Carry out resource levelling for equipment resource, Operation Research

Assignment Help:

Teesside Construction is developing a schedule for a major building project to start in 04/01/2011 in Middlesbrough, UK. The project manager has identified major activities of the project, their dependency and resources needed to run each activity. Appendix 1 provides information about the project, which includes project logic (activity links and their relationship - FS, SS, and SF), activity durations, resource allocation and WBS. Appendix 2 provides definition on different activity relationships.

You have been asked to perform the following planning and scheduling processes with the help of Microsoft Project 2007.

A: CPM & WBS

1.  Draw a Gantt-Chart and CPM network for the project. Calculate EST, EFT, LST, LFT and TF based on As Soon as Possible (ASAP) method and identify critical path. Gantt-Chat should show WBS of the project (use A4 or A3 sheet as required) 

2.  Draw manually  the hierarchy of WBS for  the project  (must include  Level 1,  Level 2, Level 3 and Level 4).use MS Visio or other IT software. You can also draw manually and scan it. 

3.  Explain why identification of the critical path is important? Also comment on the changes to the Critical Path, if the project is developed using As Late as Possible (ALAP) method. (max one page)

B: Resources Histograms

1.  Produce resource histograms for  all  the resources  using ASAP method. Identify  and  discuss  the maximum  resources needed  for this project per day and per month.

2.  If As Late as Possible (ALAP) method is used. Will the number of resource identified in question B.1 changes, explain.

C: Resource Smoothing and Resource Levelling

1.  Produce and draw smoothed resource histograms for the skilled labour resources. Do not use automatic smoothening

2.  Carry-out resource levelling  for equipment resource and discuss how activities might be delayed beyond LST to cater for the limits on equipment resources as a result of levelling.

Consider resource pool for equipment resources as 8 units per day. (use A3 sheet for each histogram, max one page for discussion)

3.  Explain and discuss the process of resource levelling. (max one page)

E: Cost Analysis

1.  Calculate the cost of each activity in the project (level 3). Consider the standard cost of a skilled labour as £10/hr, unskilled labour as £15/hr and equipment as £45/hr.

2.  Identify and analyse those activities  which are expensive, for example Structures; Envelope & claddings; Mechanical & electrical services etc. (max one page)

3.  Draw cumulative cost-time curve for each resources and for the project. Comment on the cost profile. (use A4 or A3 sheet as required)


Related Discussions:- Carry out resource levelling for equipment resource

C++ programs, C++ code for assignment problem

C++ code for assignment problem

Biographies, Biographies, Handbooks and Dictionaries: Dictionaries: ...

Biographies, Handbooks and Dictionaries: Dictionaries: Dictionaries  primarily deal with all aspects of  words from  proper definitions to spellings. Webster's Third Ne

Answer, A paper mill products two grade of paper viz., X & Y. Because of ra...

A paper mill products two grade of paper viz., X & Y. Because of raw material restriction, it cannot produce more than 400 tons of grade X paper & 300 tons of grade Y paper in a we

Competitive models, These models have been developed to establish a trade ...

These models have been developed to establish a trade off between costs of providing and the waiting time of a customer in the queuing system. Constructing a model entails desc

Making decision - hypothesis testing, Making Decision Lastly a deci...

Making Decision Lastly a decision  should  be arrived as to whether the null  hypothesis is  to be accepted  or rejected. In  this regard the value  of the test  statistic

LPP, a paper mill produce two grades of paper viz., X and Y. because of raw...

a paper mill produce two grades of paper viz., X and Y. because of raw material restrictions, it cannot produce more than 400 tona of grade X and 300 tons of grade Yin a week. ther

Reports - classification of documents, Reports: Report literature is a...

Reports: Report literature is an important primary source of information, particularly  for a research library. This new  medium for communication of information came into bei

Simplex, Maximize Z = 2x - 7y subject -2x + 3y = 3 4x + 5y >= 10 6x + 7y 4...

Maximize Z = 2x - 7y subject -2x + 3y = 3 4x + 5y >= 10 6x + 7y 4x + 8y >= 5

Policies, POLICIES, NORMS AND STANDARDS: Information source; building,...

POLICIES, NORMS AND STANDARDS: Information source; building, an important function of the library, should be based on sound policies and programmes.  The basic question of

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd