An engineer deposits an "X" amount every 6 months for 3 years so that she'll have $10,000 at the end of this period. The interest rate is 5% per year which is rebalanced every 6-month.  The amount deposited is most nearly:

Solution:  Determine the components and apply the equation:

n = 6 deposits     i = 2.5% per 6-month period 

F = $10,000(A/F, 2.5%, 6) = 0.15655 A = $1,565.50


Related Discussions:- Calculate the deposited amount - construction management

Slope, how to calculate a slope

how to calculate a slope

Explain the primary treatment for wastewater, Explain the Primary Treatment...

Explain the Primary Treatment for Wastewater Primary Treatment: to remove the pollutants that floats or settles. Typically 60% of suspended solids and 35% of BOD 5 are removed

Foundation, Explain briefly shallow foundation?

Explain briefly shallow foundation?

Simple stresses and strains, Simple stresses and strains: In this simp...

Simple stresses and strains: In this simple stresses and strains you have learnt the concepts of stress, strain, elastic modulus and the primary concepts in application to ana

Vibration in structures – resilient bearings, Q. Vibration in structures - ...

Q. Vibration in structures - resilient bearings? When railway tunnels are built close to buildings, ground-borne vibration is transmitted to buildingsthrough compression and sh

Explain the purpose of embedding puddle flange, Purpose of embedding puddle...

Purpose of embedding puddle flange inside the walls of closed valve chambers When valves are closed to stop water flow in a pipeline, a thrust is produced along the direction o

Casing has to be left in for mini-piles, Question What are thought in d...

Question What are thought in determining whether casings have to be left in for mini-piles ? Answer Contrary to most of pile design, design of min-piles is controlled

Shrinkage of concrete in prestressed members, Shrinkage of concrete in pres...

Shrinkage of concrete in prestressed members The shrinkage of concrete in prestressed members results in a shortening of ensioned wires and hence contributes to the loss of st

Hydraulics, A rectangular channel, 20ft wide is shown. The channel consists...

A rectangular channel, 20ft wide is shown. The channel consists of three reaches of different slopes. The channel has a roughness coefficient of n=0.015 and carries a discharge of

How is skin friction and point resistance of a pile computed, Describe the ...

Describe the basic difference in the bearing capacity computation of shallow and deep foundations. How are skin frictions and point resistance of a pile computed?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd