Calculate the diameter of the stockpile, Civil Engineering

Assignment Help:

1. On a 5-acre level terrain building site, an earthwork contractor has instructed her crew to strip and grub the topsoil of a 60,000-ft2 proposed building pad to a minus 2-ft sub-grade. The soil has a swell of 40% and an angle of repose at 30°. The diameter of the stockpile.

2. An earthwork contract was awarded to excavate and backfill the foundation of a proposed 75-ft by 75-ft office building.  The existing grade elevation is 37.00-ft while the sub-base for the below grade basement is 31.50-ft. The concrete contractor requires a 3-ft perimeter walkway in order to place the concrete formwork. Soil conditions are classified as OSHA Type B soils which require 1H:1V side slopes.The total volume (yd3) excavated.

 


Related Discussions:- Calculate the diameter of the stockpile

#title.cement factor, Aplease provide tables for each design mix and also t...

Aplease provide tables for each design mix and also the, high early strengh.l thanks

Systems approach to diagnose and solve the chronic w, systems approach to d...

systems approach to diagnose and solve the chronic water crisis in the city.

What do you mean by ozone test, Q. What do you mean by Ozone Test? Some...

Q. What do you mean by Ozone Test? Some research and studies determined that the ozone test was unnecessary as this affects only the surface layer.  In un-stretched rubber, ozo

Bedding of precast concrete paving units, Q. Sand layer vs. cement sand use...

Q. Sand layer vs. cement sand used as bedding of precast concrete paving units Cement sand is a mixture of sand and cement and it behaves as a cohesive mass once mixed. Usuall

Road location in dune areas, Road Location in Dune Areas: The followi...

Road Location in Dune Areas: The following principle should be observed in locating a road in dune areas : (a) Align a road where sand is covered by vegetation. (b) Sel

Phase, Each physical homogeneous type (solid, liquid orvapour) is a phase. ...

Each physical homogeneous type (solid, liquid orvapour) is a phase. Two or three phases may coexist.  e.g. Ice and water at 0 o C.  Mixtures of gases (e.g. Air) can only be

Sight distance - geometric design of roads, Sight Distance: Sight dis...

Sight Distance: Sight distance is the distance along a road at which a driver has a visibility of objects and can safely stop his vehicle or overtake another vehicle. Sto

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd