Carry out resource levelling for equipment resource, Operation Research

Assignment Help:

Teesside Construction is developing a schedule for a major building project to start in 04/01/2011 in Middlesbrough, UK. The project manager has identified major activities of the project, their dependency and resources needed to run each activity. Appendix 1 provides information about the project, which includes project logic (activity links and their relationship - FS, SS, and SF), activity durations, resource allocation and WBS. Appendix 2 provides definition on different activity relationships.

You have been asked to perform the following planning and scheduling processes with the help of Microsoft Project 2007.

A: CPM & WBS

1.  Draw a Gantt-Chart and CPM network for the project. Calculate EST, EFT, LST, LFT and TF based on As Soon as Possible (ASAP) method and identify critical path. Gantt-Chat should show WBS of the project (use A4 or A3 sheet as required) 

2.  Draw manually  the hierarchy of WBS for  the project  (must include  Level 1,  Level 2, Level 3 and Level 4).use MS Visio or other IT software. You can also draw manually and scan it. 

3.  Explain why identification of the critical path is important? Also comment on the changes to the Critical Path, if the project is developed using As Late as Possible (ALAP) method. (max one page)

B: Resources Histograms

1.  Produce resource histograms for  all  the resources  using ASAP method. Identify  and  discuss  the maximum  resources needed  for this project per day and per month.

2.  If As Late as Possible (ALAP) method is used. Will the number of resource identified in question B.1 changes, explain.

C: Resource Smoothing and Resource Levelling

1.  Produce and draw smoothed resource histograms for the skilled labour resources. Do not use automatic smoothening

2.  Carry-out resource levelling  for equipment resource and discuss how activities might be delayed beyond LST to cater for the limits on equipment resources as a result of levelling.

Consider resource pool for equipment resources as 8 units per day. (use A3 sheet for each histogram, max one page for discussion)

3.  Explain and discuss the process of resource levelling. (max one page)

E: Cost Analysis

1.  Calculate the cost of each activity in the project (level 3). Consider the standard cost of a skilled labour as £10/hr, unskilled labour as £15/hr and equipment as £45/hr.

2.  Identify and analyse those activities  which are expensive, for example Structures; Envelope & claddings; Mechanical & electrical services etc. (max one page)

3.  Draw cumulative cost-time curve for each resources and for the project. Comment on the cost profile. (use A4 or A3 sheet as required)


Related Discussions:- Carry out resource levelling for equipment resource

Solve the following linear programming graphically, Problem based on graphi...

Problem based on graphical solution of a given LPP when feasible region is bounded. 1.    Solve the following linear programming graphically; Maximize and minimize z = 60x+

LInear Programming, - A paper mill produces two grades of paper viz., X an...

- A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y pape

Linear programming, 3. A paper mill produces two grades of paper viz., X an...

3. A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y pape

What do you understand by the term operations research, Question : (a) ...

Question : (a) (i) What do you understand by the term "operations research"? (ii) Discuss three common operations research models. (b) Self-service at the university c

Describe states-transitions and transition rate, Customers arrive to a supe...

Customers arrive to a super market according to a Poisson process with intensity V = ½  per minute. The supermarket has two counters, that use a common queue. Counter 1 is always o

Sing test- hypothesis testing, SING TEST The sign test  is the simples...

SING TEST The sign test  is the simplest  of the  parametric  tests. Its name comes  from the  fact  that it is based  on the direction ( or sings  for  pluses or minuses ) of

What do you understand by the term queueing theory, Question: (a) (i) W...

Question: (a) (i) What do you understand by the term ‘queueing theory'? Give two real life examples to illustrate your answer. (ii) Outline the five components involved in

Linear programming, A paper mill produces two grades of paper viz., X and Y...

A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper i

Sources of hypothesis - hypothesis testing, Sources of Hypothesis Hyp...

Sources of Hypothesis Hypothesis  may be developed from  various  sources. Some  of the important  sources are  the  followings: 1. A Hypothesis  Arises from  Intuition

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd