Calculate the total variable cost of 6,400 units product, Cost Accounting

Assignment Help:

A company has developed a new product which it will launch next month. During the initial production phase the company expects to produce 6,400 units in batches of 100 units. The first batch to be produced is expected to require 25 hours of direct labour. The following details are expected to apply throughout the initial production phase:

•  Direct material cost per unit is expected to be $4  
•  Direct labour is to be paid $10 per hour  
•  A 90% learning curve is expected to apply  
•  Other variable costs are expected to be $2 per unit 

(a)  Calculate the total variable cost of the 6,400 units of the new product.

 
(a)
  $
Direct material (6,400 units x $4)                                         25,600
Direct labour (see below)                                                       8,503
Other variable costs (6,400 units x $2)                                12,800
                                                                                             46,903
 
Direct labour:
 
The time taken is expected to be:
 
 Y=axb = 25 x 64 -0.1520   = 13.286 hours per batch, which is a total of 850.32 hours for 64 batches
 
 850.32 hours x $10 per hour = $8,503.20

 


Related Discussions:- Calculate the total variable cost of 6,400 units product

Issues to consider when making decisions, Q. Issues to consider when making...

Q. Issues to consider when making decisions? At activity level A it can be seen from diagram that sales revenue line intersects the total cost line specifying that this is the

Time keeping - cost accumulation, Time Keeping - Cost Accumulation A l...

Time Keeping - Cost Accumulation A labour cost control routine should ensure that payments are paid only to employees who have spent time at the work place and that payments a

What is cmmi, Capability Maturity Model Integration (CMMI) is a process dev...

Capability Maturity Model Integration (CMMI) is a process development approach that gives organizations with the essential elements of effective processes. It can be used to gui

Normal job-order costing system, A normal job-order costing system is a sys...

A normal job-order costing system is a system that uses :    A.  actual costs for direct materials and estimated costs for direct labor and overhead B.  estimated costs

Job order costing, Amazing acrobatics performs acrobatics in stadiums aroun...

Amazing acrobatics performs acrobatics in stadiums around the world. The average show sells about 1,000 tickets at $60 per ticket. Each show requires a team of 45 highly trained sp

Journal entry for sale of machinery, Rayya Co. purchases and installs a mac...

Rayya Co. purchases and installs a machine on January 1, 2013, at a total cost of $105,000. Straight-line depreciation is taken each year for four years assuming a seven-year life

Determine inventory costs, Determine Inventory Costs Mary Cosmetics sells s...

Determine Inventory Costs Mary Cosmetics sells specialty lipstick for a retail price of $12.25 each. Mary purchases each tube for $5.00 and pays the following additional amounts: $

Behavioral classification of costs, Behavioral Classification of Costs ...

Behavioral Classification of Costs Definition Cost behavior refers to the change in costs as increase or may decrease like the output level changes that are like we risin

Job order costing, the folloeing job order cost sheets were purchased for t...

the folloeing job order cost sheets were purchased for three jobs that were in production during january job 97 job 98 job 99 material

Material usage variance (muv), Material Usage Variance (MUV): This is t...

Material Usage Variance (MUV): This is the variation between the actual quantity of material consumed and standard quantity which should have been consumed, expressed in terms

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd