Calculate the amount put into saving account, Civil Engineering

Assignment Help:

Calculate the Amount put into Saving Account

If you want to have $60,000 in 10 years, the amount that should be put into a 6.0% (effective annual rate) savings account now is most nearly:

Solution: This problem could also be stated:  What is the equivalent present worth of $60,000 ten years from now if monthly money is worth 6% per year?

P = F (P/F, I, n) = $60,000(P/F, 6%, 10) = $60,000 * 0.5584 = $33,503.69

1018_Calculate the Amount put into Saving Account.png


Related Discussions:- Calculate the amount put into saving account

Compass survey, define compass survey and mention its objectives

define compass survey and mention its objectives

Plagiarism, what is the importance of plagiarism in civil Engeneering

what is the importance of plagiarism in civil Engeneering

Explain about the hydrogen embrittlement, Explain about the Hydrogen Embrit...

Explain about the Hydrogen Embrittlement As a result of the action of acids on high-tensile steels, liberation of hydrogen takes place. It penetrates into the steel surface an

What is material at site return, Q. What is Material at site Return? Th...

Q. What is Material at site Return? The authority is executive charge of a work should be responsible for holding in safe custody for controlling the consumption and to the ext

What is collocated network operation, What is Collocated network operation ...

What is Collocated network operation As wireless LANs become more popular, it is likely for two or more wireless LANs to operate in the similar area or in some area where inter

Pattern of load distribution of piles in such agreement, Question For a...

Question For a rigid pile cap with vertical piles at middle and raking piles at the sides, what is pattern of load distribution of piles in such agreement? Answer Becau

Slab, Design of one way slab, two way slab, circular slab, hollow slab step...

Design of one way slab, two way slab, circular slab, hollow slab step by step as ACI code 318-08, tnx

Traditional marine piling system of steel tubular pile, Question What i...

Question What is problem in traditional marine piling system of steel tubular pile with concrete infill and what are key possible remedial measures? Answer In design

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd