Calculate the cycle and production rate , Mechanical Engineering

Assignment Help:

Calculate the Cycle and Production Rate for Single-Machine Robotic Cell

Determine the cycle and production rate for a single-machine robotic cell for an 8-hr shift if the system availability is 85%. Also find out the percent utilization of machine and robot. On average, the machine takes 35 sec. to process a part. The other robot operation times are as follows:

Robot moves the shaft to the lathe                                            1.5 sec

Robot unloads the shaft from the lathe                                       0.5 sec

Robot picks a shaft from the conveyor                                        4.0 sec

Robot loads the shaft onto the lathe                                          1.0 sec

Robot moves the conveyor                                                        1.5 sec

Robot puts the shaft on the outgoing conveyor                            0.5 sec

Robot moves from the output conveyor to the input conveyor        5.0 sec

Description of Solution Approach

The total cycle time of 49 seconds is achieved by adding all of the activities of the robot by including the machining time and other related activities. The production rate is the reciprocal of cycle time. The production rate considering system availability is therefore

Production rate = 1 unit /49 sec. (60 s / min) (60 min / h) (  8 h/ shift) (0.85% uptime)

                       = 500 units per shift

Machine Utilization = Machine cycle time /Total cycle time

                           = 35/49 = 0.7142 or 71.42%

Robot utilization = Robot cycle time /Total cycle time

                        = 14/49 = 0.2857 or 28.57


Related Discussions:- Calculate the cycle and production rate

Hot and cold working, What is the difference between hot and cold working

What is the difference between hot and cold working

Strength of materials, simply supported beam subjected to point loads resul...

simply supported beam subjected to point loads results

Wrking cran, this is a problem for designing wrecking crane. there are 2 sc...

this is a problem for designing wrecking crane. there are 2 scenarios, one is when ball is held and one where its at maximum. i calculated the loads and now need to find the follow

What do you understand by inversion of mechanism, (a) What do you understan...

(a) What do you understand by Inversion of Mechanism ? Describe in detail the following : (i) Crank and Lever mechanism (ii) Double crank Mechanism (b) What are the condit

Evaluate the resultant of magnitude and direction of force, Evaluate the re...

Evaluate the resultant both in magnitude and direction of the four force acting on the body as shown in figure given below :

What do you understand by carburization, Q. What do you understand by Carbu...

Q. What do you understand by Carburization? Carburization is initiated by the adsorption of carbon in contact with the surface of the metal and may progress by diffusion along

Describe the terms refrigeration and air-conditioning, (a) Describe the ter...

(a) Describe the terms "Refrigeration" and "Air-conditioning". Determine the units of Refrigeration ? (b) The capacity of refrigeration is 400 TR when working between -6 o C and

Scanning electron microscope, 1- Explain the rationale of using a small WD ...

1- Explain the rationale of using a small WD to improve resolution. 2- In a tungsten SEM , Why does a high accelerating voltage provide the potential for higher resolution?  Why

Determine the process of modelling, Determine the process of modelling ...

Determine the process of modelling The process of modelling is much easier, if mathematical description of an object, or at least of part of an object may be applied. In the fi

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd