Calculate the Number of Paths, Number of Critical Paths and Project Duration
For the project network shown, the total number of paths through the network; number of critical paths; and, project duration (days) is most nearly:
a. 6; 2; and, 26
b. 6; 1; and, 26
c. 5; 1; and, 25
d. 3; 3; and, 24
Solution: List the number of paths and calculate the duration for each.
L M O R T V = 4 + 7 + 2 + 2 + 2 + 9 = 26-days -- Critical
L M O S U = 4 + 7 + 2 + 3 + 7 = 23-days
L M Q V = 4 + 7 + 6 + 9 = 26-days - Critical
L M Q U = 4 + 7 + 6 + 7 = 24-days
L N P Q U = 4 + 3 + 6 + 7 = 20-days
L N P Q V = 4 + 3 + 3 + 6 + 9 = 25-days
Loads
what is grouting?
limitations of EIA
determine point of contracflexure
Question If contractor suggests increasing concrete cover beyond contractual such as 40mm to 70mm shall engineers accept suggestion? Answer In contractual part, based on requir
Phases are usually identifiable because of adifference in density which causes gravitational separation. e.g. Ice floats on water, steam rises.
How to conclude size of elastomeric bearings ?
What is the head loss in 350 ft of 12 inch diameter 20 years old cast iron pipe carrying 1.2 MGD?
What is reciprocal ranging
Ceramics is what type of materials ? Answer: It is an insulators.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd