cALCULATING THE SLACK, es,ef, ls, lf, Operation Management

Assignment Help:

Time (in Days)




Activity

Immediate Predecessor

Optimistic

Most Likely

Pessimistic


A

-

3

6

8


B

-

2

4

4


C

-

1

2

3


D

C

6

7

8


E

B, D

2

4

6


F

A, E

6

10

14


G

A, E

1

2

4


H

F

3

6

9


I

G

10

11

12


J

C

14

16

20


K

H, I

2

8

10









a. Draw the network diagram.

b. Calculate the expected (mean) completion time and its standard deviation for each activity.

c. Calculate the path mean and the path standard deviation for all of the possible paths.

d. Identify the critical path and critical activities.

e. What are the expected project completion time and variance?

f. What is the probability that the project:

i) will be completed within 38 days?

ii) will take more than 35 days to complete?

iii) will take between 35 and 38 days to complete?

Note: use the short method to compute the above probabilities.

g. Within how many days does the project have a 90% probability of completion?

h. Using the expected (mean) completion time, calculate the ES, EF, LS, LF, and slack for each activity.

Related Discussions:- cALCULATING THE SLACK, es,ef, ls, lf

Quality management systems - improving productivity, Quality Management Sys...

Quality Management Systems - Improving Productivity The introduction of approaches such as ISO 9000; Total quality management, business process reengineering, just-in-time ope

Explain how do hr managers cope with stress, Why hr managers, etc. Is a lon...

Why hr managers, etc. Is a lonely job? How do hr managers cope with stress? What does it take to become a hr manager? Reference and cited

Challenges for operations managers - operation strategy, Challenges for Ope...

Challenges for Operations Managers - Operation Strategy Most products have several competitors today - from cars to university degrees. Current market forces appears to sugge

Explain six sigma principles to health care organizations, Type two savings...

Type two savings are the least likely to occur when applying Six Sigma principles to health care organizations

Explain formulate and solve a linear optimization model, Klein Industries m...

Klein Industries manufactures three air compressors: small, medium, and large, which have unit profits of $20.50, $34, and $42 respectively. The monthly projected sales of small ar

Forcasting, what are types of forcasting?

what are types of forcasting?

Explain what behaviours destroy trust, Earlier in the class, we noted that ...

Earlier in the class, we noted that communication is the glue holding organizations together. We might say that trust is the "oil" of the organization. With it, processes can opera

Explain schematic model of the sequence, Which of the following models uses...

Which of the following models uses a schematic model of the sequence of steps in a problem and the conditions and consequences of each step?

Describe how the eoq technique helps, Explain how the EOQ technique helps e...

Explain how the EOQ technique helps explain the following: All things being equal, the production inventory quantity will be larger than the economic order quantity.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd