Calculate the modulus of elasticity of concrete, Civil Engineering

Assignment Help:

Calculate the Modulus of elasticity of concrete

A pre-stressed concrete beam, having a cross-section of 150 mm width and 400 mm depth, is used over a span of 8 m. Straight tendons. which are having a stress of 1200 N/mm2, are provided with a constant eccentricity of 60 mm. The sectional area of tendons is 120 mm2. What shall be the percentage increase in stress in the wires when the beam supports a live load of 5 kN/m over whole of its span. The density of concrete is 24 kN/ m3. Modulus of elasticity of concrete and steel may be taken as 36 kN/m2 and 210 kN/m2 respectively.

 


Related Discussions:- Calculate the modulus of elasticity of concrete

Major differences between sureties and security, Question What are majo...

Question What are major differences between sureties and security ? Answer During construction contracts, if a contractor fails to carry out works, employer would e

Bitumen, unit of kinematic viscosity

unit of kinematic viscosity

Chain, describe and sketch a survey chain

describe and sketch a survey chain

Soil classification - road materials, Soil Classification: Based on p...

Soil Classification: Based on particle size, the soils can be classified as under, adopting the IS soil classification system: 0.002   0.075   0.425   2.36     4.75

Transition curves - geometric design of roads, Transition Curves: If ...

Transition Curves: If a vehicle travelling on a straight enters a horizontal curve abruptly, it will cause shock and sway. To avoid this, it is customary to provide a transit

Breast walls, Breast Walls Needed to buttress uphill slopes. ...

Breast Walls Needed to buttress uphill slopes. Figure : Breast Check Walls Small retaining structures provided in series to arrest landslides. Gabio

Zones of smear around vertical drains, Zones of smear around vertical drain...

Zones of smear around vertical drains Smear zones are produced during the installation of vertical drains in that zone of soils surrounding the band drains are disturbed. Soil

Reason of skin reinforcement for deep beams, Question What is reason of sk...

Question What is reason of skin reinforcement for deep beams ? Answer In BS8110, it declares that secondary reinforcement have to be provided for beams greater than 750mm deep

Construction of concrete carriageway, Question If construction of conc...

Question If construction of concrete carriageway is carried out in summer, be capable of expansion joints be omitted? Answer If construction of concrete carriageway

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd