Calculate the probable wall thickness of the tank, Mechanical Engineering

Assignment Help:

The background for the oil storage tank failure is as follows: the tank involved was a four million gallon circular tank that was built in 1940 for Ashland Oil Company in Cleveland, Ohio. Beginning in 1940, the tank was operated for many years in what was believed to have been heated oil service. It is unclear as to how many years the tank was not used, but in 1986 it was disassembled by cutting it apart into sections. Using oxy-acetylene torches the "old welds" were left in place as the tank was cut apart and the sections were moved to an Ashland Oil facility near Pittsburgh, Pennsylvania. Using shielded metal arc welding, the tank was reassembled in 1987 and placed in a tank farm with many other similar tanks near the Monongahela River. When reassembled, the tank joints were x-rayed and leak tested. Test results indicated that none of the welds required rework. The reassembled tank was 50 feet high and approximately 130 feet in diameter. A dike was built around the tank that would hold 150 percent of the tank capacity.

The tank was partially filled with diesel fuel in August 1987. On January 2, 1988, during its initial filling to capacity after reconstruction, the tank failed catastrophically creating a tidal wave of oil that sent nearly 4,000,000 gallons of diesel fuel into the Monongahela River causing a major environmental problem. The problem was so severe that the entire water supply for all of South Pittsburgh had to be shutdown for two weeks. In addition to spilling thousands of gallons of oil in the river, the tidal wave of oil from the tank damaged other nearby tanks and structures as well. "A small, uncemented cinderblock shed about 120 feet distant had its walls literally swept away... leaving its roof lying neatly on the slab floor. "

Answer the following questions:

1.  Decide what material composition was most likely used for the tank wall, document the properties of the material and then decide the most likely processing history for the manufacture and construction of the storage tank.  Discuss these issues as the initial paragraph(s) of your report.

2.  Calculate the probable wall thickness of the tank.

3.  If a 3/8" thick plate was used, calculate the exact flaw size that caused the brittle failure of the tank.

4.  Use your calculations as a basis for a one or two paragraph discussion of the tank failure. 

5.  By calculation and design assumptions, determine if any of the following materials could be used for this tank, given the (improbable) assumption that all manufacturing and joining problems are solvable for the particular material.

PMMA 2024-T4

Aluminum Ti-6AL-4V

Aluminum Oxide Glass


Related Discussions:- Calculate the probable wall thickness of the tank

Manufacturing technology, Details of rolling process,Different rolling meth...

Details of rolling process,Different rolling methods,

Stress-strain curves (compression), Stress-Strai n Curves (Compression): ...

Stress-Strai n Curves (Compression): For the ductile materials stress strain curves in compression are similar to those in tension at least up to the yield point for all the

Does the selected system meet the requirements, Does the selected system me...

Does the selected system meet the requirements of the application (building purging, make-up air, filtration, ventilation)? Is the system suitable for the intended building usag

Define universal portable radial drills, Define universal portable radial d...

Define universal portable radial drills Drilling machine is mounted on a trolley base to have a greater degree of mobility. In order to move the machine to any position on or a

Locomotive boiler, advantages and disadvantages of locomotive boiler

advantages and disadvantages of locomotive boiler

Piping stress analysis, The Mechanical Engineer/Specialist shall be respons...

The Mechanical Engineer/Specialist shall be responsible for coordinating project issues related to stress analysis, as they relate to his/her equipment, with the Stress Engineer/Sp

Horizontal hinge, 2 x 2 m square gate opens clockwise on a horizontal hinge...

2 x 2 m square gate opens clockwise on a horizontal hinge located at point A, which is 100 mm below the centroid of the gate. The gate sits against solid rubber blocks which create

Show gasket compression, Q. Show Gasket Compression? Gasket compression...

Q. Show Gasket Compression? Gasket compression can also be used as a guide for limiting bolt torque. Spiral wound gaskets should be compressed to an average of 75% of origin

Calculated the diameter of an aluninium shaft , Calculated the diameter of ...

Calculated the diameter of an aluninium shaft: Calculated the diameter of an aluninium shaft that is designed to store the similar amount of strain energy per unit volume as a

Why is stress relieving in post-weld treatment necesaary, In case of welded...

In case of welded vessels why is stress relieving in the form of post-weld treatment necessary? When a metal is welded together the point at which two surfaces are joined are s

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd