Carry out resource levelling for equipment resource, Operation Research

Assignment Help:

Teesside Construction is developing a schedule for a major building project to start in 04/01/2011 in Middlesbrough, UK. The project manager has identified major activities of the project, their dependency and resources needed to run each activity. Appendix 1 provides information about the project, which includes project logic (activity links and their relationship - FS, SS, and SF), activity durations, resource allocation and WBS. Appendix 2 provides definition on different activity relationships.

You have been asked to perform the following planning and scheduling processes with the help of Microsoft Project 2007.

A: CPM & WBS

1.  Draw a Gantt-Chart and CPM network for the project. Calculate EST, EFT, LST, LFT and TF based on As Soon as Possible (ASAP) method and identify critical path. Gantt-Chat should show WBS of the project (use A4 or A3 sheet as required) 

2.  Draw manually  the hierarchy of WBS for  the project  (must include  Level 1,  Level 2, Level 3 and Level 4).use MS Visio or other IT software. You can also draw manually and scan it. 

3.  Explain why identification of the critical path is important? Also comment on the changes to the Critical Path, if the project is developed using As Late as Possible (ALAP) method. (max one page)

B: Resources Histograms

1.  Produce resource histograms for  all  the resources  using ASAP method. Identify  and  discuss  the maximum  resources needed  for this project per day and per month.

2.  If As Late as Possible (ALAP) method is used. Will the number of resource identified in question B.1 changes, explain.

C: Resource Smoothing and Resource Levelling

1.  Produce and draw smoothed resource histograms for the skilled labour resources. Do not use automatic smoothening

2.  Carry-out resource levelling  for equipment resource and discuss how activities might be delayed beyond LST to cater for the limits on equipment resources as a result of levelling.

Consider resource pool for equipment resources as 8 units per day. (use A3 sheet for each histogram, max one page for discussion)

3.  Explain and discuss the process of resource levelling. (max one page)

E: Cost Analysis

1.  Calculate the cost of each activity in the project (level 3). Consider the standard cost of a skilled labour as £10/hr, unskilled labour as £15/hr and equipment as £45/hr.

2.  Identify and analyse those activities  which are expensive, for example Structures; Envelope & claddings; Mechanical & electrical services etc. (max one page)

3.  Draw cumulative cost-time curve for each resources and for the project. Comment on the cost profile. (use A4 or A3 sheet as required)


Related Discussions:- Carry out resource levelling for equipment resource

Dual of the lpp, the dual form of the following lpp min z=3x1+2.5x2 constra...

the dual form of the following lpp min z=3x1+2.5x2 constraints:2x1+4x2>=40, 3x1+2x2>=50 and x1,x2>=0

Ap problem, Ask question A Company produces 150 cars. But the production ra...

Ask question A Company produces 150 cars. But the production rate varies with the distribution. Production Rate Probability 147 0.05 148 0.10 149 0.15 150 0.20 151 0.30 152 0.15 15

Game Theory, Task1:- A company is currently involved in negotiation with it...

Task1:- A company is currently involved in negotiation with its union on the upcoming wage contract. Positive signs in the table represent wage increase while negative sign represe

Paired sample sign test - hypothesis testing , Paired sample  sign Test ...

Paired sample  sign Test Paired samples  sign test is applied  to a situation where two sample  are taken from  two population which  have continuous symmetrical distributi

LPP, A paper mill produces two grades of paper viz., X and Y. Because of ra...

A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper i

Dynamic programming, A company is planning its advertising strategy for the...

A company is planning its advertising strategy for the next year for its three major products.

Post-optimal analysis, It can be seen from the optimal solution for the fou...

It can be seen from the optimal solution for the foundry problem that two resources, raw material-1 and labor, are exhausted whereas the other two resources, raw materi

Operations function - information system, The Operations Function has alway...

The Operations Function has always relied heavily on information for its smooth running. During this course information has been introduced as one of the five inputs to the convers

Linear programming, Use Big M method to Maximize(Z)=3_(x_1 )+2_(x_2 ) Subj...

Use Big M method to Maximize(Z)=3_(x_1 )+2_(x_2 ) Subject to 3_(x_1 )+?1.5?_(x_2 )=30 x_1+x_2=20 x_1=0 x_2=0

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd