Carry out resource levelling for equipment resource, Operation Research

Assignment Help:

Teesside Construction is developing a schedule for a major building project to start in 04/01/2011 in Middlesbrough, UK. The project manager has identified major activities of the project, their dependency and resources needed to run each activity. Appendix 1 provides information about the project, which includes project logic (activity links and their relationship - FS, SS, and SF), activity durations, resource allocation and WBS. Appendix 2 provides definition on different activity relationships.

You have been asked to perform the following planning and scheduling processes with the help of Microsoft Project 2007.

A: CPM & WBS

1.  Draw a Gantt-Chart and CPM network for the project. Calculate EST, EFT, LST, LFT and TF based on As Soon as Possible (ASAP) method and identify critical path. Gantt-Chat should show WBS of the project (use A4 or A3 sheet as required) 

2.  Draw manually  the hierarchy of WBS for  the project  (must include  Level 1,  Level 2, Level 3 and Level 4).use MS Visio or other IT software. You can also draw manually and scan it. 

3.  Explain why identification of the critical path is important? Also comment on the changes to the Critical Path, if the project is developed using As Late as Possible (ALAP) method. (max one page)

B: Resources Histograms

1.  Produce resource histograms for  all  the resources  using ASAP method. Identify  and  discuss  the maximum  resources needed  for this project per day and per month.

2.  If As Late as Possible (ALAP) method is used. Will the number of resource identified in question B.1 changes, explain.

C: Resource Smoothing and Resource Levelling

1.  Produce and draw smoothed resource histograms for the skilled labour resources. Do not use automatic smoothening

2.  Carry-out resource levelling  for equipment resource and discuss how activities might be delayed beyond LST to cater for the limits on equipment resources as a result of levelling.

Consider resource pool for equipment resources as 8 units per day. (use A3 sheet for each histogram, max one page for discussion)

3.  Explain and discuss the process of resource levelling. (max one page)

E: Cost Analysis

1.  Calculate the cost of each activity in the project (level 3). Consider the standard cost of a skilled labour as £10/hr, unskilled labour as £15/hr and equipment as £45/hr.

2.  Identify and analyse those activities  which are expensive, for example Structures; Envelope & claddings; Mechanical & electrical services etc. (max one page)

3.  Draw cumulative cost-time curve for each resources and for the project. Comment on the cost profile. (use A4 or A3 sheet as required)


Related Discussions:- Carry out resource levelling for equipment resource

Li, line drawn as Y=C+1075x, when x was 2, and y was 239, given that y inte...

line drawn as Y=C+1075x, when x was 2, and y was 239, given that y intercept was 11. calculate the residualon..

Simplex method, Solve the following Linear Programming Problem using Simple...

Solve the following Linear Programming Problem using Simplex method. Maximize Z= 3x1 + 2X2 Subject to the constraints: X1+ X2 = 4 X1 - X2 = 2 X1, X2 = 0

Research and development - information generation process, Research and Dev...

Research and Development: All intellectual activities consciously pursued and systematically completed generate useful information. Research (also Research and Development) is

Markert reseach, The Upjohn Company, based in Kalamazoo, Michigan, manufact...

The Upjohn Company, based in Kalamazoo, Michigan, manufactures and markets pharmaceuticals and health-related products. With more than 19,000 employees and distribution in over 30

Medical industry payments to physicians, Medical Industry Payments to Physi...

Medical Industry Payments to Physicians The relationships between physicians and medical related companies in the United States, generally acknowledged to be familiar given th

Linear Programming, A paper mill produces two grades of paper viz., X & Y. ...

A paper mill produces two grades of paper viz., X & Y. Because of raw material restrictions, it cannot produce more 400 tons of grade X paper & 300 tons of grade Y paper in a week.

Sampling decision, Normal 0 false false false EN-IN X...

Normal 0 false false false EN-IN X-NONE X-NONE

Network problem, Consider the following network where the value on each arc...

Consider the following network where the value on each arc represents the capacity of that arc. Use the augmenting path algorithm to find the value of the maximum flow from node 1

ASSIGNMENT PROBLEM, . Explain in brief the phases of Operations Research. 5...

. Explain in brief the phases of Operations Research. 5 +5 = 10 marks (200 - 250 words each) Q3. Solve the following Linear Programming Problem using Simple method. Maximize Z= 3

Multiple objectives- sampling decisions, Multiple  Objective s The sam...

Multiple  Objective s The sample  may vary according  to the  objective of the research. There  may several objectives  of marketing  research so the  sample  size  may vary a

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd