Carry out resource levelling for equipment resource, Operation Research

Assignment Help:

Teesside Construction is developing a schedule for a major building project to start in 04/01/2011 in Middlesbrough, UK. The project manager has identified major activities of the project, their dependency and resources needed to run each activity. Appendix 1 provides information about the project, which includes project logic (activity links and their relationship - FS, SS, and SF), activity durations, resource allocation and WBS. Appendix 2 provides definition on different activity relationships.

You have been asked to perform the following planning and scheduling processes with the help of Microsoft Project 2007.

A: CPM & WBS

1.  Draw a Gantt-Chart and CPM network for the project. Calculate EST, EFT, LST, LFT and TF based on As Soon as Possible (ASAP) method and identify critical path. Gantt-Chat should show WBS of the project (use A4 or A3 sheet as required) 

2.  Draw manually  the hierarchy of WBS for  the project  (must include  Level 1,  Level 2, Level 3 and Level 4).use MS Visio or other IT software. You can also draw manually and scan it. 

3.  Explain why identification of the critical path is important? Also comment on the changes to the Critical Path, if the project is developed using As Late as Possible (ALAP) method. (max one page)

B: Resources Histograms

1.  Produce resource histograms for  all  the resources  using ASAP method. Identify  and  discuss  the maximum  resources needed  for this project per day and per month.

2.  If As Late as Possible (ALAP) method is used. Will the number of resource identified in question B.1 changes, explain.

C: Resource Smoothing and Resource Levelling

1.  Produce and draw smoothed resource histograms for the skilled labour resources. Do not use automatic smoothening

2.  Carry-out resource levelling  for equipment resource and discuss how activities might be delayed beyond LST to cater for the limits on equipment resources as a result of levelling.

Consider resource pool for equipment resources as 8 units per day. (use A3 sheet for each histogram, max one page for discussion)

3.  Explain and discuss the process of resource levelling. (max one page)

E: Cost Analysis

1.  Calculate the cost of each activity in the project (level 3). Consider the standard cost of a skilled labour as £10/hr, unskilled labour as £15/hr and equipment as £45/hr.

2.  Identify and analyse those activities  which are expensive, for example Structures; Envelope & claddings; Mechanical & electrical services etc. (max one page)

3.  Draw cumulative cost-time curve for each resources and for the project. Comment on the cost profile. (use A4 or A3 sheet as required)


Related Discussions:- Carry out resource levelling for equipment resource

Operation reaserch, A paper mill produces two grades of paper viz., X and Y...

A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper i

Precentile - measure of central tendency , Normal 0 false fal...

Normal 0 false false false EN-IN X-NONE X-NONE

Que, #queSix Operators are to be assigned to five jobs with the cost of ass...

#queSix Operators are to be assigned to five jobs with the cost of assignment in Rs. given in the matrix below. Determine the optimal assignment. Which operator will have no assign

One sample runs test - hypothesis testing, ONE SAMPLE  RUNS  TEST A ...

ONE SAMPLE  RUNS  TEST A number of  methods have been  developed fro  judging the randomness of samples on the basis of  the order in which  teh observations  are taken. It is

Vogel approximation methods, This method is more  systematic and orderly th...

This method is more  systematic and orderly than least cost method. Here penalties for each column and row of the transportation table are determined, and the row  or  column with

Differentiate among descriptive and inferential analysis o, Question 1 ...

Question 1 A) Differentiate among descriptive and inferential analysis of data B) Describe with examples various measures of Central Tendency Question 2 The chi-square

Observation and data collection - research phases, Observation and Data Col...

Observation and Data Collection for Better Understanding of the Problem: Many times actual observations by trained observers at the scene of operation may be difficult and da

Modi method, find optimal solution for a 3*4 matrix 42 27 24 35 46 37 32 3...

find optimal solution for a 3*4 matrix 42 27 24 35 46 37 32 32 40 40 30 35 using modi method

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd