Calculate the cost to finance the construction project, Civil Engineering

Assignment Help:

A contractor is bidding a construction project that will take 12 months to complete. The terms of the bid provide that the owner will pay the Contractor one lump sum at the end of 14-months. The Contractor secured a bank loan with an interest rate of 1% per month on the outstanding balance. The Contractor will borrow $100,000 per month to reconcile costs at the end of months 1 through 12. Calculate the cost to finance the project that will be included as part of the bid.

Solution: At the end of month 12, the contractor will have borrowed 12 payments of $100,000 each.  The owner is scheduled to pay the contractor at the end of month 14 at which time the contractor will repay the bank.  Use the following equation to calculate the future value then extract the cost of financing the project:  

F = $100,000 (F/A, 1%, 12) (F/P, 1%, 2)   = $1,293,700

                                         Amount Borrowed =$1,200,000

                                    Amount of interest =$     93,700


Related Discussions:- Calculate the cost to finance the construction project

Surveying, earthen dam and gravity dam

earthen dam and gravity dam

Mr Kamal Saxena, What is WBM road. How it is constructed?

What is WBM road. How it is constructed?

Tests on stones, Tests on Stones To ascertain the needed properties of ...

Tests on Stones To ascertain the needed properties of stones, described tests can be conducted: A.   Crushing strength test B.   Water absorption test C.   Abrasion te

Poisson distribution function, Poisson distribution function: Let X I ...

Poisson distribution function: Let X I , X 2 , ..., X,& b e n independently and identically distributed random variables each having the same cdf F ( x ). What is the pdf of t

Ropeways, Ropeways: The system of ropeways consists of : (a) a cabl...

Ropeways: The system of ropeways consists of : (a) a cable suspended between towers, and (b) cars which move on the cable. Case with capacity upto 20 passengers is us

Levelling, difference between fly levelling and differential levelling

difference between fly levelling and differential levelling

Spatial structures loading, Spatial Structures Loading Dead load D...

Spatial Structures Loading Dead load Dead loads include the weight of permanent components such as elements and spheres weight, casing weight, false ceiling weight and uti

Zero energy building, This is our final year project can u suggest some tip...

This is our final year project can u suggest some tips to do well...

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd