1. 130,000-yd3 of banked soil from a borrow pit is stockpiled before being trucked to the jobsite. The soil has 18% swell and shrinkage of 8%. The final volume of the compacted soil.
2. A 30-ft wide trapezoidal shaped earthen stream diversion channel is cut along a 2-mile stretch of rolling level terrain. The depth of the channel at station 52+25 is 8'-6" deep and at station 53+75 is 12'-6" deep. The bottom of the channel is a constant 12-ft wide and parallel with the surface cut. The volume of excavated material between the referenced stations.
Describe the two fundamental purposes of surveying
Question What is the sucker deck principle for changeable depth bridge decks ? Answer For a variable depth bridge deck, depth of continuous multi-span bridge deck is greate
What is moisture content for road work
explain re inforced brick work?
list the possible cause of errors
what is the importance of plagiarism in civil Engeneering
shear force and bending moment overhanging beams
Ask question #MiAAAAnimum 100 wordAs accepted#
A capital improvement project requires the installation of a property line fence along the 250-ft Northern boundary line.The decorative aluminum fence is constructed of posts space
A strip load of considerable length and 1.5 m width transmits a pressure of 150 kN/m 2 to the underlying soil. Verify the maximum principal stress at 0.75 m depth below the footin
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd