Calculate the total duration for the four activity project, Civil Engineering

Assignment Help:

Calculate the Total Duration for the Four Activity Project

1260_Calculate the Total Duration for the Four Activity Project 1.png

Solution:     

Scheduling work activity has associated time duration. The durations shown in the Table were estimated for the project diagrammed below. The entire set of activities would then require 3-days, since the activities follow one another directly and require a total of 1.0 + 0.5 + 0.5 + 1.0 = 3-days (answer is c). If another activity proceeded in parallel with this sequence, the 3 day minimum duration of these four activities is unaffected. More than 3 days would be required for the sequence if there was a delay or a lag between the completion of one activity and the start of another.

1026_Calculate the Total Duration for the Four Activity Project 2.png


Related Discussions:- Calculate the total duration for the four activity project

Correction in bearing, write a c program To compute interior angles and cor...

write a c program To compute interior angles and correct them for observational errors and adjusting the bearing of remaining sides when the bearings taken on a closed compass trav

Define the meaning of grout - concrete, Define the meaning of Grout - Concr...

Define the meaning of Grout - Concrete Grout should be made with any type of recommended cement and using water of a required quality. If very large size ducts are to be groute

Arches, construction of arches

construction of arches

Surveying, What is the shrinkage factor

What is the shrinkage factor

Define hammer efficiency and coefficient of restitution, Q. Define Hammer e...

Q. Define Hammer efficiency and coefficient of restitution? Hammer efficiency refers to ratio of kinetic energy of hammer to the rated energy (or potential energy). Basically i

Paint, different types of paints?

different types of paints?

Design of masonry, Describe the different types of Ant proof courses

Describe the different types of Ant proof courses

What is the absolute maximum shear stress, A strip load of considerable len...

A strip load of considerable length and 1.5 m width transmits a pressure of 150 kN/m 2 to the underlying soil. Verify the maximum principal stress at 0.75 m depth below the footin

Simple bending, In case of simple bending after simply supported beam, deri...

In case of simple bending after simply supported beam, derive that M/I = s /y = E/R.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd