Calculate the total duration for the four activity project, Civil Engineering

Assignment Help:

Calculate the Total Duration for the Four Activity Project

1260_Calculate the Total Duration for the Four Activity Project 1.png

Solution:     

Scheduling work activity has associated time duration. The durations shown in the Table were estimated for the project diagrammed below. The entire set of activities would then require 3-days, since the activities follow one another directly and require a total of 1.0 + 0.5 + 0.5 + 1.0 = 3-days (answer is c). If another activity proceeded in parallel with this sequence, the 3 day minimum duration of these four activities is unaffected. More than 3 days would be required for the sequence if there was a delay or a lag between the completion of one activity and the start of another.

1026_Calculate the Total Duration for the Four Activity Project 2.png


Related Discussions:- Calculate the total duration for the four activity project

What is the design mix concrete, What is the Design Mix concrete Determ...

What is the Design Mix concrete Determination of  the proportions of  cement, aggregates and water to  achieve the required strengths in concrete is made by designing  the  con

Planning stage of the audit, Materiality is used only at the planning stage...

Materiality is used only at the planning stage of the audit. Ans: I disagree with the statement because: When planning the audit, the auditor considers what would make the fi

Structural analysis_cantilever trusses, Obtain the values and direction of ...

Obtain the values and direction of the supporting reactions of the truss given below. Use the method of section to determine the forces in each member.

Concrete structure, which section is most effective for a design of beam an...

which section is most effective for a design of beam and why

Determine the preliminary settlement analysis, Preliminary settlement analy...

Preliminary settlement analysis for a building indicated a settlement of 50 mm in 4 years and an  ultimate  settlement  of  250 mm.  The average pressure increment in the clay stra

Designing sewer pipes, Question While designing sewer pipes , why vitrifie...

Question While designing sewer pipes , why vitrified clay pipes commonly is used for pipe size less than 600mm still as precast concrete pipes with PVC lining is used for pipe

Explain gap survey and adjustment of gap, Q. Explain Gap Survey and adjustm...

Q. Explain Gap Survey and adjustment of Gap? Gap survey and rectification of gaps is to be carried out, in stretches where track develops excessive creep jammed joints, sun kin

Grades of concrete, mixing ratio of different type of ready mix concrete.(R...

mixing ratio of different type of ready mix concrete.(RMC)

Air infiltration, Using Matlab/ Simulink software, verify the heating requi...

Using Matlab/ Simulink software, verify the heating requirement (kW) for the building because of  air infiltration and natural ventilation. Note that this needs you to estimate air

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd