A contractor is bidding a construction project that will take 12 months to complete. The terms of the bid provide that the owner will pay the Contractor one lump sum at the end of 14-months. The Contractor secured a bank loan with an interest rate of 1% per month on the outstanding balance. The Contractor will borrow $100,000 per month to reconcile costs at the end of months 1 through 12. Calculate the cost to finance the project that will be included as part of the bid.
Solution: At the end of month 12, the contractor will have borrowed 12 payments of $100,000 each. The owner is scheduled to pay the contractor at the end of month 14 at which time the contractor will repay the bank. Use the following equation to calculate the future value then extract the cost of financing the project:
F = $100,000 (F/A, 1%, 12) (F/P, 1%, 2) = $1,293,700
Amount Borrowed =$1,200,000
Amount of interest =$ 93,700
what is sheer stress on triangle beam.
Maintenance of bituminous roads
methods of damp proofing
advantages and disadvantages in single flemish bond
Light-weight Aggregate Prestressed Concrete The use of light-weight aggregate concrete for prestressed concrete construction is well established. The main advantage of light-
Maintenance of Water Bound Macadam Roads: The maintenance of water bound macadam surface consists of : filling potholes, ruts with additional material and adequately c
why do we use effective depth ''d'' in calculating the shear capacity of uncracked Concrete beam. If it is uncracked, why cant we use the full depth ''D''.
The material that have lowest resistivity is Answer: Silver is the material
Explain Coagulation Surface waters must be treated to remove turbidity, color and bacteria The traditional sand filtration is not sufficient in removing bacteria, viru
Describe the process of yielding and state the effect work hardening has on the yield point of mild steel
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd