A local nursery greens uses 1560 bags of plant food annually. Green works 52 weeks per year. It costs $10 to place an order for plant food. The annual holding cost rate is $5 per bag. Lead time is one week.

(a) Calculate the economic order quantiyu
(b) Calculate the total annual costs
(c) Determine the reorder point


Related Discussions:- Calculate the economic order quantity

Describe worker adjustment and retraining notification act, Outline the pro...

Outline the provisions of the Worker Adjustment and Retraining Notification Act (WARN) of 1988 stating its rules, liabilities, and loopholes. Discuss the reasons why this act was c

Explain what is organizational culture, 1. What are personality traits? Def...

1. What are personality traits? Define and discuss the Big Five personality traits. Define and discuss other personality traits that affect managerial behaviour. 2. Explain Rike

Scope of production and operation management , Scope of Production and Oper...

Scope of Production and Operation Management Production management mainly associated with the factory management as the problem of production crept with the development of facto

Explain important to the project success, As a project manager was primaril...

As a project manager was primarily to make sure that project is done on schedule and under budget. Although these functions are very important, BRIEFLY mentioned what other functio

Explain repeat a signal form router to a workstation, On a 100BaseT Etherne...

On a 100BaseT Ethernet network, what is the maximum number of hubs that can be used to repeat a signal form a router to a workstation? a. 1 b. 2. c. 3 d. 4

Explain every business must be prepared to deal, Every business must be pre...

Every business must be prepared to deal with the global economy. True False

Explain justify a strategic information system, Why might it be difficult t...

Why might it be difficult to justify a strategic information system?

Explain concerns for product design in a dfma program, Name and briefly des...

Name and briefly describe the four primary concerns for product design in a DFMA program.

Determine the appropriate sample size, Determine the Appropriate Sample Siz...

Determine the Appropriate Sample Size The following work sampling data was collected from observing a retail assistant:  Activity

What are the benefits of the total productive maintenance, What are the ben...

What are the benefits of the total productive maintenance? Benefits of Total productive maintenance (TPM): • Less equipment downtime and main stoppages in production providi

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd