Calculate uniform annual cost for maintenance and repair, Civil Engineering

Assignment Help:

A contractor purchased a Caterpillar D-13 dozer for $100,000 and owned it for five years. The annual cost for maintenance and repair is provided in the Table. With annual interest rate at 7% and end-of-year disbursements, the uniform annual cost for maintenance and repair for the dozer is most nearly:

Year                 Maintenance and Repair Costs

1                                   $4,500

2                                  $9,000

3                                  $11,800

4                                  $13,500

5                                  $22,500

Solution:  The Equivalent Uniform Annual Cost (EUAC) can be computed for this irregular series of payments in two steps: 

Step 1:   Compute the Present Worth for five years using the single payment present worth factors.

PW of cost   = 4500(P/F, 7%, 1) + 9000(P/F, 7%, 2) + 11800(P/F, 7%, 3) +  13500(P/F, 7%, 4) + 22500(P/F, 7%, 5)

 = 4500(.9346) + 9000(.8734) + 11800(.8163) + 13500(.7629) + 22500(.7130)      

= $48,040.29

Step 2:   With the PW of cost known, compute the EUAC using the capital recovery factor.

  EUAC   = 48,040(A/P, 7%, 5)

      = 48,040(.2439) 

      = $11,717.03


Related Discussions:- Calculate uniform annual cost for maintenance and repair

Main functions of slip joints in block work seawalls, Question What are...

Question What are main functions of slip joints in block work seawalls ? Answer Slip joints are joints that are formed during a complete vertical plane from cope

Material which can endures vibrations and saline conditions, material which...

material which can endures vibrations and saline conditions

Elongation, Elongation of bar due to self weight

Elongation of bar due to self weight

Energy equation, find the pressure head at 2-2 if the rate of flow in pipe ...

find the pressure head at 2-2 if the rate of flow in pipe is 0.36m^3/s

Test leakage of constructed gravity pipelines, Question Have air test o...

Question Have air test or water tests be selected to test leakage of constructed gravity pipelines ? Answer For gravity pipes, air tests are carried out after completi

#title., Ask question #Minimum 100 words accepted2812539076# you

Ask question #Minimum 100 words accepted2812539076# you

Pre-stressing work, Under which situation shall engineers use jacking in ag...

Under which situation shall engineers use jacking in agreement end only and from both ends in pre-stressing work?

CANTILEVER RETAINING WALL, NEED TO DESIGN A CANTILEVER RETAINING WALL 8M HI...

NEED TO DESIGN A CANTILEVER RETAINING WALL 8M HIGH, SATURATED UNIT WEIGHT IS 16KN/M3, SURCHARGE IS 7KN/M2, LOAD ABOVE WALL SUPPORTED ON WALL STEM IS 10KN/M RUN, ANGLE IN INTERNAL F

Proctor test for GSB material, what is the procedure for gsb proctor test f...

what is the procedure for gsb proctor test for matrial sampling for lab density

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd