Calculate the deposited amount - construction management, Civil Engineering

Assignment Help:

An engineer deposits an "X" amount every 6 months for 3 years so that she'll have $10,000 at the end of this period. The interest rate is 5% per year which is rebalanced every 6-month.  The amount deposited is most nearly:

Solution:  Determine the components and apply the equation:

n = 6 deposits     i = 2.5% per 6-month period 

F = $10,000(A/F, 2.5%, 6) = 0.15655 A = $1,565.50


Related Discussions:- Calculate the deposited amount - construction management

Show the functions of wet wells, Q. Show the Functions of wet wells? We...

Q. Show the Functions of wet wells? Wetwells are designed to store provisionallysewage/water before it is pumped out. They are generally provided for sewage and stormwater pump

Stone tiles for construction material, Q. Stone tiles for construction mate...

Q. Stone tiles for construction material? For Public toilet bath rooms kitchen etc. we may be use stones tiles ( marble , kota stone , Polished Kuddapa stone or polished Dhura

Explain the wetted perimeter, Explain the Wetted Perimeter (P) The line...

Explain the Wetted Perimeter (P) The linear length of the interface between the fluid's cross-sectional plane edges in contact with the pipe or channel wall.

Raft foundation, after formation of the soil under raft some area around th...

after formation of the soil under raft some area around the lift pit for example will be on tipping shape and some column placed in the same area the question how we place the col

Scales and sludges, Discussscales and sludges. Writea note on internal trea...

Discussscales and sludges. Writea note on internal treatment of water

Explain energy grade line (egl), Explain Energy Grade Line (EGL) Graph ...

Explain Energy Grade Line (EGL) Graph of the sum of the potential, pressure and kinetic energies along a pipe or open channel. Energies are plotted along the y-axis above a dat

WATER RESOURCES SYSTEM PLANNING AND MANAGEMENT, Two crops are grown on land...

Two crops are grown on land of 20ha.The cost of raising crop 1 is 3unit/ha, while for crop 2 it is 1 unit/ha.The benefit from crop 1 is 5unit/ha and from crop 2, it is 2 unit/ha. A

Explain the classification of solid waste, Explain the Classification of So...

Explain the Classification of Solid Waste  Solid waste can be classified in several different ways.  Putrescible waste - Animal and Vegetable waste From Cooking and

HIGHWAY CONSTRUCTION & MAINTENANCE, what is the difference between feasibil...

what is the difference between feasibility study and traffic counting

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd