Time (in Days)




Activity

Immediate Predecessor

Optimistic

Most Likely

Pessimistic


A

-

3

6

8


B

-

2

4

4


C

-

1

2

3


D

C

6

7

8


E

B, D

2

4

6


F

A, E

6

10

14


G

A, E

1

2

4


H

F

3

6

9


I

G

10

11

12


J

C

14

16

20


K

H, I

2

8

10









a. Draw the network diagram.

b. Calculate the expected (mean) completion time and its standard deviation for each activity.

c. Calculate the path mean and the path standard deviation for all of the possible paths.

d. Identify the critical path and critical activities.

e. What are the expected project completion time and variance?

f. What is the probability that the project:

i) will be completed within 38 days?

ii) will take more than 35 days to complete?

iii) will take between 35 and 38 days to complete?

Note: use the short method to compute the above probabilities.

g. Within how many days does the project have a 90% probability of completion?

h. Using the expected (mean) completion time, calculate the ES, EF, LS, LF, and slack for each activity.

Related Discussions:- cALCULATING THE SLACK, es,ef, ls, lf

What decision management business intelligence missing piece, Please read t...

Please read through the question, then answer each item of my question to get full points. Review the following short article by visiting the link below then answer the question

Calculate seasonal indices using all of the data, Attendance at Los Angeles...

Attendance at Los Angeles's newest Disneylike attraction, Vacation World, has been as follows- Quarter Guest in Thousands Quarter Guest in Thousands Winter 07 73 Summer 08 12

Explain internet played a role in retailing transactions, Do wholesaling in...

Do wholesaling intermediaries provide any ultimate value to customers, or do they just interfere with the process of retailing? Explain the reasons for your answer. Has the emergen

Explain humidity can be controlled, Company A uses an unstable chemical com...

Company A uses an unstable chemical compound that must be kept in an environment where both temperature and humidity can be controlled. Company A uses 800 pounds per month of the c

Describe the pivot initiative at midwest bank, Complete the case study The ...

Complete the case study The PIVOT Initiative at Midwest Bank, Part I, starting on page 358. On the basis of the information: • Prepare a 3 to 5 page paper discussing what conclusio

Define part-time employees fall within artistic and creative, 1. Grapple In...

1. Grapple Industries has 1,000 full-time and part-time employees who manufacture parts for hand tools. Company policy states that part-time employees are not eligible for overtime

Explain the factors determining the sequencing of jobs, Question : (a) ...

Question : (a) Show how operations management can contribute to the success of an organization. (b) Explain the factors determining the sequencing of jobs. ( c) A machin

Describe the problem with labour productivity, Two types of cars (Deluxe an...

Two types of cars (Deluxe and Limited) were produced by a car manufacturer in 1997. Quantities sold, price per unit, and labour hours follow. What is the productivity for each car?

Explain what are the schedule and cost variances, I need to find the schedu...

I need to find the schedule and cost variances for a project Actual cost at month 16 = $540,000 Scheduled cost = $523,000 Earned value = $535,000 Provided this information,

Describe shared storage policies and list example, Define shared storage po...

Define shared storage policies and list example that it is practice in real life?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd