Calculate the daily standard production rate of equipment, Civil Engineering

Assignment Help:

Calculate the Daily Standard Production Rate of Equipment

An excavator with a bucket capacity of 3-yd3 has a standard operating cycle time of 40 seconds. The daily standard production rate of the excavator is most nearly:

 Solution: The daily standard production rate is as follows:   

Pday = (3yd3)(8hr)(3,600sec/hr)/(40sec)= 2,160 - yd3


Related Discussions:- Calculate the daily standard production rate of equipment

Proctor test for GSB material, what is the procedure for gsb proctor test f...

what is the procedure for gsb proctor test for matrial sampling for lab density

Classification of timber based on grading, Classification Based on Grading:...

Classification Based on Grading: IS 883-1970 classifies the structural timber into 3 grades-select grade, grade I and grade II. The classification is depend on, defects, permi

By which materials shank of a spur construct, Q. By which Materials Shank o...

Q. By which Materials Shank of a spur construct? Shank of a spur is constructed of sand core and its exposed faces are protected by stone pitching. The attack at nose is very h

Leveling, cooke''s reversable level

cooke''s reversable level

Millennium miles, Construction planning millennium miles

Construction planning millennium miles

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd