Calculate the cost to finance the construction project, Civil Engineering

Assignment Help:

A contractor is bidding a construction project that will take 12 months to complete. The terms of the bid provide that the owner will pay the Contractor one lump sum at the end of 14-months. The Contractor secured a bank loan with an interest rate of 1% per month on the outstanding balance. The Contractor will borrow $100,000 per month to reconcile costs at the end of months 1 through 12. Calculate the cost to finance the project that will be included as part of the bid.

Solution: At the end of month 12, the contractor will have borrowed 12 payments of $100,000 each.  The owner is scheduled to pay the contractor at the end of month 14 at which time the contractor will repay the bank.  Use the following equation to calculate the future value then extract the cost of financing the project:  

F = $100,000 (F/A, 1%, 12) (F/P, 1%, 2)   = $1,293,700

                                         Amount Borrowed =$1,200,000

                                    Amount of interest =$     93,700


Related Discussions:- Calculate the cost to finance the construction project

Tests on limestones, Tests on Limestones Practical tests are made on li...

Tests on Limestones Practical tests are made on lime stones to decide their suitability is following:     i.       Physical tests    ii.        Heat test    iii.

Well foundation in bridges, what is the purpose of 6mm ms sheet for stainin...

what is the purpose of 6mm ms sheet for staining in various conditions at inner &outer of well

Surveying, what is compass survey and and its method

what is compass survey and and its method

Mechanics problem, i am facing some problem in solving the problem of elong...

i am facing some problem in solving the problem of elongation due to self weight suspended from fixed support in the conical bar

Important parts of road pavements, Important parts of road pavements: ...

Important parts of road pavements: Prime Coat : Application of a low viscosity bituminous binder over a granular base to fill up the voids. Tack Coat : Application of b

Find the size of the foundation required, A steam turbine with base 6 m × 3...

A steam turbine with base 6 m × 3.6 m weighs 10,000 kN. It is to be placed on a clay soil with c = 135 kN/m 2 . Find the size of the foundation needed if the factor of safety is to

Explain the well drawdown equations - ground water, Explain the Well Drawdo...

Explain the Well Drawdown Equations Watch the units, especially if you use log 10 or ln.    h 1 = aquifer thickness minus the drawdown (ft)  r 1 = distance from well (ft

Thermal coefficient, Thermal Coefficient Inside of the building's tempe...

Thermal Coefficient Inside of the building's temperature can increase or reduce the snow weight. As these types of structures normally cover a wide area and heating or even tur

Open foundation, what is savest foundation in the soft sanded earth

what is savest foundation in the soft sanded earth

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd