Calculate the total duration for the four activity project, Civil Engineering

Assignment Help:

Calculate the Total Duration for the Four Activity Project

1260_Calculate the Total Duration for the Four Activity Project 1.png

Solution:     

Scheduling work activity has associated time duration. The durations shown in the Table were estimated for the project diagrammed below. The entire set of activities would then require 3-days, since the activities follow one another directly and require a total of 1.0 + 0.5 + 0.5 + 1.0 = 3-days (answer is c). If another activity proceeded in parallel with this sequence, the 3 day minimum duration of these four activities is unaffected. More than 3 days would be required for the sequence if there was a delay or a lag between the completion of one activity and the start of another.

1026_Calculate the Total Duration for the Four Activity Project 2.png


Related Discussions:- Calculate the total duration for the four activity project

Cement bag question., composition of cement in cover bag should be written ...

composition of cement in cover bag should be written or not/ If written which country uses ?please specify the name ?

Shear lag in typical box-girder bridge, Shear lag in typical box-girder bri...

Shear lag in typical box-girder bridge For multiple-cell box girders, there are normally two arrangements. First one is that independent cells are connected by their top flang

Verify the net allowable bearing pressure, A 1.8 m square column is founded...

A 1.8 m square column is founded at a depth of 1.8 m in sand, for which the accurate N-value is 24. The water table is at a detph of 2.7 m. Verify the net allowable bearing pres

Specify the various methods of soil exploration, Specify the various method...

Specify the various methods of soil exploration and mention the circumstances under which each is best suited. What do you mean by undisturbed sample? Define with a neat sketch

Define scour - underwater inspection of bridges, Define Scour - Underwater ...

Define Scour - Underwater Inspection of Bridges? Whenever a bridge crosses a waterway, even a small or intermittent one, scour is a dangerous effect that can damage bridge pier

#civil, what is whole circle barring

what is whole circle barring

Civil engineering drawing, Explain step by step procedure involved in the a...

Explain step by step procedure involved in the analysis and design of balanced cantilever bridge.

Particle size distribution - soil compaction, Particle Size Distribution (G...

Particle Size Distribution (Gradation): The particle size distribution is determined by passing the aggregates through a set of standard IS sieves (Figure) and determining th

Maintenance of gravel roads, Maintenance of Gravel Roads: The mainten...

Maintenance of Gravel Roads: The maintenance consists of : filling up of potholes/depressions with fresh gravel and compacting after light sprinkling with water. g

Marked., who invented the first LA abrasion test machine

who invented the first LA abrasion test machine

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd