2, Level 3 and Level 4).use MS Visio or other IT software. You can also draw manually and scan it. 

3.  Explain why identification of the critical path is important? Also comment on the changes to the Critical Path, if the project is developed using As Late as Possible (ALAP) method. (max one page)

B: Resources Histograms

1.  Produce resource histograms for  all  the resources  using ASAP method. Identify  and  discuss  the maximum  resources needed  for this project per day and per month.

2.  If As Late as Possible (ALAP) method is used. Will the number of resource identified in question B.1 changes, explain.

C: Resource Smoothing and Resource Levelling

1.  Produce and draw smoothed resource histograms for the skilled labour resources. Do not use automatic smoothening

2.  Carry-out resource levelling  for equipment resource and discuss how activities might be delayed beyond LST to cater for the limits on equipment resources as a result of levelling.

Consider resource pool for equipment resources as 8 units per day. (use A3 sheet for each histogram, max one page for discussion)

3.  Explain and discuss the process of resource levelling. (max one page)

E: Cost Analysis

1.  Calculate the cost of each activity in the project (level 3). Consider the standard cost of a skilled labour as £10/hr, unskilled labour as £15/hr and equipment as £45/hr.

2.  Identify and analyse those activities  which are expensive, for example Structures; Envelope & claddings; Mechanical & electrical services etc. (max one page)

3.  Draw cumulative cost-time curve for each resources and for the project. Comment on the cost profile. (use A4 or A3 sheet as required)


Related Discussions:- Carry out resource levelling for equipment resource

Evaluate a product from the view point of quality, This assignment requires...

This assignment requires you to evaluate a product from the view point of quality, both quality of design (as perceived by the user) and quality of conformance. To ensure that we a

Uncertainly, Uncertainly : There is a great uncertainly about economic a...

Uncertainly : There is a great uncertainly about economic and general environment. With economic growth uncertainty is also growing's. this makes each decisions costlier

#title.L.L.p, #use the simple method to solve the following L.P.P. Maximi...

#use the simple method to solve the following L.P.P. Maximize Z =4X1 +10X2 subject to constraints, 2X1 +X2 2X1+5X2 2X1 +3X2 X1,X2 > 0

Operation research techniques, Select five Operations Research techniques a...

Select five Operations Research techniques and describe in detail the real world application of such techniques in business decision making.

Sope, sope of operations research in a detailed manner

sope of operations research in a detailed manner

Application of the chi square test - hypothesis testing, Application of the...

Application of the chi Square Test   The  chi square distribution  has a number of applications are given  below: a.Chi Square test of goodness of fit. b.Chi square te

Simplex method, Solve the following Linear Programming Problem using Simple...

Solve the following Linear Programming Problem using Simple method. Maximize Z= 3x1 + 2X2 Subject to the constraints: X1+ X2 = 4 X1 - X2 = 2 X1, X2 = 0

Degrees of freedom, Determining Degrees of Freedom   One of the prer...

Determining Degrees of Freedom   One of the prerequisites for using chi square test is that we should calculate the number of degrees of freedom for the contingency table. T

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd