Q  A transition curve is required for a circular curve of 200-meter Φ radius, the gauge being 1.5 m. and max super elevation restricted to 15 cm. The transition restricted to 15 cm. The transition is to be designed for a velocity such that no lateral pressure is imposed on the rails and the rate of gain of radial acceleration is 30 cm / sec3 . Calculate the required length of transition. 


Related Discussions:- Calculate the required length of transition

Explain what is stationing - transportation, Explain what is Stationing - T...

Explain what is Stationing - Transportation 1) Stationing concept is used along horizontal alignments for referencing purpose 2) 1 station = 100 feet 3) How do you repres

Surveying, obstacle to ranging but not chaining inthat when line may not vi...

obstacle to ranging but not chaining inthat when line may not visible from intermediate point pls if required explain with diagram

Disparity between working stress and limit state approach, Question Wha...

Question What is key disparity between working stress approach and limit state approach ? Answer Working stress approach, service loads are used in whole plan and st

Explain the unit hydrograph method, Q.- Explain the Unit hydrograph Method ...

Q.- Explain the Unit hydrograph Method for estimation of peak flood discharge in a river. Ans.- Unit hydrograph Method A hydrograph is a representation of hydraulic cha

leveling, what are the diff.types of levels used in levlin

what are the diff.types of levels used in levling

Loss of camber in steel girders, Steel triangulated (open web) girders are ...

Steel triangulated (open web) girders are provided with camber to compensate for deflection under load. Out of the total design camber, the part corresponding to dead load is calle

Storm water drainage - Road drainage and maintenance, Storm Water Drainage:...

Storm Water Drainage: In city streets, the disposal of rain water has to be done through a system of underground storm water drains. The water is collected at the roadside ke

Surveying, if bearing of AB is 190& that of CB is 260,the included angle AB...

if bearing of AB is 190& that of CB is 260,the included angle ABC is how?

Loading and unloading cycles for soil nails, In carrying out pull-out tests...

In carrying out pull-out tests for soil nails, it generally requires the unloading and loading of soil nails of several cycles up to 80% of ultimate tensile strength of soil nails.

Explain precedence relationships - construction management, Explain the Pre...

Explain the Precedence Relationships a. Finish-to-Start - the most common, the predecessor activity must finish before the successor activity can start b. Finish to Finish

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd