A contractor will place 90-cubic yards of concrete for a housekeeping pad on the rooftop of a 36-ft tall building. Site conditions dictate that the safest and best method of placement is to use a crane and a 2-cubic-yard bucket. To perform the task efficiently, five Union laborers are needed - one at the concrete truck, three at the point of placement, and one on the portable internal vibrator. The wage rate for laborers is $22.00/hr (Union overtime rate is 1.5 times the wage rate after 8-hour day). Time needed for the operation is: Setup: 15-min; Cycle time consists of Load = 3-min., plus Swing, dump and return = 6-min. which allows a total cycle time = 9-min; Demobilize operation, 10-min. Supervision is done by the superintendent. Allow a 10% factor for inefficiencies during the cycle time. Crane rental cost is $1,800 per 8-hr day. The total labor cost per cubic yard for the concrete crane placement of the 90 cubic yards is most nearly:

Solution:

Identify (by underlining) relevant cost items and calculate summary quantities.

No. of cycles 90-CY/2-CY/Bucket = 45 cycles

Total cycle time 45-cycles x 9-min/cycle = 405 min

Inefficiency(labor,delays,etc.)10%of cycle time = 41-min

Setup and demobilize: Sub-total = 25 min

Total operation time: 405 + 41 + 25 = 471-min or 7.85-hrs

Amount of time needed (adjusted to workday) = 8 hr Laborers - five for 8 hours at $22.00/hr = $880.00

Total labor cost per 90-yd3 = $880.00

Cost per cubic yard $880/90-yd3 = $9.78/yd3


Related Discussions:- Calculate the total labor cost per cubic yard

Keywords related to water transportation, Keywords related to water transpo...

Keywords related to water transportation: Oceanic Shipping: Shipping taking place in the oceans. Coastal Shipping: Shipping taking place along the coast line. Inlan

#civil, what is whole circle barring

what is whole circle barring

Factors affecting location decision, Factors Affecting Location Decision: ...

Factors Affecting Location Decision:   Mining, quarrying and heavy manufacturing have capital intensive facilities that are costly to build and cover large area and use large q

Preloading - control of settlements, Q. Preloading - Control of settlements...

Q. Preloading - Control of settlements? This method consists of loading the soil strata by a load intensity which will be equal to or higher than the expected load intensity. T

Show afflux and scour in alluvial rivers, Q. Show Afflux and scour in alluv...

Q. Show Afflux and scour in alluvial rivers? In case of alluvial rivers, the river bed comprises scourable material like sand. Constriction of bridge waterway causes increase

Steps to determine hydraulic horsepower for pump problems, Steps to determi...

Steps to determine the hydraulic horsepower (whp) for pump problems:  1) Determine (h A ) by rearranging the Bernoulli equation.    2) Apply (h A ) into the equation found i

Principle of airlifting for cleaning pile bores, Q. Principle of airlifting...

Q. Principle of airlifting for cleaning pile bores? Airlifting is generally carried out before concreting to remove debris and clean the base of pile bores. It basically acts a

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd