Calculate uniform annual cost for maintenance and repair, Civil Engineering

Assignment Help:

A contractor purchased a Caterpillar D-13 dozer for $100,000 and owned it for five years. The annual cost for maintenance and repair is provided in the Table. With annual interest rate at 7% and end-of-year disbursements, the uniform annual cost for maintenance and repair for the dozer is most nearly:

Year                 Maintenance and Repair Costs

1                                   $4,500

2                                  $9,000

3                                  $11,800

4                                  $13,500

5                                  $22,500

Solution:  The Equivalent Uniform Annual Cost (EUAC) can be computed for this irregular series of payments in two steps: 

Step 1:   Compute the Present Worth for five years using the single payment present worth factors.

PW of cost   = 4500(P/F, 7%, 1) + 9000(P/F, 7%, 2) + 11800(P/F, 7%, 3) +  13500(P/F, 7%, 4) + 22500(P/F, 7%, 5)

 = 4500(.9346) + 9000(.8734) + 11800(.8163) + 13500(.7629) + 22500(.7130)      

= $48,040.29

Step 2:   With the PW of cost known, compute the EUAC using the capital recovery factor.

  EUAC   = 48,040(A/P, 7%, 5)

      = 48,040(.2439) 

      = $11,717.03


Related Discussions:- Calculate uniform annual cost for maintenance and repair

Draw the variation in total stress, Draw the variation in total stress, eff...

Draw the variation in total stress, effective stress, and pour water pres- sure up to a depth of 6 m below ground level, given the following data. The water table is 2 m below grou

Municipal Hydraulics, Hello I have an assignment due feb 1st at 3 pm. I wan...

Hello I have an assignment due feb 1st at 3 pm. I wanted to know if it was possible that it gets solved

Estimation of loading carrying capacity, Question While designing mini...

Question While designing mini-piles , should strength of grout be disused during estimation of loading carrying capacity? Answer While designing min-piles, there will

Prestressed concrete poles, Prestressed concrete poles In the past deca...

Prestressed concrete poles In the past decades, prestressed  concrete poles have become popular and have replaced the traditional poles made of timber, steel or reinforced  con

Sub-base for concrete carriageway - non-strength provider, Sub-base for con...

Sub-base for concrete carriageway - non-strength provider Essentially sub-base for a concrete carriageway is provided for the below reasons: (i)  It provides aneven and smo

Estimate prestress losses, Given: beam deminsions: flange width=22" FL...

Given: beam deminsions: flange width=22" FLANGE THICKNESS=7" WEB WIDTH=7" SECTION HEIGHT=40" f'c=5000psi f'ci=3500psi fpu=270ksi Ap=eighteen 1/2" diam strands superim

Ceramic tiles for construction material, Q. Ceramic Tiles for construction ...

Q. Ceramic Tiles for construction material? For public toilet bath rooms , kitchen etc to ensure cleanliness floors should be provided with ceramic tile. For water points on

Why does the pressure increase under soil, Soil pressure enhances with dept...

Soil pressure enhances with depth due to the overburden or self-weight of the soil and because of loads imposed upon the soil. For example, the pressure variation below the dept

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd