Calculate the number of paths and critical paths, Civil Engineering

Assignment Help:

Calculate the Number of Paths, Number of Critical Paths and Project Duration

For the project network shown, the total number of paths through the network; number of critical paths; and, project duration (days) is most nearly:

a. 6; 2; and, 26 

b. 6; 1; and, 26 

c. 5; 1; and, 25

d. 3; 3; and, 24

539_Calculate the Number of Paths, Number of Critical Paths and Project Duration.png

Solution:  List the number of paths and calculate the duration for each.  

L M O R T V   = 4 + 7 + 2 + 2 + 2 + 9 = 26-days -- Critical

L M O S U     = 4 + 7 + 2 + 3 + 7 = 23-days

L M Q V      = 4 + 7 + 6 + 9 = 26-days - Critical 

L M Q U    = 4 + 7 + 6 + 7 = 24-days

L N P Q U    = 4 + 3 + 6 + 7 = 20-days

L N P Q V    = 4 + 3 + 3 + 6 + 9 = 25-days


Related Discussions:- Calculate the number of paths and critical paths

What is portal cranes, Q. What is Portal Cranes? The Portal crane is a ...

Q. What is Portal Cranes? The Portal crane is a hydraulically driven four wheeled machine and is meant for carrying sleepers or track panels. The power for running and working

Vertical gradient - geometric design of roads, Vertical Gradient: Ver...

Vertical Gradient: Vertical gradient can be of three types: Ruling Gradient Used as a matter of course. Limiting Gradient Used in situations where site condit

Explain the installation of shock transmission unit, Explain the Installati...

Explain the Installation of Shock Transmission Unit? It is not always necessary to install STUs while a structure is under construction but the holding down anchor bolts and th

# bnm.l/j, what does oxymoron mean

what does oxymoron mean

Highway engineering., history and development of indian road and planning

history and development of indian road and planning

Formation of holes in pipelines, Question While branch pipelines are co...

Question While branch pipelines are connected to pipelines, now and then Y-junctions or fitting branched pipelines to key pipelines by formation of holes in pipelines are u

Arches, what is arches ? what are the classification of arches

what is arches ? what are the classification of arches

Enumerate the term - failure due to crushing of concrete, Enumerate the ter...

Enumerate the term - Failure Due to Crushing of Concrete Over reinforced pre-stressed concrete members, provided with a large amount of pre-stressing steel or relatively small

Calculate the initial height of the stockpile, On a 5-acre level terrain bu...

On a 5-acre level terrain building site, an earthwork contractor has instructed her crew to strip and grub the topsoil of a 60,000-ft 2 proposed building pad to a minus 2-ft sub-g

Measurements, Explain the concept of average velocity

Explain the concept of average velocity

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd