cALCULATING THE SLACK, es,ef, ls, lf, Operation Management

Assignment Help:

Time (in Days)




Activity

Immediate Predecessor

Optimistic

Most Likely

Pessimistic


A

-

3

6

8


B

-

2

4

4


C

-

1

2

3


D

C

6

7

8


E

B, D

2

4

6


F

A, E

6

10

14


G

A, E

1

2

4


H

F

3

6

9


I

G

10

11

12


J

C

14

16

20


K

H, I

2

8

10









a. Draw the network diagram.

b. Calculate the expected (mean) completion time and its standard deviation for each activity.

c. Calculate the path mean and the path standard deviation for all of the possible paths.

d. Identify the critical path and critical activities.

e. What are the expected project completion time and variance?

f. What is the probability that the project:

i) will be completed within 38 days?

ii) will take more than 35 days to complete?

iii) will take between 35 and 38 days to complete?

Note: use the short method to compute the above probabilities.

g. Within how many days does the project have a 90% probability of completion?

h. Using the expected (mean) completion time, calculate the ES, EF, LS, LF, and slack for each activity.

Related Discussions:- cALCULATING THE SLACK, es,ef, ls, lf

Explain what remedies are available to him, Kristina places an order for a ...

Kristina places an order for a cake on Flowers bakery's web site. She then calls the baker to tell him that she will pay him $1000 for the specially designed cake if he will guaran

Impact on the practice of leadership, Question: The fundamentals of Lea...

Question: The fundamentals of Leadership practice are still very much the same as 10 years back but the context has dramatically changed! i. Enumerate the factors in this n

Explain what the earliest the project can be completed, The following table...

The following table shows the activity details of a project. What the earliest the project can be completed? Activity Days Predecessor ctivities A 4 - B 5 - C 3 A D 5 A E

Calculate the quarterly index, Over the past year, Meredith and Smunt Manuf...

Over the past year, Meredith and Smunt Manufacturing had annual sales of 10,000 portable water pumps. The average quarterly sales for the past 5 years have averaged: Spring 4,00

Explain production and distribution of pharmaceutical, Carrington inc is an...

Carrington inc is an international company engaged in the production and distribution of pharmaceutical. Is the Peterson operation successful? To the degree that it can be judged a

Explain the appropriate marketing-mix strategy, Marketers traditionally cla...

Marketers traditionally classify products on the basis of characteristics: durability, tangibility, and use (consumer or industrial). Discuss the appropriate marketing-mix strategy

Explain how long it sits nothing happens, I am having a issue getting my bo...

I am having a issue getting my book to load it says its loading but no matter how long it sits nothing happens.

Describe the various stages in team development, Question 1: (a) Descri...

Question 1: (a) Describe the various stages in team development. (b) What are the characteristics of an effective work team? Question 2: (a) Define Leadership. (b)

MBA-2, What do you understand by"line balancing"?What happens if balance do...

What do you understand by"line balancing"?What happens if balance doesn''t exist?

Why it is important for marketers know consumer behaviour, Why it is import...

Why it is important for marketers to fully understand today's consumer behaviour? Explain the factors that influence consumer's buying behaviour.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd