Carry out resource levelling for equipment resource, Operation Research

Assignment Help:

Teesside Construction is developing a schedule for a major building project to start in 04/01/2011 in Middlesbrough, UK. The project manager has identified major activities of the project, their dependency and resources needed to run each activity. Appendix 1 provides information about the project, which includes project logic (activity links and their relationship - FS, SS, and SF), activity durations, resource allocation and WBS. Appendix 2 provides definition on different activity relationships.

You have been asked to perform the following planning and scheduling processes with the help of Microsoft Project 2007.

A: CPM & WBS

1.  Draw a Gantt-Chart and CPM network for the project. Calculate EST, EFT, LST, LFT and TF based on As Soon as Possible (ASAP) method and identify critical path. Gantt-Chat should show WBS of the project (use A4 or A3 sheet as required) 

2.  Draw manually  the hierarchy of WBS for  the project  (must include  Level 1,  Level 2, Level 3 and Level 4).use MS Visio or other IT software. You can also draw manually and scan it. 

3.  Explain why identification of the critical path is important? Also comment on the changes to the Critical Path, if the project is developed using As Late as Possible (ALAP) method. (max one page)

B: Resources Histograms

1.  Produce resource histograms for  all  the resources  using ASAP method. Identify  and  discuss  the maximum  resources needed  for this project per day and per month.

2.  If As Late as Possible (ALAP) method is used. Will the number of resource identified in question B.1 changes, explain.

C: Resource Smoothing and Resource Levelling

1.  Produce and draw smoothed resource histograms for the skilled labour resources. Do not use automatic smoothening

2.  Carry-out resource levelling  for equipment resource and discuss how activities might be delayed beyond LST to cater for the limits on equipment resources as a result of levelling.

Consider resource pool for equipment resources as 8 units per day. (use A3 sheet for each histogram, max one page for discussion)

3.  Explain and discuss the process of resource levelling. (max one page)

E: Cost Analysis

1.  Calculate the cost of each activity in the project (level 3). Consider the standard cost of a skilled labour as £10/hr, unskilled labour as £15/hr and equipment as £45/hr.

2.  Identify and analyse those activities  which are expensive, for example Structures; Envelope & claddings; Mechanical & electrical services etc. (max one page)

3.  Draw cumulative cost-time curve for each resources and for the project. Comment on the cost profile. (use A4 or A3 sheet as required)


Related Discussions:- Carry out resource levelling for equipment resource

MODI method, explain the procedure of MODI method of finding solution throu...

explain the procedure of MODI method of finding solution through optimaly test.

Advantages of operations research, Operation Research may be regarded as a...

Operation Research may be regarded as a tool which is utilized to increase the effectiveness of the management decisions. O R is objective supplement to the subjective feeling

Game thoery, In a rectangular game, pay-off matrix of player A is as follow...

In a rectangular game, pay-off matrix of player A is as follows: i) Solve the game. ii) Write down the pay-off matrix of B and then, solve the game.

RJR NABISCO, WOULD YOU RECOMMEND FOCUS GROUPS OR SOME OTHER RESEARCH DESIGN...

WOULD YOU RECOMMEND FOCUS GROUPS OR SOME OTHER RESEARCH DESIGN IN THIS SITUATION

Demerits - correlation regression analysis, Demerits a.It cannot  be ...

Demerits a.It cannot  be used in  the case  of  bi variate distribution. b.If the  numbers  of items  are greater than say  30, the calculation becomes  tedious  and  requ

Expected value analysis, Profitable Casino Corp. (PCC) is a Harrah's wannab...

Profitable Casino Corp. (PCC) is a Harrah's wannabe, intent on mimicking Harrah's analytical marketing techniques.  For example, PCC issues virtually all gamers a PCC "Rewards" car

Determine the optimal assignment, Six Operators are to be assigned to five ...

Six Operators are to be assigned to five jobs with the cost of assignment in Rs. given in the matrix below. Determine the optimal assignment. Which operator will have no assignment

Closed loop, Write a note on tracing a closed loop. What are the characteri...

Write a note on tracing a closed loop. What are the characteristic features of a closed loop?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd