Calculate the probable wall thickness of the tank, Mechanical Engineering

Assignment Help:

The background for the oil storage tank failure is as follows: the tank involved was a four million gallon circular tank that was built in 1940 for Ashland Oil Company in Cleveland, Ohio. Beginning in 1940, the tank was operated for many years in what was believed to have been heated oil service. It is unclear as to how many years the tank was not used, but in 1986 it was disassembled by cutting it apart into sections. Using oxy-acetylene torches the "old welds" were left in place as the tank was cut apart and the sections were moved to an Ashland Oil facility near Pittsburgh, Pennsylvania. Using shielded metal arc welding, the tank was reassembled in 1987 and placed in a tank farm with many other similar tanks near the Monongahela River. When reassembled, the tank joints were x-rayed and leak tested. Test results indicated that none of the welds required rework. The reassembled tank was 50 feet high and approximately 130 feet in diameter. A dike was built around the tank that would hold 150 percent of the tank capacity.

The tank was partially filled with diesel fuel in August 1987. On January 2, 1988, during its initial filling to capacity after reconstruction, the tank failed catastrophically creating a tidal wave of oil that sent nearly 4,000,000 gallons of diesel fuel into the Monongahela River causing a major environmental problem. The problem was so severe that the entire water supply for all of South Pittsburgh had to be shutdown for two weeks. In addition to spilling thousands of gallons of oil in the river, the tidal wave of oil from the tank damaged other nearby tanks and structures as well. "A small, uncemented cinderblock shed about 120 feet distant had its walls literally swept away... leaving its roof lying neatly on the slab floor. "

Answer the following questions:

1.  Decide what material composition was most likely used for the tank wall, document the properties of the material and then decide the most likely processing history for the manufacture and construction of the storage tank.  Discuss these issues as the initial paragraph(s) of your report.

2.  Calculate the probable wall thickness of the tank.

3.  If a 3/8" thick plate was used, calculate the exact flaw size that caused the brittle failure of the tank.

4.  Use your calculations as a basis for a one or two paragraph discussion of the tank failure. 

5.  By calculation and design assumptions, determine if any of the following materials could be used for this tank, given the (improbable) assumption that all manufacturing and joining problems are solvable for the particular material.

PMMA 2024-T4

Aluminum Ti-6AL-4V

Aluminum Oxide Glass


Related Discussions:- Calculate the probable wall thickness of the tank

Consideration for centrifugal tension, Consideration: 1. From above eq...

Consideration: 1. From above equation, it is clear that centrifugal tension is not dependent of T1 and T2. It depends upon velocity of the belt. For lower belt speed (that is,

Determine the force to pull box along a level surface, Determine the force ...

Determine the force to pull box along a level surface: A metal box having weight 10KN is pulled along a level surface at the uniform speed by applying horizontal force of 350

Determine the maximum efficiency, A jet strikes tangentially a smooth curve...

A jet strikes tangentially a smooth curved vane moving in the similar direction as the jet, and the jet gets reversed in the direction. Prove that the maximum efficiency is slightl

Comparison between work and heat - thermodynamics, Comparison between work ...

Comparison between work and heat - thermodynamics: There are a number of similarities between heat and work. 1. Both heat and work are transient phenomena. The systems do n

Types of culverts - causeway and bridges, Types of Culverts: Culverts ...

Types of Culverts: Culverts are constructed with various materials and to different designs. The popular forms are : (a) Temporary stone scuppers (b) Stone slab culverts

Scope of work for a project in mechanical engineering, Q. Scope of work for...

Q. Scope of work for a project in Mechanical Engineering? The Mechanical Engineering scope of work for a project involves the design and specification of mechanical equipment a

Determine resultant of four forces - mechanics, Determine resultant of four...

Determine resultant of four forces: D etermine resultant of four forces tangent to the circle of radius 3m shown in the figure given below.  What will be the location of it

Evaluate maximum inclination that can climb - car, Evaluate maximum inclina...

Evaluate maximum inclination that can climb: Q: A four wheel drive can as shown in the figure has mass of 2000Kg with the passengers. The roadway is inclined at the angle wit

Flange assembly, The assembly techniques of bolted connections and bolts an...

The assembly techniques of bolted connections and bolts and gaskets material selection are closely interrelated. Consequently, they must be treated as an integrated problem.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd