Carry out resource levelling for equipment resource, Operation Research

Assignment Help:

Teesside Construction is developing a schedule for a major building project to start in 04/01/2011 in Middlesbrough, UK. The project manager has identified major activities of the project, their dependency and resources needed to run each activity. Appendix 1 provides information about the project, which includes project logic (activity links and their relationship - FS, SS, and SF), activity durations, resource allocation and WBS. Appendix 2 provides definition on different activity relationships.

You have been asked to perform the following planning and scheduling processes with the help of Microsoft Project 2007.

A: CPM & WBS

1.  Draw a Gantt-Chart and CPM network for the project. Calculate EST, EFT, LST, LFT and TF based on As Soon as Possible (ASAP) method and identify critical path. Gantt-Chat should show WBS of the project (use A4 or A3 sheet as required) 

2.  Draw manually  the hierarchy of WBS for  the project  (must include  Level 1,  Level 2, Level 3 and Level 4).use MS Visio or other IT software. You can also draw manually and scan it. 

3.  Explain why identification of the critical path is important? Also comment on the changes to the Critical Path, if the project is developed using As Late as Possible (ALAP) method. (max one page)

B: Resources Histograms

1.  Produce resource histograms for  all  the resources  using ASAP method. Identify  and  discuss  the maximum  resources needed  for this project per day and per month.

2.  If As Late as Possible (ALAP) method is used. Will the number of resource identified in question B.1 changes, explain.

C: Resource Smoothing and Resource Levelling

1.  Produce and draw smoothed resource histograms for the skilled labour resources. Do not use automatic smoothening

2.  Carry-out resource levelling  for equipment resource and discuss how activities might be delayed beyond LST to cater for the limits on equipment resources as a result of levelling.

Consider resource pool for equipment resources as 8 units per day. (use A3 sheet for each histogram, max one page for discussion)

3.  Explain and discuss the process of resource levelling. (max one page)

E: Cost Analysis

1.  Calculate the cost of each activity in the project (level 3). Consider the standard cost of a skilled labour as £10/hr, unskilled labour as £15/hr and equipment as £45/hr.

2.  Identify and analyse those activities  which are expensive, for example Structures; Envelope & claddings; Mechanical & electrical services etc. (max one page)

3.  Draw cumulative cost-time curve for each resources and for the project. Comment on the cost profile. (use A4 or A3 sheet as required)


Related Discussions:- Carry out resource levelling for equipment resource

Important to theoretical distribution , Important to Theoretical Distributi...

Important to Theoretical Distribution The science  of theoretical distribution  under which  the frequencies of a variable are derived by  some  mathematical  model  without

Mathematical, Ask 7:23 PM Docx Reader GROUP-7 1. A firm manufactures two pr...

Ask 7:23 PM Docx Reader GROUP-7 1. A firm manufactures two products A & B on which the profits earned per unit is Rs.3 and Rs.4. Each product is processed on two machines Miand M2.

Research and evaluation, - Please research and discuss this activity. (plea...

- Please research and discuss this activity. (please cite all of the websites) - Prepare a memo on the research and evaluation. What does research and evaluation mean? Ele

Classification of models, what are the classifications of operations resea...

what are the classifications of operations research?

LPP, A FIRM MANUFACTURES HAEDACHE PILLS IN TWO SIZE A AND B

A FIRM MANUFACTURES HAEDACHE PILLS IN TWO SIZE A AND B

Linear Programming, A paper mill produces two grades of paper viz., X & Y. ...

A paper mill produces two grades of paper viz., X & Y. Because of raw material restrictions, it cannot produce more 400 tons of grade X paper & 300 tons of grade Y paper in a week.

Variables, Variables A concept which varies is variable. These can be ...

Variables A concept which varies is variable. These can be different in quantitative values. For example, weight, height, income are examples of variables. Qualitative phenom

Linear programming, maximize z=3x1+2x2 subgect to the constraints x1+x2 x1-...

maximize z=3x1+2x2 subgect to the constraints x1+x2 x1-x2 x1,x2>_0

Complexity - necessity of operations research, In a big industry the numbe...

In a big industry the numbers of factors influencing a decision have increased situation has become big and complex because these factors interact with each other in complica

Operation research techniques, High Costs are Involved in the Use of O. R...

High Costs are Involved in the Use of O. R Techniques: O. R techniques usually prove very expensive. Services of specialized persons are invariably called for ( and along w

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd