Carry out resource levelling for equipment resource, Operation Research

Assignment Help:

Teesside Construction is developing a schedule for a major building project to start in 04/01/2011 in Middlesbrough, UK. The project manager has identified major activities of the project, their dependency and resources needed to run each activity. Appendix 1 provides information about the project, which includes project logic (activity links and their relationship - FS, SS, and SF), activity durations, resource allocation and WBS. Appendix 2 provides definition on different activity relationships.

You have been asked to perform the following planning and scheduling processes with the help of Microsoft Project 2007.

A: CPM & WBS

1.  Draw a Gantt-Chart and CPM network for the project. Calculate EST, EFT, LST, LFT and TF based on As Soon as Possible (ASAP) method and identify critical path. Gantt-Chat should show WBS of the project (use A4 or A3 sheet as required) 

2.  Draw manually  the hierarchy of WBS for  the project  (must include  Level 1,  Level 2, Level 3 and Level 4).use MS Visio or other IT software. You can also draw manually and scan it. 

3.  Explain why identification of the critical path is important? Also comment on the changes to the Critical Path, if the project is developed using As Late as Possible (ALAP) method. (max one page)

B: Resources Histograms

1.  Produce resource histograms for  all  the resources  using ASAP method. Identify  and  discuss  the maximum  resources needed  for this project per day and per month.

2.  If As Late as Possible (ALAP) method is used. Will the number of resource identified in question B.1 changes, explain.

C: Resource Smoothing and Resource Levelling

1.  Produce and draw smoothed resource histograms for the skilled labour resources. Do not use automatic smoothening

2.  Carry-out resource levelling  for equipment resource and discuss how activities might be delayed beyond LST to cater for the limits on equipment resources as a result of levelling.

Consider resource pool for equipment resources as 8 units per day. (use A3 sheet for each histogram, max one page for discussion)

3.  Explain and discuss the process of resource levelling. (max one page)

E: Cost Analysis

1.  Calculate the cost of each activity in the project (level 3). Consider the standard cost of a skilled labour as £10/hr, unskilled labour as £15/hr and equipment as £45/hr.

2.  Identify and analyse those activities  which are expensive, for example Structures; Envelope & claddings; Mechanical & electrical services etc. (max one page)

3.  Draw cumulative cost-time curve for each resources and for the project. Comment on the cost profile. (use A4 or A3 sheet as required)


Related Discussions:- Carry out resource levelling for equipment resource

LLP, A paper mill produces two grades of paper viz., X and Y. Because of ra...

A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper i

Inherent forces fomenting conflicts of interest, Inherent forces fomenting ...

Inherent forces fomenting conflicts of interest Several forces have coalesced to increase the incidence of conflicts of interest in the medical industry: the vertical integrat

Explain decision making process, Explain Decision Making Process. Deci...

Explain Decision Making Process. Decision Making Process: A good decision can only be prepared as a result of a rational decision making process. The different stages of the

CORE TECHNOLOGY TO WATCH IN FUTURE, AI TECHNOLOGY''S CURRENT AND POTENTIAL ...

AI TECHNOLOGY''S CURRENT AND POTENTIAL FUTURE APPLICATIONS

project management , Project Management Your  data need to be orga...

Project Management Your  data need to be organized in such  a way that  access to them  is both  quick  and accurate. In  achieving  this a good qualitative analysis progra

Research, Regression line drawn as Y=C+1075x, when x was 2, and y was 239, ...

Regression line drawn as Y=C+1075x, when x was 2, and y was 239, given that y intercept was 11. calculate the residual#

Purchasing power of customers, This is determined by disposable personal ...

This is determined by disposable personal income( personal income minus direct taxes and other deductions ). Some people suggest the use of discretionary income in place of

Method of calculation of mode - measure of central tendency , Method of cal...

Method of calculation of Mode Calculation  of Mode  Individual  series: For determining  mode count the  number of times the  various  values  repeat  themselves and the  va

Sampling decision, Normal 0 false false false EN-IN X...

Normal 0 false false false EN-IN X-NONE X-NONE

Replacement, an electric company which generates and distributes electricit...

an electric company which generates and distributes electricity conducted a study on the life of poles. tha appropriate life data are given in the following table: years after inst

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd